Peterson v. Pusey

86 N.E. 692, 237 Ill. 204
CourtIllinois Supreme Court
DecidedDecember 15, 1908
StatusPublished
Cited by14 cases

This text of 86 N.E. 692 (Peterson v. Pusey) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Peterson v. Pusey, 86 N.E. 692, 237 Ill. 204 (Ill. 1908).

Opinion

Mr. Justice Carter

delivered the opinion of the court:

Appellee recovered a judgment in the municipal court of Chicago for labor and material furnished appellant under a Verbal contract for digging trenches, furnishing material, doing the mason work and laying cut stone for the erection of a building in Chicago. Appellee claimed that the contract price finally agreed on was $4775, of which he was paid by appellant $3101.85, leaving a balance on the original of $1673.15. He also claims for extras $87, making the total amount claimed $1760.15, which, with inter-1 est, made the total amount of $1833.33 awarded by the verdict of the jury. This judgment was affirmed on appeal to the Appellate Court for the First District, and an appeal to this court followed.

At the time the case was called for trial appellee had not filed a joinder to the general issue or replication to the pleas of set-off. He was allowed by the trial court to file a joinder and replications at that time, over the objection of appellant, who then contended, as he does now, that he was entitled to have judgment entered for want of joinder on the plea of general issue and replications to the pleas of set-off. We think otherwise. Under our practice the trial court, in any action pending, may permit amendments to pleadings or proceedings, in form or substance, for the furtherance of justice. We think it would have been error for the trial court to have refused to allow appellee to file the pleadings in question. City of East St. Louis v. Thomas, 102 Ill. 453, is not in point.

Appellee claims that he had fully performed his agreement as to the work in question. There was no written contract, although there were some memoranda on a card which was introduced in evidence, and the plans and specifications in accordance with which the appellant claims the work was to be prosecuted. The defense was that appellee failed to comply with certain provisions called for by the plans and specifications and that the work was done in an unskillful manner, making the building permanently defective ; and further, that appellee could not recover for the alleged extras, as the appellant did not authorize the extra work. Appellee testified that he was told by appellant that one Stevens was to act as superintendent as to the work in question, and that he (appellee) should take orders from Stevens. This is denied by both appellant and Stevens.

Appellant moved, at the close of plaintiff’s evidence and again at the close of all the evidence, that the court direct a verdict for defendant, both of which motions were overruled and exceptions duly taken.

Whether the evidence justified the amount of the verdict; whether Stevens was authorized to act as superintendent; whether the contract was performed in accordance with the agreement, in a workmanlike and skillful manner; whether the work was accepted by appellant after its completion, (as contended by appellee but denied by appellant,) and other questions of fact urged in the appellant’s brief, are all controverted, and as there is evidence in the record tending to support the appellee’s contentions on all these points, the judgment of the trial court on the verdict, which has been affirmed by the judgment of the Appellate Court, conclusively settles those controverted questions of fact in this court. We have nothing to do with the preponderance or weight of the evidence. (Blakeslee’s Express Co. v. Ford, 215 Ill. 230; Chicago and Eastern Illinois Railroad Co. v. Snedaker, 223 id. 395; Donnelly v. Chicago City Railway Co. 235 id. 35.) This court can only inquire whether the rules of law were properly followed in the trial court in the admission of evidence, the giving of instructions, and the like.

Counsel for the appellant earnestly insists that recovery could not be had under the declaration filed in this case, as the contract was not fully performed as originally agreed. The declaration had two special counts alleging the oral contract, and the common counts. It has been frequently held by this court that where a contract has been performed and it only remains for the contract price for labor and material to be paid, recovery may be had under the common counts. (Concord Apartment House Co. v. O’Brien, 228 Ill. 360; Expanded Metal Fireproofing Co. v. Boyce, 233 id. 284.) As we have said, there was no written agreement, and it is not contended that by oral agreement any architect’s certificate 'was required to be given. Even though there were slight variations from the agreement as originally entered into on some portions of the work, as contended for by appellant, we think, under the authorities just cited, appellee could still recover under the common counts, as he testified that the work was performed in accordance with the agreement.

What we have said with reference to recovery under the common counts we think practically disposes of all objections to the admission or exclusion of evidence raised by appellant. It is sufficient to say we find no reversible error on those questions.

Appellant argues that an impeaching instruction given for the appellee was erroneous because it omitted the word “willfully” in the clause, “if you believe any witness has knowingly testified falsely to any material issue.” While the words “knowingly” and “willfully” are usually coupled together in such an instruction, if a person knowingly testified falsely we think he must be held to have willfully testified falsely. The two words are equivalents. (Fry v. Hubner, 57 Pac. Rep.—Ore.—420.) “Intentionally” is given as one of the meanings of each of these words. (Standard Diet.) This court has held that by a willful violation of the law is meant a violation of its provisions knowingly and deliberately. (Catlett v. Young, 143 Ill. 74.) We have also held that if a person consciously omitted to comply with a statutory -requirement this constituted a willful violation. (Spring Valley Coal Co. v. Greig, 226 Ill. 511.) We do not consider this instruction erroneous.

Appellant also complains of the second instruction given for appellee, which stated that substantial compliance with the terms of the agreement was all that the law requires, arguing that this instruction, considered by itself, submitted to the jury the question of performance without telling them what was a substantial compliance, and that therefore, under Estep v. Fenton, 66 Ill. 467, this was reversible error. This instruction did not direct a verdict, and several of the instructions given for appellant plainly set forth what was meant by a substantial compliance with the contract. Instructions must be considered as a series, and taking them together we do not think there was any possibility of the jury being misled on this point. Helbig v. Citizens’ Ins. Co. 234 Ill. 251.

Appellant, while admitting that this court in Keeler v. Herr, 157 Ill. 57, laid down the rule that a substantial compliance was sufficient, and that where there has been no willful departure from the terms of the contract and no omission in essential points and it has been honestly and faithfully performed in its material and substantial particulars, recovery can be had even though there have been technical or unimportant omissions or defects, and that we have sanctioned that ruling in Shepard v. Mills, 173 Ill. 223, Evans v. Howell, 211 id. 85, Bauer v. Hindley, 222 id. 319, Concord Apartment House Co. v. O’Brien, supra, and other decisions, argues that the Keeler v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kelley v. Call
57 N.E.2d 501 (Appellate Court of Illinois, 1944)
Budek v. City of Chicago
279 Ill. App. 410 (Appellate Court of Illinois, 1935)
Kleihege v. State
188 N.E. 786 (Indiana Supreme Court, 1934)
Edward Edinger Co. v. Willis
260 Ill. App. 106 (Appellate Court of Illinois, 1931)
People v. O'Brien
251 Ill. App. 314 (Appellate Court of Illinois, 1929)
Hardy v. Dobler
248 Ill. App. 361 (Appellate Court of Illinois, 1928)
Erikson v. Ward
266 Ill. 259 (Illinois Supreme Court, 1914)
Connelly v. Wallin
181 Ill. App. 212 (Appellate Court of Illinois, 1913)
Mengelkamp v. Consolidated Coal Co.
173 Ill. App. 370 (Appellate Court of Illinois, 1912)
Krumholz v. Tobias
167 Ill. App. 553 (Appellate Court of Illinois, 1912)
Lawrence v. Village of Channahon
157 Ill. App. 560 (Appellate Court of Illinois, 1910)
Hamilton v. Chaffee
158 Ill. App. 54 (Appellate Court of Illinois, 1910)
Dobbles v. Electric Coal Co.
158 Ill. App. 357 (Appellate Court of Illinois, 1910)
Peebles v. O'Gara Coal Co.
88 N.E. 166 (Illinois Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
86 N.E. 692, 237 Ill. 204, Counsel Stack Legal Research, https://law.counselstack.com/opinion/peterson-v-pusey-ill-1908.