Barker's Inc. v. B.D.J. Development Co.

308 N.W.2d 78, 1981 Iowa Sup. LEXIS 998
Supreme Court of Iowa·Decided July 15, 1981·No. 65178·Published·Cited by 5 cases

Opinion

UHLENHOPP, Justice.

This appeal deals principally with priority as between a mechanic’s lien and a mortgage.

Jim Reid as representative of B.D.J. Development Company (comprised of B ill Yansky, Donnie Shull, and Jim Reid) contacted Dave Schmitt as owner of Dave Schmitt Construction Company in December 1977. BDJ planned to subdivide an area for residential housing in the City of North Liberty, and solicited a bid from Schmitt for the installation of sanitary sewer, storm sewer, and water main systems. Schmitt examined plans in February 1978, and on March 9 made a proposal which was accepted.

About March 1, 1978, Barker’s, Inc. and BDJ orally agreed that Barker’s would do grading work on the land at a later date.

On March 4 and 16, 1978, Yansky, Shull, and Reid purchased the land to be used in the subdivision. The deeds were recorded March 20, 1978.

The land was subdivided, and on March 31 the three owners and their wives gave a mortgage to uniBank & Trust Company for essentially the same land they had purchased.

Schmitt began work about April 4, 1978. North Liberty approved the subdivision on April 11, and a preconstruction meeting of the contractors was held April 12. On April 14, uniBank’s mortgage was recorded. At that time a substantial portion of the sanitary sewer had been installed.

On April 27, 1978, Yansky, Shull, and Reid and their wives conveyed the mortgaged land to BDJ, a corporation. The deed was recorded on May 12.

Schmitt finished work on May 16, 1978. Metro Pavers, Inc. installed storm water catch basins from May 22 to 27. Barker’s did grading work from June 8 to 23. Schmitt did additional work on August 11 and 12, and Barker’s did further grading from August 17 to 25. River Products Company provided rock for the road sub-grade on August 23, and Metro Pavers paved and backfilled from August 23 to October 12.

Barker’s filed its mechanic’s lien against BDJ and Yansky, Shull, and Reid on October 17,1978; Metro Pavers filed on October 25; and River Products filed on December 1. Metro Pavers and River Products did not press their claims, and we give those parties no further consideration.

I. The trial court held that Barker’s lien had priority over uniBank’s mortgage. This result was reached by making Barker’s lien effective for priority purposes against uniBank’s mortgage from the first date work was done by anyone on the project. The court so interpreted “original commencement of the work” in section 572.-18, The Code 1977. That section provides (emphasis added):

Mechanics’ liens shall be preferred to all other liens which may attach to or upon any building or improvement and to the land upon which it is situated, except *80 liens of record prior to the time of the original commencement of the work or improvements; but the rights of purchasers, encumbrancers, and other persons who acquire interests in good faith and for a valuable consideration, and without notice, after the expiration of the time for filing claims for such liens, shall be prior to the claims of all contractors or subcontractors who have not, at the dates such rights and interests were acquired, filed their claims for such liens.

The court’s interpretation was crucial to the result; although Schmitt began work on April 4 (after the mortgage was executed on March 31 but before it was recorded on April 14), Barker’s did not begin work until June 8. If Barker’s lien is to have priority over the uniBank’s mortgage, the priority must be predicated on the date of original commencement of work on the project as a whole.

Unibank appeals, asserting the trial court erred in holding that liens for subsequent work can be tacked to the first work done by any party on the project. The bank urges the priority of the lien of each mechanic dates from the first work done by that mechanic, as against a recorded mortgage.

The trial court relied on Neilson v. Iowa Eastern Railroad, 44 Iowa 71 (1876). The facts of that case are surprisingly similar to these. There as here work commenced on a project prior to recordation of a mortgage. The work for which the mechanic’s lien was claimed, however, did not begin until after the mortgage was recorded. The applicable statute had previously read, “lien upon the land, including the building ..., against all except incumbrances by judgment rendered and by instrument recorded before commencement of the work or the furnishing of the materials.” It had been revised to read, “commencement of such building, erection or other improvement.” Id. at 73-74. The latter language is similar to the language of present section 572.18. The Neilson case contains this analysis:

Such was the law from 1851 to 1860. By section 1853 of the Revision, the mechanic’s lien is made to attach from the commencement of “the building, erection or other improvement.” The language of this statute differs materially from the former. The question in this case is: does it mean the same thing? We are of the opinion that it does not. If the mechanic’s lien is to attach only from the commencement of the work for which it is claimed, why should language be abandoned which expressed that idea unequivocally for other language which does not? Indeed, the language of the Revision cannot be made to express that idea by any proper rules of construction. It provides that the lien shall attach from the commencement of the building. According to the construction contended for by the in-tervenors, it does not necessarily attach from the commencement of the building. It does so only when the commencement of the particular work in question happens to coincide with the commencement of the building. According to that construction, the words “building” and “erection” have no force in the statute. But the rules of construction require that some force shall be given to every word, if it can be done consistently.
The idea that the mechanic’s lien attaches only from the commencement of his particular work, is wrought out through the supposition that the word “improvement,” as used in the statute, denotes the several distinct and successive jobs of work performed by the different mechanics. But this construction is precluded by the use of the word “other” before “improvement.” The lien is to attach from the commencement of “the building, erection, or other improvement.” The statute implies that a building is an improvement, and that an erection is an improvement, and that there may be others still. We understand by “other improvement” the result of mechanical labor or materials furnished other than buildings or erections upon real estate.

Id. at 73-74. The Neilson court went on to say:

*81

Free access — add to your briefcase to read the full text and ask questions with AI

Barker's Inc. v. B.D.J. Development Co., 308 N.W.2d 78, 1981 Iowa Sup. LEXIS 998 (iowa 1981).

308 N.W.2d 78 (Barker's Inc. v. B.D.J. Development Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Midland Savings Bank FSB v. Stewart Group, LC
533 N.W.2d 191 (Supreme Court of Iowa, 1995)
Valley Federal Savings & Loan Ass'n v. T-Bird Home Centers, Inc.
741 P.2d 826 (New Mexico Supreme Court, 1987)
Merv E. Hilpipre Auction Co. v. Solon State Bank
343 N.W.2d 452 (Supreme Court of Iowa, 1984)