Diversified Mortgage Investors v. Gepada, Inc.

401 F. Supp. 682, 1975 U.S. Dist. LEXIS 15965
CourtDistrict Court, S.D. Iowa
DecidedSeptember 29, 1975
DocketCiv. 74-33-W
StatusPublished
Cited by2 cases

This text of 401 F. Supp. 682 (Diversified Mortgage Investors v. Gepada, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Diversified Mortgage Investors v. Gepada, Inc., 401 F. Supp. 682, 1975 U.S. Dist. LEXIS 15965 (S.D. Iowa 1975).

Opinion

ORDER

HANSON, Chief Judge.

This action was commenced by plaintiff’s filing of a “complaint for foreclosure of real estate mortgage” on August 21, 1974. The suit seeks foreclosure of a real estate mortgage given by defendant-mortgagor, Gepada, Inc., to the National Bank of Des Moines, which in turn assigned the mortgage to Diversified Mortgage Investors (DMI), the plaintiff herein. DMI is a Massachusetts business trust. Defendants are various entities from states other than Massachusetts. Since the amount in controversy exceeds $10,000, this Court has jurisdiction under 28 U.S.C. § 1332(a) (1970).

The instant controversy involves a matter of priorities between two parties: DMI, the mortgage holder, and the Andersen Construction Company, which claims rights under a mechanic’s lien.

FINDINGS OF FACT

1. On June 20, 1972, the Andersen Construction Company of Council Bluffs, Iowa (Andersen Construction) entered into a contract with Gepada, Inc., an Iowa corporation, for the construction of a Ramada Inn near the intersection of 27th Avenue and 24th Street in Council Bluffs. This contract was in the amount *684 of nine hundred sixty-eight thousand dollars ($968,000) and was subject to renegotiation after July 31, 1972, as notice to proceed had not been given by Gepada on or before that date.

2. Herbert Andersen is the president of the Andersen Construction Company. Mr. Andersen was the company’s representative in the contract negotiations with Gepada.

3. The land on which the motel in question was to be built was undeveloped prior to the summer of 1972. As of August 7, 1972, no work had been done on the lot by Andersen. It was weed-covered, and contained a few trees. Surrounding lots were agricultural, with corn and other crops planted on them.

4. On August 7, 1972, Andersen visited the lot with one F. M. Warburton, president of Gepada, Inc. Mr. Andersen was told by Mr. Warburton that financing for the motel project was imminent. Their visual inspection of the lot revealed that fill would be needed to raise its elevation for proper drainage to the street. Andersen was directed to determine how much fill would be necessary, and to estimate its cost.

5. Approximately two weeks later, a farmer was engaged by Andersen to mow the weeds which were covering the lot. After removal of the weeds, Andersen visited the site and spent approximately four hours determining existing ground elevations. From these figures, a plat was prepared from which estimates of needed fill were made. These steps were completed by the first week of September, 1972.

6. Subsequent to Andersen’s survey of the lot for purposes of the plat, he engaged Petry and Sons Contractors to strip six inches topsoil, weeds, and vegetation from the lot. This precaution was to prevent any settling of the filled land. The job took two days. Some dispute exists between the parties as to when this stripping took place. It is the testimony of Andersen that it was done in early September, and at the latest before September 21, 1972. The Court finds from a preponderance of the evidence that the soil was stripped sometime before September 25, 1972.

7. On September 21, 1972, Andersen Construction and Gepada signed a revised contract. This document was identical to the June 20th contract, with these exceptions: the contract price was increased to one million fifteen thousand seventeen dollars ($1,015,017.00); grade and fill requirements were increased; a standby propane fuel system was added; the thickness of some asphalt paving was increased; and roof specifications were changed.

8. The mortgage on the property involved herein was given by Gepada to the National Bank of Des Moines on September 22, 1972. The mortgage was recorded on Monday, September 25, 1972 in the Pottawattamie County Recorder’s office, and was assigned to plaintiff DMI on December 7, 1973.

9. A formal groundbreaking for the motel was held on September 26, 1972. Andersen began actual work on the footings for the building on September 28, 1972.

10. On April 11, 1974, Andersen filed a mechanic’s lien against the mortgaged premises with the Clerk of the Pottawattamie County District Court.

CONCLUSIONS OF LAW

The legal question presented by this case is a narrow one. Section 572.18, Code of Iowa (1975), provides that:

Mechanics’ liens shall be preferred to all other liens which may attach to or upon any building or improvement and to the land upon which it is situated, except liens of record prior to the time of the original commencement of the work or improvements . (emphasis added).

Plaintiff’s mortgage was recorded on September 25, 1972; the issue is simply whether the Andersen Construction Com-, pany’s “original commencement of the work” of building a motel occurred before September 25th. If it did, Ander *685 sen’s mechanic’s lien takes priority over DMI’s mortgage; if it did not, the mortgage is prior. Because of the alleged default of Gepada, Inc., DMI is seeking a sum in excess of $1,500,000 as the amount due under the mortgage. Andersen’s mechanic’s lien is in the amount of $67,-317.75.

The parties agree that the question of whether Andersen “commenced” work prior to September 25, 1972, is a matter of Iowa law. The Court has been unable to find any recent Iowa decisions which shed light on this matter of statutory interpretation. The Court’s research does indicate, however, that two older Iowa rulings in this area are stiil viable. In Conrad & Ewinger v. Starr, 50 Iowa 470 (1879), the Iowa Supreme Court endorsed the view “that the commencement of a building under the mechanic’s lien law is the first labor done on the ground, which is made the foundation of the building, and is to form part of the work suitable and necessary for its construction.” Id. at 481. This statement was reaffirmed in Kiene v. Hodge, 90 Iowa 212, 215, 57 N.W. 717 (1894). See also New Hampshire Savings Bank v. Varner, 216 F. 721, 727 (8th Cir. 1914), aff'd, 240 U.S. 617, 36 S.Ct. 409, 60 L.Ed. 828 (1916).

The Kiene and Conrad cases place Iowa with those states that adhere to the following rule regarding the accrual of a mechanic’s lien:

The commencement of the building or improvement within the meaning of mechanics’ liens statutes is the visible commencement of actual operations on the ground for the erection of the building, the doing of some work or labor on the ground, such as beginning to excavate for the foundation or the basement or cellar, walling the cellar, or work of a like description, which everyone can readily see and recognize as the commencement of a building, and which is done with the intention and purpose then formed to continue the work until the completion of the building.

In re Anderson’s Estate, 244 Iowa 325, 56 N.W.2d 913

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Zachman Homes, Inc.
47 B.R. 496 (D. Minnesota, 1984)
Barker's Inc. v. B.D.J. Development Co.
308 N.W.2d 78 (Supreme Court of Iowa, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
401 F. Supp. 682, 1975 U.S. Dist. LEXIS 15965, Counsel Stack Legal Research, https://law.counselstack.com/opinion/diversified-mortgage-investors-v-gepada-inc-iasd-1975.