D. Construction, Inc. v. Commonwealth Edison Co.

CourtAppellate Court of Illinois
DecidedMarch 31, 2026
Docket1-24-0901
StatusUnpublished

This text of D. Construction, Inc. v. Commonwealth Edison Co. (D. Construction, Inc. v. Commonwealth Edison Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D. Construction, Inc. v. Commonwealth Edison Co., (Ill. Ct. App. 2026).

Opinion

2026 IL App (1st) 240901-U Fourth Division Filed March 31, 2026 No. 1-24-0901

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).

IN THE APPELLATE COURT OF ILLINOIS FIRST DISTRICT

) D. CONSTRUCTION, INC., ) Appeal from the Plaintiff-Appellant and Cross-Appellee, ) Circuit Court of Cook County ) v. ) No. 2019 L 009852 ) COMMONWEALTH EDISON COMPANY, ) The Honorable Daniel J. Kubasiak, Defendant-Appellee and Cross-Appellant. ) Judge, presiding. )

JUSTICE OCASIO delivered the judgment of the court. Presiding Justice Navarro and Justice Lyle concurred in the judgment.

ORDER

¶1 Held: We affirm the circuit court’s order granting dismissal of the defendant’s claim for early completion incentives, its order granting partial summary judgment, and its order granting the defendant’s motion for directed finding. We also affirm the circuit court’s post-trial order; however, we reverse the grant of prejudgment interest.

¶2 The plaintiff, D. Construction, Inc., sued the defendant, Commonwealth Edison Company

(“ComEd”), following the termination of contracts between the parties. Prior to trial, the circuit

court dismissed one of D. Construction’s claims, and following a bench trial, the court found that

D. Construction was entitled to partial recovery on Count I of its complaint and no recovery on

Counts II and III. The court also found in favor of ComEd on its counterclaims. D. Construction No. 1-24-0901

appeals. ComEd cross-appeals, arguing the court erred in determining prejudgment interest. For

the reasons outlined below, we affirm in part and reverse in part.

¶3 I. BACKGROUND

¶4 D. Construction provided construction services to Exelon Generation Company, LLC

(“Exelon Generation”). In 2014, D. Construction submitted bids, which included ComEd Perfect

Commerce Event 6130 (“Event 6130”) and request for proposal 029 (“Event 029”), and began

providing construction services for ComEd. Exelon Generation and ComEd were subsidiaries of

Exelon Corporation (“Exelon”). D. Construction performed general civil work and facilities

enhance program work (“FEP Work”) for ComEd. Civil work entailed foundation work, substation

work, yard stone, and drill shafts. The FEP Work included security upgrades such as fencing,

technology, and lighting.

¶5 Civil work performed by D. Construction was governed by two successive sets of master

terms and conditions and blanket master contracts. Civil work performed before December 31,

2017 was governed by the Master Terms and Conditions Contract signed on April 24, 2014 (“2014

Master Terms”) and the blanket master contract signed December 10, 2014. Civil work performed

on or after January 1, 2018 was governed by a new Master Terms and Conditions Contract signed

on August 11, 2017 (“2017 Master Terms,” collectively together with the 2014 Master Terms

“Master Terms”) and a blanket master contract signed on January 26, 2018. FEP Work performed

by D. Construction was governed by individual contracts for each project. The aforementioned

contracts will be referred to herein collectively as the “Agreements.”

¶6 The Agreements between the parties included “volume discounts,” which were discounts

ComEd received based on a percentage of ComEd’s annual spending on work performed by

D. Construction. Civil work and FEP work were subject to different volume discounts tiers. There

were no volume discounts for work done for Exelon Generation. ComEd could also receive prompt

payment discounts by paying D. Construction’s invoices within 10 days after receipt.

-2- No. 1-24-0901

¶7 In April 2018, ComEd terminated its Agreements with D. Construction for convenience,

pursuant to the Agreements’ terms. At the time, there were numerous uncompleted projects.

¶8 Revenew International, LLC (“Revenew”) performed audits of the parties’ invoices. In 2012,

Revenew audited D. Construction’s work for Exelon Generation from 2010-2012. In 2016,

Revenew audited D. Construction’s work for Exelon Generation and ComEd from 2014-2015. In

2018, Revenew audited D. Construction’s work for ComEd from 2015-2018.

¶9 In its second amended complaint, D. Construction raised four breach of contract claims.

Count I alleged that ComEd underestimated the earned value,—the amount it owed

D. Construction for work completed at the time of termination—for seven projects. Count II

alleged that D. Construction was entitled to a refund for volume discounts given to ComEd. Count

III alleged that D. Construction was entitled to prompt payment discounts. Count IV alleged that

D. Construction was entitled to early completion incentives. ComEd filed a counterclaim seeking

to recover amounts it overpaid on two projects and volume discounts owed by D. Construction for

2017 and 2018.

¶ 10 ComEd filed a motion to dismiss D. Construction’s second amended complaint. In April

2021, the circuit court dismissed count IV of D. Construction’s second amended complaint. The

court found that the Master Terms and FEP purchase orders’ plain language did not include early

completion incentives.

¶ 11 Prior to trial, ComEd filed a motion for partial summary judgment. In relevant part, ComEd

argued that the terms of the Agreements set forth the earned value calculation for the projects at

issue. On December 1, 2023, the circuit court granted ComEd’s motion for summary judgment as

to the contractual obligations to calculate damages under Count I. The court found that sections

18.4.2 and 18.5 of the Master Terms were clear and unambiguous and controlled the calculation

of damages.

¶ 12 A four-day long bench trial was held for D. Construction’s remaining claims and ComEd’s

counterclaims. Matt LaPoint, a project manager and structural designer for D. Construction,

testified he was a project manager for the projects in dispute and he was involved in the bidding

-3- No. 1-24-0901

for those projects. During the bidding process, D. Construction completed unit pricing sheets,

which had line items for each task to be completed during a project. The aggregate sum of these

line items became the lump sum total for a project. LaPoint testified that D. Construction’s bids

were part of the Agreements between the parties as the Agreements would reference the bid

documents and the bid documents were attached as an exhibit to the contracts. LaPoint testified

that the civil work was governed by the blanket contracts and the Master Terms. The FEP work

was performed under different contracts.

¶ 13 After termination of the Agreements, D. Construction determined the earned value by going

through each line item on the unit pricing sheet. LaPoint testified that if it was finite calculation,

D. Construction would apply that to the quantities performed in order to get a completion

percentage for each line item. If the calculation “was a little less clear,” D. Construction, along

with its subcontractors and onsite managers, would perform final onsite walkdowns for work

performed. LaPoint prepared the earned value calculations for the project. In order to determine

the earned value, he went down each line item, identified what and how much was done, and what

the agreed price was. LaPoint’s earned value calculations for each project was admitted into

evidence.

¶ 14 At the time the Agreements were terminated, the Itasca Fencing Project was partially

completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

1472 N. Milwaukee, LTD. v. Feinerman
2013 IL App (1st) 121191 (Appellate Court of Illinois, 2013)
Razor v. Hyundai Motor America
854 N.E.2d 607 (Illinois Supreme Court, 2006)
Provident Federal Savings & Loan Ass'n v. Realty Centre, Ltd.
454 N.E.2d 249 (Illinois Supreme Court, 1983)
A.W. Wendell & Sons, Inc. v. Qazi
626 N.E.2d 280 (Appellate Court of Illinois, 1993)
Kokinis v. Kotrich
407 N.E.2d 43 (Illinois Supreme Court, 1980)
Berg & Associates, Inc. v. Nelsen Steel & Wire Co.
580 N.E.2d 1198 (Appellate Court of Illinois, 1991)
Gallagher v. Lenart
874 N.E.2d 43 (Illinois Supreme Court, 2007)
General Dynamics Corp. v. Zion State Bank & Trust Co.
427 N.E.2d 131 (Illinois Supreme Court, 1981)
Arneson v. BD. OF TR., McKENDREE COLLEGE
569 N.E.2d 252 (Appellate Court of Illinois, 1991)
Gonet v. Chicago & North Western Transportation Co.
552 N.E.2d 1224 (Appellate Court of Illinois, 1990)
Kehoe v. WILDMAN, HARROLD, ALLEN AND DIXON
899 N.E.2d 1177 (Appellate Court of Illinois, 2008)
Marshall v. Burger King Corp.
856 N.E.2d 1048 (Illinois Supreme Court, 2006)
Tri-G, Inc. v. Burke, Bosselman & Weaver
856 N.E.2d 389 (Illinois Supreme Court, 2006)
Chicago's Pizza, Inc. v. Chicago's Pizza Franchise Limited USA
893 N.E.2d 981 (Appellate Court of Illinois, 2008)
Liberty Mutual Insurance v. Zambole
491 N.E.2d 132 (Appellate Court of Illinois, 1986)
R & R Construction Co. v. Junior College District No. 529
370 N.E.2d 599 (Appellate Court of Illinois, 1977)
Duncan v. Cannon
561 N.E.2d 1147 (Appellate Court of Illinois, 1990)
Alpha School Bus Co., Inc. v. Wagner
910 N.E.2d 1134 (Appellate Court of Illinois, 2009)
Snelson v. Kamm
787 N.E.2d 796 (Illinois Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
D. Construction, Inc. v. Commonwealth Edison Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-construction-inc-v-commonwealth-edison-co-illappct-2026.