D. Construction, Inc. v. Commonwealth Edison Co.

Appellate Court of Illinois·Decided March 31, 2026·No. 1-24-0901·Unpublished

Opinion

2026 IL App (1st) 240901-U Fourth Division

Filed March 31, 2026

No. 1-24-0901

NOTICE: This order was filed under Supreme Court Rule 23 and is not precedent except in the limited circumstances allowed under Rule 23(e)(1).

IN THE

APPELLATE COURT OF ILLINOIS FIRST DISTRICT

)

D. CONSTRUCTION, INC., ) Appeal from the Plaintiff-Appellant and Cross-Appellee, ) Circuit Court of Cook County )

v. ) No. 2019 L 009852 )

COMMONWEALTH EDISON COMPANY, ) The Honorable Daniel J. Kubasiak, Defendant-Appellee and Cross-Appellant. ) Judge, presiding.

)

JUSTICE OCASIO delivered the judgment of the court.

Presiding Justice Navarro and Justice Lyle concurred in the judgment.

ORDER

¶1 Held: We affirm the circuit court’s order granting dismissal of the defendant’s claim for early completion incentives, its order granting partial summary judgment, and its order granting the defendant’s motion for directed finding. We also affirm the circuit court’s post-trial order; however, we reverse the grant of prejudgment interest.

¶2 The plaintiff, D. Construction, Inc., sued the defendant, Commonwealth Edison Company (“ComEd”), following the termination of contracts between the parties. Prior to trial, the circuit court dismissed one of D. Construction’s claims, and following a bench trial, the court found that D. Construction was entitled to partial recovery on Count I of its complaint and no recovery on Counts II and III. The court also found in favor of ComEd on its counterclaims. D. Construction

appeals. ComEd cross-appeals, arguing the court erred in determining prejudgment interest. For the reasons outlined below, we affirm in part and reverse in part.

¶3 I. BACKGROUND

¶4 D. Construction provided construction services to Exelon Generation Company, LLC (“Exelon Generation”). In 2014, D. Construction submitted bids, which included ComEd Perfect Commerce Event 6130 (“Event 6130”) and request for proposal 029 (“Event 029”), and began providing construction services for ComEd. Exelon Generation and ComEd were subsidiaries of Exelon Corporation (“Exelon”). D. Construction performed general civil work and facilities enhance program work (“FEP Work”) for ComEd. Civil work entailed foundation work, substation work, yard stone, and drill shafts. The FEP Work included security upgrades such as fencing, technology, and lighting.

¶5 Civil work performed by D. Construction was governed by two successive sets of master terms and conditions and blanket master contracts. Civil work performed before December 31, 2017 was governed by the Master Terms and Conditions Contract signed on April 24, 2014 (“2014 Master Terms”) and the blanket master contract signed December 10, 2014. Civil work performed on or after January 1, 2018 was governed by a new Master Terms and Conditions Contract signed on August 11, 2017 (“2017 Master Terms,” collectively together with the 2014 Master Terms “Master Terms”) and a blanket master contract signed on January 26, 2018. FEP Work performed by D. Construction was governed by individual contracts for each project. The aforementioned contracts will be referred to herein collectively as the “Agreements.”

¶6 The Agreements between the parties included “volume discounts,” which were discounts ComEd received based on a percentage of ComEd’s annual spending on work performed by D. Construction. Civil work and FEP work were subject to different volume discounts tiers. There were no volume discounts for work done for Exelon Generation. ComEd could also receive prompt payment discounts by paying D. Construction’s invoices within 10 days after receipt.

¶7 In April 2018, ComEd terminated its Agreements with D. Construction for convenience, pursuant to the Agreements’ terms. At the time, there were numerous uncompleted projects.

¶8 Revenew International, LLC (“Revenew”) performed audits of the parties’ invoices. In 2012, Revenew audited D. Construction’s work for Exelon Generation from 2010-2012. In 2016, Revenew audited D. Construction’s work for Exelon Generation and ComEd from 2014-2015. In 2018, Revenew audited D. Construction’s work for ComEd from 2015-2018.

¶9 In its second amended complaint, D. Construction raised four breach of contract claims. Count I alleged that ComEd underestimated the earned value,—the amount it owed D. Construction for work completed at the time of termination—for seven projects. Count II alleged that D. Construction was entitled to a refund for volume discounts given to ComEd. Count III alleged that D. Construction was entitled to prompt payment discounts. Count IV alleged that D. Construction was entitled to early completion incentives. ComEd filed a counterclaim seeking to recover amounts it overpaid on two projects and volume discounts owed by D. Construction for 2017 and 2018.

¶ 10 ComEd filed a motion to dismiss D. Construction’s second amended complaint. In April 2021, the circuit court dismissed count IV of D. Construction’s second amended complaint. The court found that the Master Terms and FEP purchase orders’ plain language did not include early completion incentives.

¶ 11 Prior to trial, ComEd filed a motion for partial summary judgment. In relevant part, ComEd argued that the terms of the Agreements set forth the earned value calculation for the projects at issue. On December 1, 2023, the circuit court granted ComEd’s motion for summary judgment as to the contractual obligations to calculate damages under Count I. The court found that sections 18.4.2 and 18.5 of the Master Terms were clear and unambiguous and controlled the calculation of damages.

¶ 12 A four-day long bench trial was held for D. Construction’s remaining claims and ComEd’s counterclaims. Matt LaPoint, a project manager and structural designer for D. Construction, testified he was a project manager for the projects in dispute and he was involved in the bidding

for those projects. During the bidding process, D. Construction completed unit pricing sheets, which had line items for each task to be completed during a project. The aggregate sum of these line items became the lump sum total for a project. LaPoint testified that D. Construction’s bids were part of the Agreements between the parties as the Agreements would reference the bid documents and the bid documents were attached as an exhibit to the contracts. LaPoint testified that the civil work was governed by the blanket contracts and the Master Terms. The FEP work was performed under different contracts.

¶ 13 After termination of the Agreements, D. Construction determined the earned value by going through each line item on the unit pricing sheet. LaPoint testified that if it was finite calculation, D. Construction would apply that to the quantities performed in order to get a completion percentage for each line item. If the calculation “was a little less clear,” D. Construction, along with its subcontractors and onsite managers, would perform final onsite walkdowns for work performed. LaPoint prepared the earned value calculations for the project. In order to determine the earned value, he went down each line item, identified what and how much was done, and what the agreed price was. LaPoint’s earned value calculations for each project was admitted into evidence.

¶ 14 At the time the Agreements were terminated, the Itasca Fencing Project was partially completed. This project was a part of the FEP work and was a lump sum contract. LaPoint’s earned value calculation for this project was $1,992,473.62. LaPoint testified that 42.72% of line 15, vacuum excavate fence post and gate post holes, had been completed. He arrived at this number as 42% of the fence had been completed.

Free access — add to your briefcase to read the full text and ask questions with AI

D. Construction, Inc. v. Commonwealth Edison Co., (Ill. Ct. App. 2026).

D. Construction, Inc. v. Commonwealth Edison Co. (D. Construction, Inc. v. Commonwealth Edison Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

1472 N. Milwaukee, LTD. v. Feinerman
2013 IL App (1st) 121191 (Appellate Court of Illinois, 2013)
Razor v. Hyundai Motor America
854 N.E.2d 607 (Illinois Supreme Court, 2006)
Provident Federal Savings & Loan Ass'n v. Realty Centre, Ltd.
454 N.E.2d 249 (Illinois Supreme Court, 1983)
A.W. Wendell & Sons, Inc. v. Qazi
626 N.E.2d 280 (Appellate Court of Illinois, 1993)
Kokinis v. Kotrich
407 N.E.2d 43 (Illinois Supreme Court, 1980)
Berg & Associates, Inc. v. Nelsen Steel & Wire Co.
580 N.E.2d 1198 (Appellate Court of Illinois, 1991)
Gallagher v. Lenart
874 N.E.2d 43 (Illinois Supreme Court, 2007)
General Dynamics Corp. v. Zion State Bank & Trust Co.
427 N.E.2d 131 (Illinois Supreme Court, 1981)
Arneson v. BD. OF TR., McKENDREE COLLEGE
569 N.E.2d 252 (Appellate Court of Illinois, 1991)
Gonet v. Chicago & North Western Transportation Co.
552 N.E.2d 1224 (Appellate Court of Illinois, 1990)
Kehoe v. WILDMAN, HARROLD, ALLEN AND DIXON
899 N.E.2d 1177 (Appellate Court of Illinois, 2008)
Marshall v. Burger King Corp.
856 N.E.2d 1048 (Illinois Supreme Court, 2006)
Tri-G, Inc. v. Burke, Bosselman & Weaver
856 N.E.2d 389 (Illinois Supreme Court, 2006)
Chicago's Pizza, Inc. v. Chicago's Pizza Franchise Limited USA
893 N.E.2d 981 (Appellate Court of Illinois, 2008)
Liberty Mutual Insurance v. Zambole
491 N.E.2d 132 (Appellate Court of Illinois, 1986)
R & R Construction Co. v. Junior College District No. 529
370 N.E.2d 599 (Appellate Court of Illinois, 1977)
Duncan v. Cannon
561 N.E.2d 1147 (Appellate Court of Illinois, 1990)
Alpha School Bus Co., Inc. v. Wagner
910 N.E.2d 1134 (Appellate Court of Illinois, 2009)
Snelson v. Kamm
787 N.E.2d 796 (Illinois Supreme Court, 2003)