Atlee Electric Co. v. Johnson Construction Co.

303 N.E.2d 192, 14 Ill. App. 3d 716, 1973 Ill. App. LEXIS 1908
CourtAppellate Court of Illinois
DecidedSeptember 24, 1973
Docket57203
StatusPublished
Cited by22 cases

This text of 303 N.E.2d 192 (Atlee Electric Co. v. Johnson Construction Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlee Electric Co. v. Johnson Construction Co., 303 N.E.2d 192, 14 Ill. App. 3d 716, 1973 Ill. App. LEXIS 1908 (Ill. Ct. App. 1973).

Opinion

Mr. JUSTICE GOLDBERG

delivered the opinion of the court:

Atlee Electric Company, Inc. (plaintiff) filed suit for the foreclosure of a mechanic’s lien upon certain real estate. After trial by the court, a judgment for foreclosure of the lien and sale of the property was entered. Johnson Construction Co., Howard Western Industries, Inc., Howard Savings & Loan Association, Howard-Northfield Building Development Corp. and Gustav A. Pródromos (defendants) appeal.

Defendants urge that the judgment appealed from should be reversed for failure of plaintiff to join another lien claimant as a party defendant; the trial court erred in taking judicial notice of foreclosure of another mechanic’s lien claim and in denying defendants the right to a continuance for amendment of their pleadings. Defendants also urge that the judgment is contrary to the evidence in that the trial court improperly included certain extras and the amount of certain labor and material; inconsistencies between plaintiff’s claim for hen, complaint and proof are fatal, and the evidence is insufficient to support the judgment so that the judgment was arbitrary and capricious. Plaintiff responds that the point regarding alleged failure to join a necessary party is without legal foundation; the trial court properly took judicial notice of sworn pleadings in other proceedings; the trial court did not abuse discretion in denying a continuance; plaintiff met the burden of proof regarding extras; monies expended by plaintiff for labor and materials were properly proved; there is no inconsistency between plaintiff’s claim for lien and its complaint; and, finally, since the judgment is not clearly against the manifest weight of the evidence, it should be affirmed.

We will first state the general factual background and we will later supplement this statement as required for decision of the various points raised. On February 27, 1970, Johnson Construction Company (Johnson Co.), one of the defendants, entered into a written contract with plaintiff. Johnson Co. was the general contractor for remodeling of improved real estate at 1321 West Howard Street, in Evanston, so that plaintiff was a subcontractor. The contract provided that plaintiff was to furnish and install various electric apparatus complete with wiring for a stated price of $20,517. The allegation in plaintiffs complaint that, as regards this contract, Johnson Co. served as nominee and agent of the owner of the property is admitted by defendants.

Plaintiff entered into the premises and commenced performance. On May 21, 1970, another written agreement was entered into between plaintiff and Johnson Co. for additional electrical work for a stated price of $2080. The first agreement provided that an initial payment was to be made to plaintiff upon commencement of performance with 85% of the balance to be paid as the work progressed and final balance to be paid upon completion. The second agreement provided for payment of 85% of the contract price according to progress with balance upon completion.

It is plaintiffs general theory that the work progressed in due course but that defendants failed to pay plaintiff in accordance with progress. It is the theory of defendants that plaintiff failed to pursue the work diligently and that defendants, although ready, willing and able to pay, were not legally obligated to do so. It is agreed, however, that plaintiff stopped performance on August 12, 1970, and withdrew from the job. Thereafter, defendants entered into a contract with another firm, Amber Electric Construction Corp. (Amber Co.), to complete the electrical work.

The property is registered under the provisions of “An Act concerning land titles” generally referred to as the Torrens Act. (Ill. Rev. Stat. 1971, ch. 30, pars. 45 et seq.) Therefore, service of notice of subcontractor’s lien upon the owner was unnecessary. (Ill. Rev. Stat. 1971, ch. 82, par. 24.) Plaintiff registered its initial claim for hen on October 16, 1970 and another claim on December 4, 1970.

Defendants’ first point bears upon the statutory requirement that plaintiff in a mechanic’s lien foreclosure “* # # shall make all parties interested, of whose interest he is notified or has knowledge, parties defendant * # *. Parties in interest within the meaning of this act, shall include persons entitled to liens thereunder whose claims are not, as well as are, due at the time of the commencement of suit * * * also all persons who may have any legal or equitable claim to the whole or any part of the premises.” (Ill. Rev. Stat. 1971, ch. 82, par. 11.) Defendants interpret this as a mandatory requirement of the statute. They reason from this premise that since the record shows that Amber Co. had instituted a suit for foreclosure of a mechanic’s lien against defendants’ property, it was a necessary party so that the judgment appealed from should thus be reversed. However, certain additional facts must be supplied from this record before this simplistic reasoning can be accepted.

Plaintiff’s complaint contains no allegation regarding Amber Co. Plaintiff conceded in its brief in this court that it was aware that Amber Co. intended to take over the job after plaintiff abandoned it. However, plaintiff contends, and this assertion is borne out by the record, that there is no evidence before us that Amber Co. was a party in interest within the meaning of the statute. There is no evidence that Amber Co. furnished any labor or materials under its contract; and no evidence that any monies remained due and unpaid to Amber Co. The record shows only that at one point one of the defendants, Gustav A. Pródromos, testified, “I paid Amber.” This could be construed to mean that Amber Co. had been paid and therefore had no lien. Immediately after this, counsel for plaintiff asked the court to take judicial notice of “a pending lawsuit” brought by Amber Co. against certain of defendants to which defendants objected.

Furthermore, there is no showing here that Amber Co. ever registered a claim for lien against the property in the office of the Registrar of Titles of Cook County. Such registration would generally be a mandatory condition precedent to creation of any interest in the registered property by a lien claimant. (Ill. Rev. Stat. 1971, ch. 30, par. 126. See also 31 I.L.P. 328, § 10 under Registration of Land Titles.) Thus, the record does not show whether Amber Co. in fact has any “legal or equitable claim” against the premises which would make it a necessary party.

It follows that there was no legal requirement in the case at bar for plaintiff to add Amber Co. as a party. We cannot agree with the contention of defendants that the trial court should have consolidated the proceedings brought by Amber Co. with the case at bar sua sponte as soon as counsel for plaintiff showed the court a copy of the complaint filed by Amber Co. The authorities cited by defendants in this regard are inapplicable. (Granquist v. Western Tube Co., 240 Ill. 132, 88 N.E.2d 468; Malkov Lumber Co. v. Serafine Builders, Inc., 1 Ill.App.3d 543, 273 N.E.2d 654; Rochelle Bldg. Co. v. Oak Pk. Tr. & Sav. Bank, 121 Ill.App, 2d 274, 257 N.E.2d 542.) All of these cases are dramatically different from the case at bar in their factual structure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

G.M. Harston Construction Co. v. City of Chicago
371 F. Supp. 2d 949 (N.D. Illinois, 2005)
Chicago Whirly, Inc. v. Amp Rite Electric Co., Inc.
710 N.E.2d 45 (Appellate Court of Illinois, 1999)
EDWARD M. COHON & ASSOCS., LTD. v. First Nat. Bank
618 N.E.2d 676 (Appellate Court of Illinois, 1993)
Joseph T. Ryerson & Son, Inc. v. Manulife Real Estate Co.
566 N.E.2d 297 (Appellate Court of Illinois, 1990)
Duncan v. Cannon
561 N.E.2d 1147 (Appellate Court of Illinois, 1990)
Ford Motor Credit Co. v. Neiser
554 N.E.2d 322 (Appellate Court of Illinois, 1990)
Jack v. Pugeda
539 N.E.2d 1328 (Appellate Court of Illinois, 1989)
Stone v. City of Arcola
536 N.E.2d 1329 (Appellate Court of Illinois, 1989)
Mann v. People
424 N.E.2d 883 (Appellate Court of Illinois, 1981)
Hutchinson v. Brotman-Sherman Theatres, Inc.
419 N.E.2d 530 (Appellate Court of Illinois, 1981)
City of Chicago v. Southgate Corp.
407 N.E.2d 881 (Appellate Court of Illinois, 1980)
Volvo of America Corp. v. Gibson
404 N.E.2d 406 (Appellate Court of Illinois, 1980)
Daehler v. Oggoian
390 N.E.2d 417 (Appellate Court of Illinois, 1979)
Stony Island Church of Christ v. Stephens
369 N.E.2d 1313 (Appellate Court of Illinois, 1977)
Central Steel & Wire Co. v. Coating Research Corp.
369 N.E.2d 140 (Appellate Court of Illinois, 1977)
Custom Builders, Inc. v. Clemons
367 N.E.2d 537 (Appellate Court of Illinois, 1977)
Agrico Chemical Corp. v. Forreston Fertilizer Co.
337 N.E.2d 76 (Appellate Court of Illinois, 1975)
Gill Custom House, Inc. v. Gaslight Club, Inc.
330 N.E.2d 559 (Appellate Court of Illinois, 1975)
William Aupperle & Sons, Inc. v. American National Bank & Trust Co.
329 N.E.2d 458 (Appellate Court of Illinois, 1975)
People v. Lewis
329 N.E.2d 390 (Appellate Court of Illinois, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
303 N.E.2d 192, 14 Ill. App. 3d 716, 1973 Ill. App. LEXIS 1908, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlee-electric-co-v-johnson-construction-co-illappct-1973.