Joseph T. Ryerson & Son, Inc. v. Manulife Real Estate Co.

566 N.E.2d 297, 207 Ill. App. 3d 622, 152 Ill. Dec. 610, 1990 Ill. App. LEXIS 1775
CourtAppellate Court of Illinois
DecidedNovember 26, 1990
Docket1-89-3431
StatusPublished
Cited by2 cases

This text of 566 N.E.2d 297 (Joseph T. Ryerson & Son, Inc. v. Manulife Real Estate Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph T. Ryerson & Son, Inc. v. Manulife Real Estate Co., 566 N.E.2d 297, 207 Ill. App. 3d 622, 152 Ill. Dec. 610, 1990 Ill. App. LEXIS 1775 (Ill. Ct. App. 1990).

Opinion

JUSTICE EGAN

delivered the opinion of the court:

The plaintiff, Joseph T. Ryerson & Son, Inc. (Ryerson), brought suit to foreclose a mechanics’ lien on property owned by defendant Manufacturers Life Insurance Company (Manulife). Manulife had employed defendant E.W. Corrigan Construction Company (Corrigan) as the general contractor on a project requiring Corrigan to construct a new office building in Schaumburg, Illinois. Corrigan, in turn, entered into a subcontract with Crescent Corporation (Crescent) that required Crescent to fabricate and install a curtain wall on the project. Crescent then contracted with Ryerson for the furnishing of certain materials necessary for Crescent’s performance on the subcontract.

In December 1985 Crescent ceased to perform on its subcontract with Corrigan, allegedly in breach of that subcontract. Crescent also allegedly failed to pay Ryerson for materials and supplies worth $55,913 which Ryerson had delivered to Crescent and which were received and used in the project. On November 3, 1986, Ryerson filed the underlying suit against Manulife and Corrigan seeking to foreclose its alleged mechanics’ lien for the unpaid balance. Ryerson did not name Crescent as a party to the suit.

The defendants, Corrigan and Manulife, each filed a motion to strike the complaint, alleging that Crescent was a necessary party to the action and that the failure to name Crescent constituted a fatal defect in the pleading. Ryerson opposed the motion, and the trial judge denied it. The judge later granted Ryerson’s motion for summary judgment and entered judgment against the defendants jointly for $47,368.30 plus interest.

The defendants argue that the trial court erred in denying the motion to strike for failure to name a necessary party. Alternatively, the defendants challenge whether an owner and a general contractor can be required to pay a material supplier to a subcontractor more than the subcontract price or more than the amount owed to the subcontractor when the owner and general contractor received notice of the material supplier’s lien claim.

Section 22 of the Mechanics’ Liens Act (Act) provides the basis for Ryerson’s lien, stating:

“When the contractor shall sub-let his contract or a specific portion thereof to a sub-contractor, the party furnishing material to or performing labor for such sub-contractor shall have a lien therefor; and may enforce his lien in the same manner as is herein provided for the enforcement of liens by sub-contractors.” (Ill. Rev. Stat. 1989, ch. 82, par. 22.)

Section 28 of the Act provides for the enforcement of liens by subcontractors and states, in part, as follows:

“All suits and actions by sub-contractors shall be against both the contractor and owner jointly, and no judgment shall be rendered therein until both are duly brought before the court by process or publication ***.” (Ill. Rev. Stat. 1989, ch. 82, par. 28.)

Section 11 of the Act provides:

“§11. The complaint shall contain a brief statement of the contract or contracts on which it is founded ***. *** The plaintiff shall make all parties interested, of whose interest he is notified or has knowledge, parties defendant, and summons shall issue and service thereof be had as in other civil actions; * * * and his failure to so act with regard to summons or notice shall be ground for judgment against him as upon the merits. *** Parties in interest, within the meaning of this act, shall include *** all persons *** who are interested in the subject matter of the suit.” (Emphasis added.) Ill. Rev. Stat. 1989, ch. 82, par. 11.

Boiled down, the issue is whether Crescent is a person “interested in the subject matter of the suit.” The defendants cite John E. Burns Lumber Co. v. W.J. Reynolds Co. (1909), 148 Ill. App. 356, as the only Illinois authority directly in point. In Burns the appellate court found that the evidence showed that the plaintiff had contracted to supply material to a carpentry subcontractor, W.J. Reynolds, an individual. The complaint, however, had named the W. J. Reynolds Company as the alleged subcontractor. (The complaint also named the owner and the general contractor.) The appellate court reversed the judgment in favor of the plaintiff because the complaint had failed to name the true subcontractor, W.J. Reynolds, personally and individually. In so doing the court stated:

“The complainant [and other intervening material suppliers] are all furnishers of material for the subcontract and, being of that class, they *** claim liens under section 22 of the Mechanics’ Lien Act. They contracted with and trusted the subcontractor and, through that relation, they claim their lien upon the property. Should they eventually establish a right to liens and thereby the amount the owner would be obliged to pay for the carpenter work be made to exceed the contract price, a right to be reimbursed by the subcontractor, if not by the original contractor, would arise. It is, therefore, of the highest importance that the actual subcontractor, a party in interest and under the lien law a necessary party as such, be a party to this proceeding.” (Emphasis added.) 148 Ill. App. at 365-66.

The relation of the parties in Burns is identical to the relation of the parties in this case. The plaintiff in Burns claimed its lien through the subcontractor, Reynolds; Ryerson claimed its lien through its contract with the subcontractor, Crescent. Under the authority of Burns, therefore, it is inescapable that Crescent is “a party in interest and under the lien law a necessary party as such.” 148 Ill. App. at 366.

Ryerson seeks to distinguish Burns; it emphasizes that the trial court in Burns heard evidence which established the interest of the subcontractor, W.J. Reynolds; it further claims that the record in this case shows that Crescent had no interest because Crescent was bankrupt. First of all, there was no need to hear evidence to establish the relationship between Ryerson, Crescent and the defendants. Ryerson’s complaint established the relationship. Second, as the defendants point out, the record does not support a finding that Crescent was bankrupt. Moreover, the trial judge never made such a finding; he was never asked to do so. Indeed, in the memoranda filed by Ryerson in the trial court, no argument was made that Crescent was not a necessary party because it was bankrupt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chicago Whirly, Inc. v. Amp Rite Electric Co., Inc.
710 N.E.2d 45 (Appellate Court of Illinois, 1999)
Joseph T. Ryerson & Son, Inc. v. Manulife Real Estate Co.
606 N.E.2d 463 (Appellate Court of Illinois, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
566 N.E.2d 297, 207 Ill. App. 3d 622, 152 Ill. Dec. 610, 1990 Ill. App. LEXIS 1775, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joseph-t-ryerson-son-inc-v-manulife-real-estate-co-illappct-1990.