M.P. Kenes, Incorporated v. Technicote, Incorporated

36 F.3d 1099, 1994 U.S. App. LEXIS 33860, 1994 WL 534767
CourtCourt of Appeals for the Seventh Circuit
DecidedSeptember 30, 1994
Docket93-3975
StatusUnpublished

This text of 36 F.3d 1099 (M.P. Kenes, Incorporated v. Technicote, Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
M.P. Kenes, Incorporated v. Technicote, Incorporated, 36 F.3d 1099, 1994 U.S. App. LEXIS 33860, 1994 WL 534767 (7th Cir. 1994).

Opinion

36 F.3d 1099

NOTICE: Seventh Circuit Rule 53(b)(2) states unpublished orders shall not be cited or used as precedent except to support a claim of res judicata, collateral estoppel or law of the case in any federal court within the circuit.
M.P. KENES, INCORPORATED, Plaintiff-Appellant,
v.
TECHNICOTE, INCORPORATED, Defendant-Appellee.

No. 93-3975.

United States Court of Appeals, Seventh Circuit.

Argued June 9, 1994.
Decided Sept. 30, 1994.

Before MANION and KANNE, Circuit Judges, and SHABAZ, District Judge.*

ORDER

M.P. Kenes, Inc. filed suit against Technicote, Inc. seeking recovery of money that Technicote withheld under an engineering services contract. M.P. Kenes also sought additional compensation of $125,000 for work it performed allegedly outside the scope of this engineering services contract. Technicote counterclaimed for breach of contract. The parties agreed to submit their claims to a magistrate judge. After a bench trial, the magistrate judge found that M.P. Kenes was entitled to 85% of the money remaining due under the engineering services contract, but that it was not entitled to additional compensation for "out-of-scope" work. The magistrate judge also concluded that Technicote was not entitled to damages for breach of contract. M.P. Kenes appeals. We affirm.

I. Background

In 1988, defendant Technicote, Inc. ("Technicote") entered into a contract with a Chinese company, Carrie Enterprise, Ltd. This contract required Technicote to provide Carrie Enterprise with machinery to manufacture pressure sensitive labels. The contract also obligated Technicote to provide Carrie Enterprise with "equipment detailed part drawings" for the machinery.

In turn, Technicote entered into a contract with M.P. Kenes ("Kenes") in which Kenes agreed to provide Technicote with certain engineering services. Among these services, Kenes was to convert to metric units measurements on certain engineering drawings. To do this, Kenes planned to use drawings provided to Technicote from two Indiana machine shops (hereinafter referred to as the "Indiana drawings"). The Indiana drawings which Kenes was to convert, however, contained numerous errors and omissions. Kenes informed Technicote of these inaccuracies in March of 1989 and a Technicote representative told Kenes to "do whatever was necessary to make the drawings correct." Kenes undertook substantial efforts to redo the Indiana drawings. Kenes' employees identified dimensional errors and discrepancies in the drawings, and then they inspected photographs of the machinery. They also identified and determined the dimensions of items listed in spare part and gear catalogs and then even travelled to Technicote's plant in Ohio to inspect the machinery. Kenes then incorporated this new information into the drawings to correct the dimensional errors and inconsistencies.

Despite the substantial trouble (in terms of time and money) that Kenes invested to correct the Indiana drawings, it did not request additional compensation from Technicote for this work until December of 1989--eight months later. At that time, Kenes faxed Technicote a request for an additional $96,850 for its work in correcting the Indiana drawings. Technicote refused to pay Kenes any additional money claiming that Kenes was required under the contract to redraft the drawings if necessary. Technicote also maintained that even if the work was beyond the scope of the original contract, Kenes was not entitled to additional compensation because Technicote had not agreed to pay for this work. Representatives from Kenes and Technicote met later to resolve their dispute. The meeting, however, proved futile. Kenes continued to demand additional compensation and Technicote refused to pay. After reaching this impasse, Kenes informed Technicote that it would perform no further work on the project. At the time, Kenes had provided Technicote approximately 85% of the Indiana drawings converted to metric. Technicote in turn refused to pay Kenes the remaining amount due Kenes under the contract--$47,490.

Kenes eventually filed suit against Technicote, now asking for $125,000 in compensation for its work in redrafting the Indiana drawings. Kenes also sought recovery of the $47,490 remaining due under its original contract with Technicote. Technicote in turn counterclaimed for breach of contract for Kenes' failure to convert the remaining 15% of the Indiana drawings to metric. The parties agreed to have their dispute decided by a magistrate judge. After a bench trial, the magistrate judge concluded that Kenes was not entitled to additional compensation for its work in redrafting the Indiana drawings because Technicote had not agreed to pay for the additional work, as required for recovery under Illinois law. The magistrate judge, however, concluded that Kenes was entitled to 85% of the $47,490 that Technicote withheld. She also concluded that Technicote was not entitled to any damages for Kenes' breach of contract. Kenes appeals.

II. Analysis

On appeal, Kenes claims that the magistrate judge erred in finding that it was not entitled to compensation for its work in redrafting the Indiana drawings. Kenes also appeals the magistrate judge's determination that it was entitled to only 85% of the $47,490 which Technicote withheld under the original contract.1 The parties agree that Illinois law governs these issues.

A. Out-of-scope work.

Kenes claims that in addition to the compensation due it under the engineering service contract, it was entitled to compensation for its work in redrafting the Indiana drawings. Where parties have an express contract and one of them seeks additional payment for work outside the scope of that contract, the party seeking additional compensation must establish by clear and convincing evidence that the work was:

1. outside the scope of the original contract;

2. ordered at the direction of the owner;

3. agreed to be paid for by the owner either by words or by conduct;

4. not voluntarily furnished by the contractor; and

5. not rendered necessary by the fault of the contractor.

Duncan v. Cannon, 561 N.E.2d 1147, 1149 (Ill.App.1990); Brant Constr. Co., Inc. v. Metropolitan Water Reclamation Dist., 967 F.2d 244, 246 (7th Cir.1992).

The magistrate judge found that Kenes failed to meet its burden of proof concerning requirement three--that Technicote agreed to pay Kenes for redrafting the Indiana drawings--and, therefore, Kenes was not entitled to recover for "out-of-scope" work. We review a district court's findings of fact under a clearly erroneous standard. Business Records Corp. v. Lueth, 981 F.2d 957, 959 (7th Cir.1992).

The evidence before the magistrate judge in this case established that John Rodda of Technicote told Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Danny Lee Wey
895 F.2d 429 (Seventh Circuit, 1990)
Pope v. Speiser
130 N.E.2d 507 (Illinois Supreme Court, 1955)
Berg & Associates, Inc. v. Nelsen Steel & Wire Co.
580 N.E.2d 1198 (Appellate Court of Illinois, 1991)
Batterman v. Consumers Illinois Water Co.
634 N.E.2d 1235 (Appellate Court of Illinois, 1994)
Duncan v. Cannon
561 N.E.2d 1147 (Appellate Court of Illinois, 1990)
Howard v. Jay
561 N.E.2d 274 (Appellate Court of Illinois, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
36 F.3d 1099, 1994 U.S. App. LEXIS 33860, 1994 WL 534767, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mp-kenes-incorporated-v-technicote-incorporated-ca7-1994.