Yankee Atomic Electric Co. v. United States

73 Fed. Cl. 249, 64 ERC (BNA) 1147, 2006 U.S. Claims LEXIS 296
CourtUnited States Court of Federal Claims
DecidedSeptember 30, 2006
DocketNo. 98-126C
StatusPublished
Cited by32 cases

This text of 73 Fed. Cl. 249 (Yankee Atomic Electric Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Yankee Atomic Electric Co. v. United States, 73 Fed. Cl. 249, 64 ERC (BNA) 1147, 2006 U.S. Claims LEXIS 296 (uscfc 2006).

Opinion

OPINION and ORDER1

MEROW, Senior Judge.

Three nuclear utilities seek damages for the Department of Energy’s (“DOE”)’s [251]*251breach of contract to accept, transport, and dispose of their spent nuclear fuel (“SNF”).2 Substantial storage costs for SNF are borne by utility ratepayers whose rates also reflect the $440.5 ± million paid or to be paid to DOE under the contracts involved. Breach of contract by the United States has been established. Maine Yankee Atomic Power Co. v. United States, 225 F.3d 1336, 1342 (Fed.Cir.2000). Plaintiffs seek to recover their incurred SNF storage costs from the United States as mitigation expenses — commercially reasonable and foreseeable responses to DOE’s admitted decade-long delay in commencing performance. Defendant counters that many, if not most, of the costs would have been incurred regardless of DOE’s delay. Trial in this matter consumed seven weeks.

INTRODUCTION

In 1983, pursuant to the Nuclear Waste Policy Act of 1982 (“NWPA”), Pub.L. No. 97-425, 96 Stat. 2201 (codified at 42 U.S.C. §§ 10101-10270 (2000)) plaintiffs, along with all domestic nuclear utilities, entered into Standard Contracts with DOE wherein, in return for payment of substantial fees, DOE would accept title to, transport and dispose of the utilities’ SNF, commencing performance no later than January 31, 1998. Due in part to the highly regulated nature of the industry, entry into Standard Contracts was mandatory. “Nuclear plant operators and utilities were mandated by Congress to enter into Standard Contracts, the terms of which are presented at 10 C.F.E. § 961.11, as a prerequisite to obtaining renewal of their operating licenses.” Indiana Michigan Power Co. (hereinafter “Ind. Mich.”) v. United States, 422 F.3d 1369, 1372 (Fed.Cir.2005) (citing 42 U.S.C. § 10222(a)(1)); Maine Yankee, 225 F.3d at 1337 (“ ‘The NWPA effectively made entry into such contracts mandatory for the utilities.’ ”). DOE did not commence performance by 1998 as required by the NWPA and the Standard Contract. While insisting there will be performance, the date continues to recede from 2010 to 2017, the latest prognosis.

Plaintiffs assert that the delay in DOE’s performance has resulted in substantial damages. All three plaintiffs’ nuclear reactors have been shut down. They contend that if DOE had timely commenced performance, all their SNF would no longer be on-site (or at least they would not be responsible for it); and accordingly, their sites would have been “decommissioned” and available for other use.

At trial, damages were presented on actual and future costs for time periods preceding January 31, 1998 (pre-breach) through 2012 (2011 for Maine Yankee). See Yankee Atomic Elec. Co. v. United States, 2004 WL 1535688, at * 1-3 (June 28, 2004). Future costs were based in substantial part on cost projections approved by regulators for rate base purposes. As such, these costs were subject to public notice and opportunity for input, analysis and criticism. After trial was completed, the Circuit Court issued its decision in Indiana Michigan and held that, in any suit for breach of an SNF contract, recoverable costs were limited to those actually incurred up to the date the litigation was initiated. Trial, as well as post-trial briefing and proposed findings in the instant cases included future damages based on the then assumption that DOE planned to commence performance in 2010. Following the ruling in Indiana Michigan, the court requested supplemental briefing. Thereafter, plaintiffs’ Motion to Amend their Complaints was granted in part, and record evidence was limited to damages actually incurred through 2001 for Yankee Atomic and Connecticut Yankee, and through 2002 for Maine Yankee. These damages involved costs actually incurred as of trial and contained in plaintiffs’ pre-trial and trial evidence. Costs asserted for periods beyond these time periods were dismissed without prejudice to their reassertion in future litigation.

Upon careful consideration of testimony, argument, documents and exhibits, the court [252]*252concludes that the plaintiffs reasonably incurred substantial and foreseeable costs in mitigating DOE’s acknowledged impending and substantial delay in commencement of performance of the contracts involved, and that the delay was a substantial causal factor in their respective expenditure decisions. Accordingly, plaintiffs are entitled to recover certain, but not all, mitigation costs claimed as damages for DOE’s partial breach in not commencing contract performance by January 31, 1998.

Technical summary

The nuclear waste problems involved in this litigation commence with the content of the fuel rods. Uranium oxide pellets (little finger-sized) are placed into 12-14 foot metal rods of about the same diameter and bundled together with metallic bands into “assemblies.” Each fuel assembly contains about one metric ton of uranium (“MTU”). A fuel assembly is approximately nine inches square and fourteen feet long. (PX 1926.001; Yankee Atomic’s Proposed Findings of Fact (“YA PFF”) 9; Maine Yankee’s Proposed Findings of Fact (“MY PFF”) 8; Connecticut Yankee’s Proposed Findings of Fact (“CY PFF”) 8 and Def.’s Resps.) Assemblies are placed in the reactor core where fission produces heat which is converted to steam to drive turbines and generate electricity.

Within twelve to eighteen months, the uranium in the rods becomes relatively inefficient. The reactor is shut down, the assemblies removed and placed on-site in adjacent “wet” pools of treated water where the SNF is cooled for at least five years.3 Wet pools involved in this litigation are about 80 by 40 feet, are made of concrete, lined with stainless steel and filled with treated water that shields radioactivity. Boric acid, which absorbs neutrons, and spacing in the racks help prevent “criticality” — self-sustaining fission reaction resulting from the interchange of neutrons. The assemblies are placed in basket-like racks lowered into the pools. When SNF is removed from the reactor core, it is still capable of attaining criticality. Transporting rods in or out of the reactor core, or in and out of the wet pool, is a complex, expensive and highly regulated process. (YA PFF 11-15 and Def.’s Resp.) See Twp. of Lower Alloways Creek v. Pub. Serv. Elec. & Gas Co., 687 F.2d 732, 737 (3rd Cir.1982). Storage, and most activities in and around the plant, are regulated by the Nuclear Regulatory Commission (“NRC”). See generally 10 C.F.R. pts. 72-73 (2004).

The size and configuration of the spent fuel pool and the racks constrain the number of spent fuel rods that can be stored there. The reactor core can hold only a limited number of rods. Storage need is triggered by the removal of either “spent” fuel or damaged assemblies from the reactor core. Also, repair or inspection of the reactor core requires removal of all the fuel. Irradiated tools are also stored along the walls of the pool.

“Pool capacity” refers to the maximum number of rods that can be stored in a pool. “Full core reserve capability” is the maintenance of sufficient unused space in the pool for all the rods in the reactor core. Maintaining full core reserve (“FCR”) is a common safety-enhancing practice. (Tr. 2591-92 (Mellor); Tr. 2672, 2676 (Heider); Tr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Yankee Atomic Electric Company v. United States
113 Fed. Cl. 323 (Federal Claims, 2013)
Kansas Gas & Electric Co. v. United States
95 Fed. Cl. 257 (Federal Claims, 2010)
Yankee Atomic Power Co. v. United States
94 Fed. Cl. 678 (Federal Claims, 2010)
Southern California Edison Co. v. United States
93 Fed. Cl. 337 (Federal Claims, 2010)
Pacific Gas & Electric Co. v. United States
92 Fed. Cl. 175 (Federal Claims, 2010)
Energy Northwest v. United States
91 Fed. Cl. 531 (Federal Claims, 2010)
Dairyland Power Cooperative v. United States
90 Fed. Cl. 615 (Federal Claims, 2009)
Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)
Pacific Gas & Electric Co. v. United States
536 F.3d 1282 (Federal Circuit, 2008)
Sacramento Municipal Utility District v. United States
293 F. App'x 766 (Federal Circuit, 2008)
Yankee Atomic Electric Co. v. United States
536 F.3d 1268 (Federal Circuit, 2008)
Carolina Power & Light Co. v. United States
82 Fed. Cl. 23 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
73 Fed. Cl. 249, 64 ERC (BNA) 1147, 2006 U.S. Claims LEXIS 296, Counsel Stack Legal Research, https://law.counselstack.com/opinion/yankee-atomic-electric-co-v-united-states-uscfc-2006.