Odyssey International, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJuly 29, 2021
DocketASBCA No. 62062, 62279
StatusPublished

This text of Odyssey International, Inc. (Odyssey International, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Odyssey International, Inc., (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Odyssey International, Inc. ) ASBCA Nos. 62062, 62279 ) Under Contract No. W912DR-15-C-0038 )

APPEARANCES FOR THE APPELLANT: Brian C. Johnson, Esq. H. Burt Ringwood, Esq. Spencer W. Young, Esq. Ian L. Quiel, Esq. Strong & Hanni Salt Lake City, UT

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Adam J. Kwiatkowski, Esq. Engineer Trial Attorney U.S. Army Engineer District, Baltimore

OPINION BY ADMINISTRATIVE JUDGE D’ALESSANDRIS ON THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT

In August 2015, the United States Army Corps of Engineers (USACE or the government) awarded appellant, Odyssey International Inc. (Odyssey) a contract for construction of a building at the Letterkenny Army Depot in Chambersburg, Pennsylvania. The contract called for the use of “micropiles” 1 in the foundation of the building. While the contract line item (CLIN) described the work as a fixed-price line item, the contract also contained language suggesting that the micropiles were being bid at a per-unit rate. In a modification, the government compensated Odyssey for 8 of the 20 claimed additional micropiles. Odyssey additionally asserted entitlement to delay costs, but was not able to reach agreement with the government. The government issued a unilateral modification (Modification No. 3) granting Odyssey some additional time on the contract. At the end of performance, the parties executed a modification (Modification No. 9) that resolved several unrelated issues, and also converted Modification No. 3 to a bilateral modification. Modification No. 9 additionally contained a general release of claims by Odyssey.

1 Micropiles are a building foundation system that involves drilling small diameter holes into bedrock and inserting grout into any voids in the rock before inserting a metal pole and casing. Odyssey filed a request for equitable adjustment (REA) in August 2018, seeking additional costs related to the micropiles. In October 2018, the government denied the REA on the basis that Odyssey had released those costs in Modification No. 9. An Odyssey employee responded that the release in Modification No. 9 seemed to be a “trick, trap or typo,” a characterization disputed by the government. Odyssey subsequently filed a claim in January 2019, which was denied by the USACE contracting officer in an April 2019, final decision. Odyssey appealed the contracting officer’s final decision to the Board, which docketed the case as ASBCA No. 62062.

In July 2019, the government filed a motion to dismiss Odyssey’s appeal for lack of subject matter jurisdiction, contending that the claims had not been submitted to the contracting officer. We granted the government’s motion, in part, on January 28, 2020. Odyssey International Inc., ASBCA No. 62062, 20-1 BCA ¶ 37,510. In our opinion, we found jurisdiction to entertain portions of Odyssey’s complaint that were the “same claim” as had been presented to the contacting officer. While the motion to dismiss was pending before the Board, Odyssey filed a second claim, incorporating the January 2019 claim by reference, and asserting some of the facts raised in Odyssey’s complaint, but not previously presented to the contracting officer. Odyssey appealed the contracting officer’s final decision denying that claim to the Board, where it was docketed as ASBCA No. 62279.

Now pending before the Board is the government’s motion for summary judgment, and motion to dismiss, requesting that both appeals be denied based on the release contained in Modification No. 9. We agree that Odyssey released its claims in Modification No. 9. Odyssey opposes the motion for summary judgment alleging that there is a material factual dispute as to whether there was a meeting of the minds regarding the release in Modification No. 9, based solely on the email statement that the release “seem[s] to be a trick, trap or typo.” We find that Odyssey has not demonstrated the existence of a material factual dispute. Odyssey additionally asserts that it requires discovery pursuant to Federal Rule of Civil Procedure (FED. R. CIV. P.) 56(d) to respond to the government’s motion. We hold that Odyssey has not demonstrated that it would be able to defend against the entry of summary judgment if it obtained its requested discovery. Additionally, we reject Odyssey’s claim for lost profits and its allegations regarding implied-in-fact contracts. Accordingly, Odyssey’s appeals are denied.

STATMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

I. The Contract

On August 13, 2015, the USACE issued invitation for bids W912DR-15-B-0009 for construction of the Component Rebuild Facility at the Letterkenny Army Depot in Chambersburg, Pennsylvania (R4, tab 38 at 1). The invitation for bids provided that the

2 building’s foundation was to be supported by a series of narrow, underground, reinforced and grouted columns, drilled through soil and into competent bedrock, called “micropiles” (R4, tab 37 at 1569-81).

The invitation for bids included a price schedule with 17 contract line item numbers (CLINs), with CLIN 0007 being a fixed-price line item covering all costs relating to construction of the micropiles (R4, tab 38 at 4-7). Paragraph 1.4.1, entitled “General,” of the “Measurement and Payment” section of the Micropile Specification, provides:

All costs in connection with furnishing all materials, equipment, and performing all labor for the construction of the micropiles, . . . but exclusive of work covered by specific unit price items included herein shall be paid for as lump sum.

(R4, tab 37 at 1569-70). Similarly, paragraph 1.4.2, entitled “Rock Probe Holes for Micropile Pile Caps,” of the “Measurement and Payment” section of the Micropile Specification, provides:

Where inspection of rock quality is necessary beneath bond zone depths, the Contracting Officer will direct that a probe hole be performed. Since verification of competent bedrock . . . is the part of the Contractor’s micropile design, payment for rock probing will be part of the lump sum. The contract lump sum price shall constitute full compensation for furnishing all plant, labor, equipment, materials, and supplies, grouting of rock probe holes and performing all operations required for the completion of all work specified in paragraph “Rock Probe Holes”.

(R4, tab 37 at 1570). Paragraph 3.3.4, entitled “Grouting,” of the “Micropile Installation” section of the Micropile Specification provides, in pertinent part, that “[n]o additional payments for excessive grout volumes will be made” (R4, tab 37 at 1579-80).

Paragraph 3.4.3, entitled “Rock Probe Holes,” of the “Testing and Evaluation” section of the Micropile Specification provided that the rock probe costs were included in the micropile lump sum:

Where inspection of rock quality is necessary beneath bond zone depths, the Contracting Officer will direct that a probe hole be performed. Since verification of competent

3 bedrock at all mirocpile [sic] locations, . . . is the part of the Contractor’s micropile design, payment for rock probing will be included with the lump sum.

(R4, tab 37 at 1581). However, despite the language cited above providing that the micropiles were a fixed-price CLIN, the invitation for bids also included language consistent with a per-unit price at paragraph 1.4.1.3 “Criteria for Bidding” providing that:

For bidding purposes, the contractor shall assusme [sic] that 2 micropiles will be installed at each pile cap, with each micropile drilled to a depth of 10 feet into bedrock, with 15 feet of overburden soil.

(R4, tab 37 at 1570) (emphasis added).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anchor Savings Bank, FSB v. United States
597 F.3d 1356 (Federal Circuit, 2010)
Precision Pine & Timber, Inc. v. United States
596 F.3d 817 (Federal Circuit, 2010)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lujan v. National Wildlife Federation
497 U.S. 871 (Supreme Court, 1990)
M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Bliss v. Franco
446 F.3d 1036 (Tenth Circuit, 2006)
Bell Bci Co. v. United States
570 F.3d 1337 (Federal Circuit, 2009)
Serdarevic v. Advanced Medical Optics, Inc.
532 F.3d 1352 (Federal Circuit, 2008)
Centex Corp. v. United States
395 F.3d 1283 (Federal Circuit, 2005)
Gary L. Costlow v. United States
552 F.2d 560 (Third Circuit, 1977)
Pure Gold, Inc. v. Syntex (u.s.a.), Inc.
739 F.2d 624 (Federal Circuit, 1984)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Mil-Spec Contractors, Inc. v. The United States
835 F.2d 865 (Federal Circuit, 1987)
Beta Systems, Inc. v. The United States
838 F.2d 1179 (Federal Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
Odyssey International, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/odyssey-international-inc-asbca-2021.