Fortis Networks, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJune 2, 2021
DocketASBCA No. 61941
StatusPublished

This text of Fortis Networks, Inc. (Fortis Networks, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fortis Networks, Inc., (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Fortis Networks, Inc. ) ASBCA No. 61941 ) Under Contract No. W912BV-14-D-0005 )

APPEARANCE FOR THE APPELLANT: David A. Rose, Esq. Rose Consulting Law Firm Valdosta, GA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Lauren M. Williams, Esq. Engineer Trial Attorney U.S. Army Engineer District, Tulsa

OPINION BY ADMINISTRATIVE JUDGE OSTERHOUT ON THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT

This appeal concerns liquidated damages assessed on a task order to repair five different buildings, issued by the United States Army Corps of Engineers (the government or USACE) to Fortis Networks, Inc. (appellant or Fortis). The government filed a motion for summary judgment, asking the Board to uphold the liquidated damages for the full amount. We grant the motion, in part, and deny the motion, in part.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. The contracting officer (CO) awarded Contract No. W912BV-D-0005 (the contract), an indefinite-delivery, indefinite-quantity (IDIQ), on July 10, 2014. The contract included a base year and four option years for

Design Build Single Award Task Order Contract Indefinite Delivery Indefinite Quantity (SATOC IDIQ) for construction services in support of various military, civil works, and International and Interagency Support (IIS) projects within Southwestern Division (SWD) boundaries and for Tulsa District customers. This contract is primarily for Central Oklahoma Area Resident Office projects, but may encompass work in other states covered by the geographic region included in the SWD boundaries and other SWD customers.

(R4, tab 3 at 1-16)

2. The SATOC IDIQ contract included FAR 52.211-11, Liquidated Damages—Supplies, Services, or Research and Development (SEP 2000). The amount for liquidated damages was set at $988 per calendar day. The clause also stated, “(c) The Contractor will not be charged with liquidated damages when the delay in delivery or performance is beyond the control and without the fault or negligence of the Contractor as defined in the Default—Fixed-Price Supply and Service clause in this contract.” (R4, tab 3 at 45-46)

3. On August 28, 2014, the government issued a solicitation for a task order under the contract for multiple repairs in Ft. Sill, OK (R4, tabs 4-5). The project was

“a design-build construction project to replace existing mechanical equipment and add cooling to B1643; replace all sanitary and domestic water plumbing and renovate the first floor restrooms in B500; provide a new fire sprinkler system and alarm system in B443; provide a new HVAC system in B443, which was listed as an option the government could exercise; provide sound proofing on ductwork in B700; and replace an existing oil-water separator in B2245”

(R4, tab 5 at 3). Each contract line item number (CLIN) had its own distinct and detailed section of the statement of work, numbered 01 10 00 with a letter designation after the number of A through F (R4, tab 5 at 2, 219-355).

4. The solicitation included an updated liquidated damages amount for the task order. The amount was $735 per calendar day. (R4, tab 5 at 11)

5. On September 29, 2014, the CO awarded Task Order No. 0002 (the task order). CLIN 0001 was a job to replace the Heating Ventilation and Air Conditioning (HVAC) in building no. 1643, valued at $433,457. CLIN 0002 was a job to replace plumbing and renovating bathrooms in building no. 500, valued at $865,927. CLIN 0003 was a job to replace the fire suppression system in building no. 443, valued at $551,078. CLIN 0004 was a job to provide duct soundproofing in building no. 700, valued at $28,406. CLIN 0005 was a job to replace the oil and water separator in building no. 2245, valued at $225,258. CLIN 0006 was an option the CO exercised to install HVAC in building no. 443, valued at $845,636. (R4, tab 8 at 1-4)

6. Task Order No. 0002 contained Federal Acquisition Regulation (FAR) 52.211-10, COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984), ordering appellant to begin within 10 days after the receipt of notice to proceed and to finish the project in not more than 592 calendar days (R4, tab 8 at 13).

7. On October 28, 2014, the CO issued the notice to proceed (R4, tab 10). We find that 592 calendar days after October 28, 2014 was June 11, 2016.

8. On January 27, 2016, the CO modified task order no. 0002 for a no-cost change to remove “the new mechanical room as described in 01 10 00 C Part 5.3.5” from the contract and add repairing an additional 2,000 square feet of deteriorated ceilings and walls in various locations. Appellant’s Vice President signed the modification. The modification included a release, in which appellant agreed “to release and discharge the Government, its officers, agents, and employees from any and all claims and demands whatsoever (present, past, or future) arising out of or incidental to the performance by the contractor of the work herein described.” The contract delivery time remained unchanged. (R4, tab 9)

9. Beginning in February 2016, the CO informed appellant that it was behind schedule in payment documents. The CO also informed appellant that it would retain 10% of the payment request until satisfactory progress was achieved. (R4, tab 11 at 534). At that time, CLIN 0001 was 49% complete, CLIN 0002 was 62% complete, CLIN 0003 was 20% complete, CLIN 0004 was 100% complete, CLIN 0005 was 96% complete, and CLIN 0006 had been removed from the task order in the first modification and was listed as 0% complete (R4, tab 11 at 536).

10. The government continued to withhold 10% of the payments for Pay Applications 9 through 30. 1 (R4, tab 11 at 645, 756, 964, 1064, 1166, 1268, 1370, 1471, 1565, 1665, 1752, 1838, 1925, 2010, 2096, 2188, 2280, 2378, 2395, 2486, and 2576). The government informed appellant in the payment documentation that it was assessing liquidated damages as early as April 20, 2016 (R4, tab 11 at 756). The government continued to inform appellant of the amount of liquidated damages for the remainder of the invoices, increasing the amount each invoice (R4, tab 11 at 964, 1064, 1166, 1268, 1370, 1471, 1565, 1665, 1752, 1838, 1925, 2010, 2096, 2188, 2280, 2378, 2395, 2486, and 2576).

11. According to the processed invoices, the government authorized payment for 100% completion of CLIN 0004 on May 18, 2015 (R4, tab 11 at 89, 91).

1 Pay application 11 was paid in full. 12. According to the processed invoices, the government authorized payment for 100% completion of CLIN 0002 on October 7, 2016 (R4, tab 11 at 1370, 1372).

13. According to the processed invoices, the government authorized payment for 100% completion of CLIN 0005 on November 15, 2016 (R4, tab 11 at 1471, 1473).

14. According to the processed invoices, the government authorized payment for 100% completion of CLIN 0003 on April 12, 2017 (R4, tab 11 at 1925, 1927).

15. According to the processed invoices, the government authorized payment for 99.7% completion of CLIN 0001 on May 17, 2018 (R4, tab 11 at 2576, 2578).

16. On November 7, 2018, the CO issued a final decision, Contracting Officer’s Final Decision (COFD) assessing liquidated damages because appellant allegedly failed to complete the work until August 7, 2018, 787 calendar days beyond the required contract completion date of June 11, 2016. The CO demanded $735 per day for 787 calendar days of delay, for a total of $578,445. The CO withheld the remaining $81,163.45 left on the contract and demanded payment from appellant in the amount of $496,281.55. (R4, tab 2)

17. By letter dated January 16, 2019, appellant timely appealed the assessment of liquidated damages and the Board docketed the appeal as ASBCA No. 61941.

18.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Applied Companies v. United States
144 F.3d 1470 (Federal Circuit, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Fortis Networks, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/fortis-networks-inc-asbca-2021.