City of Sherman v. Connor & Oliver

88 Tex. 35
Texas Supreme Court·Decided February 18, 1895·No. No. 171·Published·Cited by 29 cases

Opinion

DENMAN, Associate Justice.

—The record of this cause contains no statement of facts. The cause was tried before the court below without a jury. We will state such portions of the facts, found by [38]*38the court below, as are pertinent to the questions hereinafter discussed: In 1886, plaintiff in error, the city of Sherman, and defendants in error, Connor & Oliver, entered into a written contract. By said contract Connor & Oliver obligated themselves (1) “to well and truly construct and build and finish at their own expense, furnishing all necessary labor and materials for the same, a system of waterworks in and through the said city of Sherman, in accordance with the plans and specifications attached” to said contract, but not made a part of this record; (2) to secure at their expense an underground water supply equal in quantity to 250,000 United States gallons every twenty-four hours for a period of twelve months from the completion and acceptance of the said works; but if, after having used all reasonable means to develop the water supply at two different places, it were demonstrated that such underground supply could not be obtained at such places, then they were permitted to resort to a storage or overground supply; (3) upon the completion of the said works according to contract, to run and operate same for a period of thirty days at their own expense, and furnish a water supply for the city as a test of their efficiency, and upon completion of said test, if the said works were in all respects found complete in accordance with the terms of the contract, to turn them over to the city, whereupon the contract, so far as the erection and completion of the works as distinguished from the water supply was concerned, should be considered by both parties as complied with; (4) to furnish, as part of said system, two pumps, each to have a capacity of 500,000 gallons every twenty-four hours; (5) to deed to the city all land purchased and used in connection with the overground tank, together with the tank and all rights and easements acquired, in case it became necessary, under the terms of the contract, to resort to an overground supply to secure the requisite quantity of water; (6) to commence the work within thirty days, and complete the system within six months from the daté of the contract, said six months not to include the thirty days trial aforesaid.

By said contract, the city obligated itself (1) to furnish the ground for the standpipe; (2) to furnish the ground for the first set of wells to be dug in the attempt to secure an underground supply of water as aforesaid; and (3) to pay, “in consideration of the works above referred to being well and truly executed and completed in the manner-above specified,” the sum of $78,205, the greater portion thereof to ■be paid in installments as the work progressed, and the balance to be paid when the works were completed and accepted by the city.

In attempted compliance with the contract, Connor & Oliver caused to be erected and constructed in said city a sj^stem of waterworks, consisting of machinery and digging of certain wells for an underground supply of water, and about July, 1887, tendered said works to said •city, claiming same to be complete under the contract; whereupon the city refused to accept the works, because (1) the water supply was not sufficient, and (2) the test required by the contract had-not been made. [39]*39Connor & Oliver wholly failed to make the test required by the contract, or in fact any test, and not more than 50,000 gallons of water for each twenty-four hours could be procured from such works as were made by them.

Upon the refusal of the city to accept the works as a compliance with the contract as aforesaid, Connor & Oliver at once abandoned the further prosecution of the works, and did not procure an overground supply of water, or supply at any other place as required by the contract. '

During the progress of the work, and before it refused to accept same as above stated, the city had, in accordance with the contract, paid to Connor & Oliver various sums aggregating $43,400 of the entire contract price of the system. In September, 1887, the city entered upon and took possession of the system, and has since that date been using same.

In addition to the above the trial court found as follows:

“7. I find, that the fair and reasonable value of all material used and work done by defendants was, at the time aforesaid, when plaintiff (city) took possession of the works, $47,500, or in other words, that the sum just above -named was the fair and reasonable value of the entire waterworks system as constructed by defendants.
“8. I find, that if a system of waterworks furnishing said 250,000 gallons per twenty-four hours had been constructed by defendants as called for in the contract, that such works would have been worth, with such capacity, the sum of $100,000, provided the said amount of water could have been disposed of in said city; and' upon- this last point there is no evidence going to show whether such an amount of water could have been utilized in said city.”

Connor & Oliver in their pleadings sought to recover from the city of Sherman (1) the contract price of the system, alleging a full compliance with the contract; and (2) in the alternative, the reasonable value of the system actually erected, alleging that the city had taken possession of and was using same.

The city in its pleadings alleged noncompliance with the contract by Connor & Oliver, in that (1) the water supply obtained would not exceed 50,000 gallons every twenty-four hours, and- (2) they refused to make any test; that the works in the condition they were left by Con-nor & Oliver were not worth exceeding $30,000, -which was much less than the city had advanced during the progress of the work; that if the system of waterworks had been constructed with the water supply stipulated in the contract, it would have been worth $100,000; and sought to recover damages from Connor & Oliver for breach of said contract.

The trial court found, as a conclusion of law, that Connor & Oliver were entitled to recover of the city of Sherman the reasonable value of the works actually constructed, found by it to be $47,500, less the sums advanced by the city during the progress of the work, found by [40]*40it to be $43,400, thus making the recovery $4100, with interest to date of trial, amounting to $5149.50; and that the city of Sherman “ was not entitled to any recovery for damages in this case;” and thereupon rendered judgment in favor of Connor & Oliver against the city for $5149.50.

The city appealed to the Court of Civil Appeals, where the judgment of the lower court was affirmed, and the city has .brought the case to this court on writ of error, claiming that both of said courts erred in not allowing the city any damages against Connor & Oliver for breach of the contract.

The facts above stated having been found by the court below and adopted by the Court of Civil Appeals, must in this court, which has jurisdiction only of questions of law, be taken as true; but it is incumbent upon this court to determine the legal effect of such facts.

When the contract was entered into, each of the contracting parties acquired an interest therein and a legal right to demand of the other a substantial performance thereof; each had a chance of profit.

Free access — add to your briefcase to read the full text and ask questions with AI

City of Sherman v. Connor & Oliver, 88 Tex. 35 (Tex. 1895).

88 Tex. 35 (City of Sherman v. Connor & Oliver) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Elite Door & Trim, Inc. v. Tapia
355 S.W.3d 757 (Court of Appeals of Texas, 2011)
Lee Edward Morris v. State
Court of Appeals of Texas, 2010
Walker & Associates Surveying, Inc. v. Roberts
306 S.W.3d 839 (Court of Appeals of Texas, 2010)
Garcia v. Kastner Farms, Inc.
789 S.W.2d 656 (Court of Appeals of Texas, 1990)
Truly v. Austin
744 S.W.2d 934 (Texas Supreme Court, 1988)
Sitterle Properties v. Weidner
628 S.W.2d 127 (Court of Appeals of Texas, 1981)
Insurance Agency Managers v. Gonzales
578 S.W.2d 803 (Court of Appeals of Texas, 1979)
Davidson v. Clearman
391 S.W.2d 48 (Texas Supreme Court, 1965)
Humphrey v. Placid Oil Company
142 F. Supp. 246 (E.D. Texas, 1956)
Green MacHinery Co. v. Green
266 S.W.2d 279 (Court of Appeals of Texas, 1953)
Stanley v. Lieb
243 S.W.2d 227 (Court of Appeals of Texas, 1951)
Dallas Joint Stock Land Bank v. Colbert
127 S.W.2d 1004 (Court of Appeals of Texas, 1939)
Colbert v. Dallas Joint Stock Land Bank
102 S.W.2d 1031 (Texas Supreme Court, 1937)
United States Pipe & Foundry Co. v. City of Waco
100 S.W.2d 1099 (Court of Appeals of Texas, 1936)
Wilson v. Place
293 S.W. 322 (Court of Appeals of Texas, 1927)
Markham Irr. Co. v. Brown
286 S.W. 574 (Court of Appeals of Texas, 1926)
Harrell v. City of Lufkin
280 S.W. 174 (Texas Commission of Appeals, 1926)
Craven v. Davison
276 S.W. 193 (Texas Commission of Appeals, 1925)
Perry v. Smith
180 S.W. 160 (Court of Appeals of Texas, 1915)