Leeward Construction, Inc v. United States

CourtUnited States Court of Federal Claims
DecidedJuly 5, 2022
Docket22-374
StatusPublished

This text of Leeward Construction, Inc v. United States (Leeward Construction, Inc v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Leeward Construction, Inc v. United States, (uscfc 2022).

Opinion

IN THE UNITED STATES COURT OF FEDERAL CLAIMS ____________________________________ ) LEEWARD CONSTRUCTION, INC., ) ) Plaintiff, ) ) v. ) No. 22-374C ) THE UNITED STATES, ) Filed: June 17, 2022 ) Defendant, ) Reissued: July 5, 20221 ) and ) ) MOHAWK VALLEY MATERIALS, INC., ) ) Defendant-Intervenor. ) ____________________________________ )

OPINION AND ORDER

Plaintiff Leeward Construction, Inc. (“Leeward”) filed this bid protest challenging the

Army Corps of Engineers’ (“Army”) rejection of Leeward’s bid as non-responsive. Leeward

contends the Army erred as a matter of law in determining that a liability limitation in its bid bond

significantly departed from the solicitation’s requirements. Even if its bid bond were

noncompliant, it claims in the alternative that the Army acted arbitrarily and capriciously because

the alleged irregularity was immaterial and should have been waived, especially where the Army

waived an irregularity in the awardee’s bid. The Government and Defendant-Intervenor Mohawk

Valley Materials, Inc. (“Mohawk”) argue that the ambiguities of the bid bond language presented

a defense to enforcement and the Army reasonably relied on decisions by the Government

Accountability Office (“GAO”) finding the same bid bond defective.

1 The Court issued this opinion under seal on June 17, 2022, and directed the parties to file any proposed redactions by June 28, 2022. As the parties did not propose any redactions, the Court reissues the opinion publicly in full. Before the Court are the parties’ Cross-Motions for Judgment on the Administrative

Record. For the reasons discussed below, the Court finds that Leeward is not entitled to judgment

in its favor because: (1) its bid bond did not comply with the solicitation as a matter of law; (2) the

defect in its bid bond was material and not subject to waiver; (3) Leeward has not stated a valid

disparate evaluation challenge; (4) the defect in its bid bond created a defense to enforcement; and

(5) the Army acted rationally in relying on two prior GAO decisions addressing the same bid bond

language. Accordingly, the Government and Mohawk’s Motions are GRANTED, and Leeward’s

Motion is DENIED.

I. BACKGROUND

A. Findings of Fact

On October 27, 2021, the Army issued Invitation for Bids No. W912BU22B0003 (“IFB”)

for maintenance and modification of the General Edgar Jadwin Dam in Honesdale, Pennsylvania.

Admin. R. 263–95, ECF No. 17 (hereafter “AR”).2 The Army sought a contractor to replace the

“riprap” (i.e., stone facing) on the upstream face of the dam and install a new geosynthetic liner to

protect the dam from erosion. AR 309. The project was scheduled to last 455 days. AR 263.

Six bidders submitted bids in response to the IFB. AR 1362–63. Of the six bidders,

Leeward submitted the lowest bid at a cost of $3,887,454. Id. This was $1,112,401 less than the

next lowest proposal submitted by Mohawk. Id. Leeward is a heavy and highway commercial

construction contractor located in Honesdale, Pennsylvania. AR 1367–70. Leeward has been in

the construction business for over 28 years and holds pre-qualifications with state agencies to

perform earthwork, excavation, grading, and geotextile placement. AR 2015–16. The company

2 For ease of reference, citations to the Administrative Record refer to the bates-stamped page numbers rather than the ECF page numbers.

2 had over $44 million in sales in 2019 and 2020, and it has surety bonding up to $60 million. AR

1368, 1411.

The IFB incorporated Federal Acquisition Regulation (“FAR”) 52.228-1(e), which

requires bidders to include a bid guarantee (i.e., bid bond) with their submission. AR 290–91. Bid

bonds are designed to protect a contracting agency from an awardee’s default by compensating the

agency for costs incurred in reprocuring the contract or reissuing the award to a more expensive

runner-up. See Matter of: G2G, LLC, B-416502, 2018 WL 4679148, at *2 (Comp. Gen. Sept. 27,

2018); see also FAR 28.001 (defining “bid guarantee); FAR 28.101-2(b). The FAR’s bid

guarantee provision reads in relevant part:

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government . . . .

(c) The amount of the bid guarantee shall be _____ percent of the bid price or _____, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

FAR 52.228-1. The IFB set the bond amount at the lesser of 20 percent of the bid price or

$3 million. AR 291.

Before submitting its bid, Leeward sought clarification from the Army regarding the form

of its bid bond. AR 2535. On November 29, 2021, Leeward emailed the contracting specialist

who was listed in the IFB as the point of contact for requests for information to “confirm there is

3 not a special bid bond form” that the Army requires. Id.; see AR 269. The contracting specialist

followed up with a phone call to confirm that Leeward had all of the relevant IFB documents. AR

2569. Leeward sought additional clarification whether the Army would accept a bid bond on the

American Institute of Architects Document A310, 2010 edition (“AIA Form A310”). Id. The

contracting specialist responded that there was no special form for bidders to use, and they needed

only to include a bid bond of the requisite amount. Id. Leeward went on to submit a bid bond

with a penal sum of $777,490.94 (20 percent of its bid price) using the AIA Form A310. AR 1318.

Every other bidder used Standard Form 24 (“SF 24”), the bid bond form provided in FAR

28.106-1.3 AR 1289, 1298, 1306, 1334, 1348.

The AIA Form A310 used by Leeward includes a provision that limits the liability of the

bidder in the case of default to “the difference, not to exceed the amount of this Bond, between the

amount specified in said bid and such larger amount for which the [contracting agency] may in

good faith contract with another party[.]” AR 1318. In contrast, SF 24 states that “in the event of

failure to excuse such further contractual documents and give such bonds, [the Principal] pays the

Government for any cost of procuring the work which exceeds the amount of the bid.” AR 1334

(emphasis added). The AIA Form A310 also includes a savings clause, which states in full:

When this bond has been furnished to comply with a statutory or other legal requirement in the location of the Project, any provision in this Bond conflicting with said statutory or legal requirement shall be deemed deleted herefrom and provisions conforming to such statutory or other legal requirement shall be deemed incorporated herein. When so furnished, the intent is that this Bond shall be construed as a statutory bond and not as a common law bond.

AR 1318.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Camp v. Pitts
411 U.S. 138 (Supreme Court, 1973)
Callaway Golf Co. v. Acushnet Co.
576 F.3d 1331 (Federal Circuit, 2009)
Centech Group, Inc. v. United States
554 F.3d 1029 (Federal Circuit, 2009)
Zenon Environmental, Inc. v. United States Filter Corp.
506 F.3d 1370 (Federal Circuit, 2007)
Teg-Paradigm Environmental, Inc. v. United States
465 F.3d 1329 (Federal Circuit, 2006)
Cook Biotech Inc. v. ACell, Inc.
460 F.3d 1365 (Federal Circuit, 2006)
Balboa Insurance Company v. The United States
775 F.2d 1158 (Federal Circuit, 1985)
The United States v. The Boeing Company
802 F.2d 1390 (Federal Circuit, 1986)
A-Transport Northwest Co., Inc. v. United States
36 F.3d 1576 (Federal Circuit, 1994)
E.W. Bliss Company v. United States
77 F.3d 445 (Federal Circuit, 1996)
McAbee Construction, Inc. v. United States
97 F.3d 1431 (Federal Circuit, 1996)
Am-Pro Protective Agency, Inc. v. United States
281 F.3d 1234 (Federal Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Leeward Construction, Inc v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/leeward-construction-inc-v-united-states-uscfc-2022.