CTI/DC, Inc. v. Selective Insurance Co. of America

271 F. Supp. 2d 758, 2003 U.S. Dist. LEXIS 12593, 2003 WL 21689606
CourtDistrict Court, D. Maryland
DecidedJuly 15, 2003
DocketCIV.AW-03-599
StatusPublished

This text of 271 F. Supp. 2d 758 (CTI/DC, Inc. v. Selective Insurance Co. of America) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CTI/DC, Inc. v. Selective Insurance Co. of America, 271 F. Supp. 2d 758, 2003 U.S. Dist. LEXIS 12593, 2003 WL 21689606 (D. Md. 2003).

Opinion

MEMORANDUM OPINION

WILLIAMS, District Judge.

CTI/DC, Inc. (“Plaintiff’) filed suit against Selby Construction, Inc. (“Selby”) and Selective Insurance Company of America (“Selective”) alleging violations of Maryland’s “Little Miller Act”, Md. State Fin. & Proc.Code § 17-101, et seq., and breach of contract. Currently pending is Selective’s Motion to Dismiss the Amended Complaint [Paper No. 19] in which it seeks to have the claims against it dismissed on the ground that Plaintiff failed to abide by the statutory notice requirements of the Little Miller Act. 1 The motion has been fully briefed. No hearing is deemed necessary. See D. Md. R. 105.6. Upon review of the arguments made in support of, and opposition to, the motion, the Court will GRANT the motion to dismiss the Amended Complaint as against Selective.

/. FACTUAL BACKGROUND

The facts necessary for adjudication of the motion are drawn from the Amended Complaint. HR General Maintenance Corporation (“HRGM”) entered into a contract with an agency or instrumentality of Prince George’s County (“County”) to perform work on a construction project in Cheverly, Maryland. HRGM entered into another agreement with Selby to perform certain portions of the project.

Selective, the surety for the project, furnished the County with a payment bond (“bond”) naming HRGM as the principal and Selective as the surety. Plaintiff and Selby executed an agreement whereby Plaintiff would provide certain materials to Selby for the project. Selby failed to pay Plaintiff in accordance with the contract.

*760 All supplies and materials were last furnished to the project on October 1, 2002. On December 3, 2002, Plaintiff sent a letter to HRGM in which it stated the amount of the outstanding sum. On January 10, 2003, Plaintiff sent another letter to HRGM by certified mail in which it notified HRGM that it has provided a certain sum ($112, 263.97) of materials to Selby. It stated in the second letter that it planned to make a claim on the payment bond.

II. MOTION TO DISMISS

Under Fed. R. Civ. Proc. 12(b)(6), a court should not dismiss a complaint “unless it appears beyond doubt that the plaintiff can prove no set of facts in support of his claim which would entitle him to relief.” Conley v. Gibson, 355 U.S. 41, 45-46, 78 S.Ct. 99, 102, 2 L.Ed.2d 80 (1957). The function of a motion to dismiss for failure to state a claim is to.test the legal sufficiency of the complaint, and not the facts that support it. Neitzke v. Williams, 490 U.S. 319, 326-27, 109 S.Ct. 1827, 1832, 104 L.Ed.2d 338 (1989). The Fourth Circuit has recently stated,

[A] Rule 12(b)(6) motion should only be granted if, after accepting all well-pleaded allegations in the plaintiffs complaint as true and drawing all reasonable factual inferences from those facts in the plaintiffs favor, it appears certain that the plaintiff cannot prove any set of facts in support of his claim entitling him to relief.

Edwards v. City of Goldsboro, 178 F.3d 231, 244 (4th Cir.1999).

III. DISCUSSION

Selective argues that the Court should dismiss the claims against it because the notice that Plaintiff gave to HRGM on December 3, 2003 (“first letter”) was insufficient and the notice that Plaintiff gave to HRGM on January 10, 2003 (“second letter”) was untimely. Plaintiff concedes that the second letter was untimely under the ninety-day requirement of the Little Miller Act but argues that the parties impliedly intended to incorporate Maryland’s Mechanic’s Lien statute into the agreement; the Mechanic’s Lien statute carries a 120-day notice period. Alternatively, Plaintiff argues that the December 3, 2002 letter was sufficiently compliant with the notice requirements of the Little Miller Act.. Finding that the first letter was insufficient and that the second letter was untimely-(and that the two can not somehow be read together to constitute sufficient and timely notice)-the Court will grant the motion to dismiss.

A) January 10, 2003 Letter

Maryland’s Little Miller Act requires that before a public body awards a construction contract exceeding one-hundred thousand dollars, the contractor shall provide a payment security that meet the Act’s requirements. See Md. State Fin. & Proc.Code § 17-103. In order for a supplier to sue on a payment security, the supplier must follow the notice requirements of § 17-108. In particular, the Act requires that within ninety (90) days after the labor or materials for which the claim is made were supplied, the supplier must give notice to the “contractor”. See id. at § 17-108(b). The pertinent parts of the statute read:

(b) Payment owed by the subcontractor- (1) A supplier who has direct contractual relationship with a subcontractor ... of a contractor who has provided payment security but no contractual relationship with the contractor may sue on the security if the supplier gives written notice to the contractor within 90 days after the labor or materials for which the claim is made were last supplied in prosecution of work covered by the security. *761 (2) A notice under this subsection: (i) shall state with substantial accuracy the amount claimed and the person to whom the labor or material was supplied ....

Id. at § 17-108(b)(2)(i)-(ii).

Plaintiff appears to concede that the January 10, 2003 was given after the ninety-day period of the Little Miller Act. Nevertheless, Plaintiff asks the Court to apply the 120-day period of the Mechanic’s Lien statute. For the following reasons, the Court must reject Plaintiffs argument. First, nothing in the bond indicates that it was meant to be anything other than what it was: a payment bond in accordance with the Little Miller Act. The bond references the County and the public contract number, which tags the bond as one for a Little Miller Act requirement. Second, Plaintiff rests its entire argument on the bond’s reference to § 9-113 of the Real Property Article of the Maryland Code (the section that was formerly the Little Miller Act). This reference does not amount to an indication of the intent of the parties to extend the period from 90 to 120 days. 2 Finally, even if the parties refer to the Mechanic’s Lien statute, the section they referred to has no relevance to timing whatsoever. In sum, nothing supports the notion that parties intended to extend the 90-day period to 120 days. As such, the second letter was untimely.

B) December S, 2002 Letter

Although the December 3, 2003 letter was timely, Selective argues that it is insufficient in that (a) it failed to name the “person to whom the labor or material was supplied”, see id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conley v. Gibson
355 U.S. 41 (Supreme Court, 1957)
Neitzke v. Williams
490 U.S. 319 (Supreme Court, 1989)
Edwards v. City of Goldsboro
178 F.3d 231 (Fourth Circuit, 1999)
Westinghouse Electric Corp. v. Minnix
269 A.2d 580 (Court of Appeals of Maryland, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
271 F. Supp. 2d 758, 2003 U.S. Dist. LEXIS 12593, 2003 WL 21689606, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ctidc-inc-v-selective-insurance-co-of-america-mdd-2003.