Specialty Products & Insulation Co. v. St. Paul Fire & Marine Insurance

788 N.E.2d 604, 99 N.Y.2d 459, 758 N.Y.S.2d 255, 2003 N.Y. LEXIS 157
CourtNew York Court of Appeals
DecidedFebruary 18, 2003
StatusPublished
Cited by3 cases

This text of 788 N.E.2d 604 (Specialty Products & Insulation Co. v. St. Paul Fire & Marine Insurance) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Specialty Products & Insulation Co. v. St. Paul Fire & Marine Insurance, 788 N.E.2d 604, 99 N.Y.2d 459, 758 N.Y.S.2d 255, 2003 N.Y. LEXIS 157 (N.Y. 2003).

Opinion

OPINION OF THE COURT

Chief Judge Kaye.

Specialty Products & Insulation Company, a supplier to a subcontractor on a public improvement project, made several unreimbursed deliveries of materials under an open account arrangement with the subcontractor. In this appeal, we are asked to determine whether the supplier provided timely notice of its claim for payment for those deliveries under State Finance Law § 137 (3), so as to be entitled to payment under the labor and materials payment bond posted for the project. The issue boils down to whether, in an open account arrangement, the statutory 120-day notice period is measured from each delivery to the project or from the final delivery of materials for which the claim is made. We agree with the Appellate Division that the latter interpretation is correct.

I.

At issue is payment for deliveries made to a public improvement project involving additions and alterations to Broome County courts. Northland Associates, Inc., as general contractor, hired Klimchuck & Company, Inc. for a portion of the work. Klimchuck in turn arranged for the supply of materials by Specialty Products on an open account basis. Under the open account arrangement, Klimchuck placed a separate purchase order for each materials request and the supplier submitted a separate invoice for each corresponding delivery.

At Klimchuck’s request, Specialty Products periodically delivered supplies, including eight separately invoiced deliveries made between October 15 and December 17, 1998, totaling $48,578.34.1 On March 29, 1999, the supplier notified North-land that it had not been paid.

[462]*462Consistent with State Finance Law § 137, St. Paul Fire & Marine Insurance Company issued a payment bond on behalf of Northland and in favor of Broome County, as obligee, to secure payment for labor and materials provided to the project. After notifying Northland of the amounts owed, Specialty Products delivered a notice of claim to Northland and the Broome County Commissioners, and filed a proof of claim with St. Paul. The supplier then filed suit against St. Paul under the payment bond for the outstanding amounts. Northland later paid the supplier $12,780.43, the amount owed for materials furnished within 120 days preceding the March 29, 1999 notice, but refused to pay the balance. The parties cross-moved for summary judgment, contesting whether the supplier had provided timely notice under the State Finance Law for the remaining $35,797.91 relating to earlier deliveries.

Supreme Court granted St. Paul summary judgment and dismissed the complaint. The court interpreted the 120-day notice requirement of State Finance Law § 137 (3) to apply separately to each delivery, ruling that each invoice constituted a separate contract between the subcontractor and the supplier. The Appellate Division reversed and granted Specialty Products partial summary judgment, dismissing St. Paul’s affirmative defense related to timeliness of the notice. The Court rejected the trial court’s contract-based analysis, looking instead to decisions construing a similar provision in the Federal Miller Act (40 USC § 270a et seq.) and requiring notice of a claim within 120 days after final delivery. On remittal, Supreme Court granted Specialty Products summary judgment and entered a judgment in the amount of $35,797.91. This Court granted leave to appeal, and we now affirm.

II.

Section 137 of the State Finance Law protects the rights of persons furnishing labor or materials to contractors or subcontractors on a public improvement project to receive payment by requiring the posting of a payment bond. The statute provides laborers and material suppliers with a right to sue directly on the bond for amounts not paid by the contractor or subcontractor, as follows:

“Every person who has furnished labor or material, to the contractor or to a subcontractor of the [463]*463contractor, in the prosecution of the work provided for in the contract [for a State public improvement] and who has not been paid in full therefor before the expiration of a period of ninety days after the day on which the last of the labor was performed or material was furnished by him for which the claim is made, shall have the right to sue on such payment bond in his own name for the amount, or the balance thereof, unpaid at the time of commencement of the action * * (State Finance Law § 137 [3].)

Laborers and material suppliers who work for a subcontractor — rather than directly for the general contractor — are also permitted to assert claims under the payment bond but first must give the general contractor notice of their claim. Section 137 (3) requires that

“a person having a direct contractual relationship with a subcontractor of the contractor furnishing the payment bond but no contractual relationship express or implied with such contractor shall not have a right of action upon the bond unless he shall have given written notice to such contractor within one hundred twenty days from the date on which the last of the labor was performed or the last of the material was furnished, for which his claim is made * * * ” (emphasis added).

The statute strongly resembles its model, the Federal Miller Act (40 USC § 270a et seq.), both with the same remedial purpose. In particular, since 1935 the Miller Act has contained a parallel notice provision but requires that notice be given within 90 rather than 120 days after the date the last of the material was supplied or labor furnished (compare State Finance Law § 137 [3] with 40 USC § 270b [a]).

The similarity between the two laws did not always exist. As originally enacted in 1938, the State Finance Law contained more rigorous preconditions for a laborer or material supplier seeking to recover under a payment bond. The statute required suppliers first to file and enforce mechanics’ liens under the Lien Law, and laborers to file and enforce either mechanics’ liens or claims for unpaid wages under the Labor Law (see L 1938, ch 707).

In 1964, at the recommendation of the Law Revision Commission, the State Finance Law was amended to more closely [464]*464follow the federal statute. In particular, the presuit conditions were amended to permit a laborer or material supplier to sue on the performance bond for unpaid amounts — without first exhausting Lien Law and Labor Law remedies — starting 90 days after the last of the labor was performed or material furnished. A person who had no direct contractual relationship with the contractor was required to provide written notice of a claim within 90 days from the date on which the last of the labor was performed, or the last of the material was furnished, for which the claim is made (L 1964, ch 700).2

The Law Revision Commission encouraged the adoption of the modern section 137 (3) procedures because, in its view, the prior statutory scheme provided only limited assurance of prompt payment to laborers and suppliers. The Commission observed that in New York a payment bond claim served as a “remedy of last resort” after other sources of recovery were exhausted or shown to be futile, and the Lien Law limitations period indirectly barred claims later asserted against a payment bond (see 1963 Report of NY Law Rev Commn, at 101).3

The 1964 bill received wide support.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J. Reed Constructors, Inc. v. Roofing Supply Group, L.L.C.
135 So. 3d 752 (Louisiana Court of Appeal, 2013)
L & W Supply Corp. v. A.D.F. Drywall, Inc.
55 A.D.3d 1026 (Appellate Division of the Supreme Court of New York, 2008)
Triboro Hardware & Supply Corp. v. Federal Insurance
45 A.D.3d 134 (Appellate Division of the Supreme Court of New York, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
788 N.E.2d 604, 99 N.Y.2d 459, 758 N.Y.S.2d 255, 2003 N.Y. LEXIS 157, Counsel Stack Legal Research, https://law.counselstack.com/opinion/specialty-products-insulation-co-v-st-paul-fire-marine-insurance-ny-2003.