United States Ex Rel. I. Burack, Inc. v. Sovereign Construction Co.

338 F. Supp. 657, 1972 U.S. Dist. LEXIS 15328
CourtDistrict Court, S.D. New York
DecidedJanuary 31, 1972
Docket64 Civ. 382
StatusPublished
Cited by17 cases

This text of 338 F. Supp. 657 (United States Ex Rel. I. Burack, Inc. v. Sovereign Construction Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. I. Burack, Inc. v. Sovereign Construction Co., 338 F. Supp. 657, 1972 U.S. Dist. LEXIS 15328 (S.D.N.Y. 1972).

Opinion

CANNELLA, District Judge.

Action brought pursuant to the Miller Act, 40 U.S.C. § 270a et seq., to recover the purchase price of materials furnished by the use plaintiff to defendant Kings Ferry Corporation for the construction of a Cadet library. Judgment shall be entered in favor of the use plaintiff.

On December 28, 1961, defendant Sovereign Construction Company, Ltd. [hereinafter “Sovereign”] entered into a written contract 1 [hereinafter “prime contract”] with the United States of America to furnish all of the labor and materials and to perform all of the work required to construct a Cadet library at the United States Military Academy at West Point, New York [hereinafter “the project”]. On that same day, defendant Sovereign, as principal, and defendant Continental Casualty Company, as surety, furnished a payment bond to the United States of America in the sum of $1,458,987.60 to secure the prompt payment by Sovereign to all persons supplying labor and material in the prosecution of the work provided for in the prime contract. 2 Thereafter, on January 5, 1962, Sovereign entered into a subcontract with defendant Kings Ferry Corporation [hereinafter “Kings Ferry”] wherein the subcontractor agreed, inter alia, to complete a portion of the mechanical work required under the prime contract. 3 In order to perform under the subcontract, Kings Ferry ordered various materials between February 13, 1962 and August 29, 1963 from the use plaintiff, I. Burack, Inc. [hereinafter “Burack”]. When the defendants refused to pay for certain of these materials, Burack gave written notice to them, in accordance with 40 U.S.C. § 270b(a), 4 that they owed $7,932.65, with interest. The defendants again refused to pay and this action ensued. 5

This court has jurisdiction under 40 U.S.C. § 270a et seq.

The defendants contend that Burack should be estopped from making any claim for payment because it violated the terms of a guarantee agreement that it made with Sovereign. The court finds that Sovereign agreed on April 3, 1962 to guarantee payment up to $20,000 for material furnished by Burack to Kings Ferry 6 and that on April 18, 1963 the guarantee was increased to $35,000. 7 However, in both cases Burack refused to signify its assent to the terms contained in the guarantees by failing to sign them as requested by Sovereign. *660 In addition, Burack specifically disagreed with Sovereign's interpretation of the first guarantee. 8

Under certain factual circumstances, estoppel may be a defense in a Miller Act case. See, e. g., United States for Use and Benefit of Gulfport Piping Co. v. Monaco & Son, Inc., 336 F.2d 636 (4th Cir. 1964). However, the court is persuaded that a request for a guarantee as additional security is not such a circumstance. Cf. United States for Use of Friedrich Refrigerators, Inc. v. Forrester, 441 F.2d 779, 782-783 (5th Cir. 1971); United States for Use and Benefit of Clark-Fontana Paint Co. v. Glassman Construction Co., 397 F.2d 8, 11 (4th Cir. 1968); United States for Use of Koppers Co. v. Five Boro Construction Corp., 310 F.2d 701, 703 (4th Cir. 1962). The defendants further contend that Burack should be estopped because it failed to send a substantial number of invoices to Sovereign on current shipments. The court finds, however, that Burack at no time specifically agreed to furnish this information and was under no duty to do so. Cf. United States ex rel. Westinghouse Electric v. James Stewart Co., 336 F.2d 777 (9th Cir. 1964). The court therefore concludes that under these circumstances Burack is not to be estopped from asserting its claim. See, e. g., United States for Use and Benefit of Lincoln Electric Products Co. v. Greene Electrical Service of Long Island, Inc., 379 F. 2d 207, 210 (2d Cir. 1967).

The defendants also argue that Burack has failed to prove that the material for which claim is made was actually delivered to and intended for the project. Kings Ferry normally ordered materials from Burack by telephone and either sent down workers employed on the project to pick them up or used Burack’s drivers to deliver them to the jobsite. 9 The court concludes that Burack furnished these materials to Kings Ferry in good faith and under the reasonable belief that they were intended for use in the prosecution of the work on the project and that it therefore need not show actual delivery to and incorporation on the jobsite. See, e. g., United States for Use and Benefit of J. P. Byrne & Co. v. Fire Association, 260 F. 2d 541, 545 (2d Cir. 1958). Moreover, the court finds no merit to the defendants’ assertion that the amount claimed does not represent the fair and reasonable value of these materials. Cf. Continental Casualty Co. v. Allsop Lumber Co., 336 F.2d 445, 455 (8th Cir. 1964), cert. denied, 379 U.S. 968, 85 S.Ct. 662, 13 L.Ed.2d 561 (1965); Geis Construction Co. v. United States for Use of Tom Igel Co., 243 F.2d 568 (6th Cir. 1957) (per curiam).

The defendants contend that the notice by Burack on September 23, 1963 was untimely. Under the Miller Act, notice must be made within ninety days from the date on which the use plaintiff supplied the last of the material for which claim is made. See 40 U.S.C. § 270b(a). The court finds that on May 10, 1962 Kings Ferry ordered certain materials for the project under Purchase Order # 6204-40-1 for a sum of $3,987.50. 10 The court further finds that deliveries of a portion of this order were made to the project between April 23, 1963 and August 21, 1963, totalling $3,198.25. 11 Proper notice was given *661

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Specialty Products & Insulation Co. v. St. Paul Fire & Marine Insurance
788 N.E.2d 604 (New York Court of Appeals, 2003)
Specialty Products & Insulation Co. v. St. Paul Fire & Marine Insurance
287 A.D.2d 852 (Appellate Division of the Supreme Court of New York, 2001)
Granite Constr. Co. v. Am. Motorists Ins. Co.
29 Cal. App. 4th 658 (California Court of Appeal, 1994)
United States v. William L. Crow Construction Co.
826 F. Supp. 647 (E.D. New York, 1993)
DIC COM'L CONST. CORP. v. Knight Erec. & Fab.
547 So. 2d 977 (District Court of Appeal of Florida, 1989)
D.I.C. Commercial Construction Corp. v. Knight Erection & Fabrication Inc.
547 So. 2d 977 (District Court of Appeal of Florida, 1989)
United States v. Arundel Corp.
814 F.2d 193 (Fifth Circuit, 1987)
Coast Electric Co. v. Industrial Indemnity Co.
144 Cal. App. 3d 879 (California Court of Appeal, 1983)
Ibex Industries, Inc. v. Coast Line Waterproofing
563 F. Supp. 1142 (District of Columbia, 1983)
J. M. Lynne Co. v. P.B.S., Inc.
11 Pa. D. & C.3d 431 (Philadelphia County Court of Common Pleas, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
338 F. Supp. 657, 1972 U.S. Dist. LEXIS 15328, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-i-burack-inc-v-sovereign-construction-co-nysd-1972.