United States of America, for the Use and Benefit of Balzer Pacific Equipment Company v. Fidelity and Deposit Company of Maryland

895 F.2d 546, 36 Cont. Cas. Fed. 75,792, 1990 U.S. App. LEXIS 1073, 1990 WL 6377
CourtCourt of Appeals for the Ninth Circuit
DecidedJanuary 31, 1990
Docket88-15464
StatusPublished
Cited by6 cases

This text of 895 F.2d 546 (United States of America, for the Use and Benefit of Balzer Pacific Equipment Company v. Fidelity and Deposit Company of Maryland) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, for the Use and Benefit of Balzer Pacific Equipment Company v. Fidelity and Deposit Company of Maryland, 895 F.2d 546, 36 Cont. Cas. Fed. 75,792, 1990 U.S. App. LEXIS 1073, 1990 WL 6377 (9th Cir. 1990).

Opinions

SNEED, Circuit Judge:

Fidelity and Deposit Company of Maryland (F & D) appeals from a jury verdict of $66,082.54 in favor of Balzer Pacific Equipment Company (Balzer). F & D asserts that the trial court erred in denying its motion for a directed verdict, as well as in denying its motion for judgment n.o.v., and, alternatively, for a new trial. We reverse and remand for a new trial.

I.

JURISDICTION

Jurisdiction in the district court resides in 28 U.S.C. § 1331 and we have jurisdiction under 28 U.S.C. § 1291.

II.

FACTS AND PROCEEDINGS BELOW

Balzer brought this action under the Miller Act, 40 U.S.C. §§ 270a-270d, against F & D on payment bonds issued by F & D in respect to four contracts between S & S Contracting, Inc. (S & S) and the United States to be performed principally in Guam. These contracts were for construction of (1) an airport, (2) a highway, (3) a park memorial, and (4) work for the Navy in Midway. Balzer furnished material to S & S to be used both in connection with these contracts and for several contracts S & S had with parties other than instrumentalities of the United States. S & S became insolvent and was unable to meet its obligations owed to Balzer. This action ensued.

To perform its federal and non-federal projects, S & S needed to mine and process limestone on Guam as a component of pavement. S & S thereupon moved a rock crusher from Samoa to Guam that it had previously purchased from Balzer. S & S also bought from Balzer an asphalt plant and additional crushing equipment that it placed at a limestone quarry in Guam. S & S’s operations also employed a cement mixer and two Bomag rollers which were mobile and taken to the job sites. Balzer furnished material and parts for each of these pieces of equipment in amounts stipulated to by Balzer and F & D.

The difficulty which provides the genesis of this lawsuit is that neither Balzer nor S & S attempted to maintain any records that would enable the apportionment of specific materials and parts to each specific contract as to which F & D issued its payment bonds. Balzer insists that such apportionment is not necessary; it is enough for it to show that it reasonably believed that all the stipulated items were to be used in bonded federal projects. F & D argues that there must be an apportionment of specific materials to each contract before it becomes liable on any payment bond issued as to the four federal projects.

The district court ruled in favor of Balzer and incorporated that ruling in its instructions to the jury. E.g. Instructions No. 4,1 5,2 6,3 and 7.4 In its “Memorandum and [548]*548Order,” the court concluded “that to require Balzer to prove that it had a reasonable belief that the use of each item supplied was for one specific job of the four contracts, or to apportion its claims among the four contracts, would place an insurmountable burden on Balzer in light of the record keeping of S & S Contracting and the nature of the use to which Balzer’s equipment or materials were put.”

F & D argues vigorously that apportionment to each bonded contract is required by the language of the Miller Act, the cases interpreting the Act, and the need to preclude “cross-collateralization.” Cross-collateralization occurs when the protection afforded by one bond is available to provide protection with respect to supplies in fact furnished on a different contract in excess of the coverage provided by the bond applicable to this latter contract.

III.

STANDARD OF REVIEW

The issues presented by this appeal are questions of law; therefore, our review is de novo. United States v. McConney, 728 F.2d 1195, 1201 (9th Cir.) (en banc), cert. denied, 469 U.S. 824, 105 S.Ct. 101, 83 L.Ed.2d 46 (1984).

IV.

DISCUSSION

A. The Miller Act

Quite correctly F & D points out that the Miller Act’s language speaks in the singular when using the term “payment bond” and “contract,” see 40 U.S.C. § 270a, b, and c, and that no provision exists therein to aggregate the amounts of the bonds applicable to several contracts even when such contracts pertain to related projects. Claims that exceed the penal sum of a particular bond must be paid on a pro rata basis. See generally Pennsylvania Fire Ins. Co. v. American Airlines, Inc., 180 F.Supp. 239 (E.D.N.Y.1960).

Balzer argues to the contrary on the basis of cases that have held that the supplier of materials need not prove that all such materials were actually delivered to the site of the bonded work and incorporated therein so long as it had a good faith [549]*549and reasonable belief that the material was intended for use in the bonded federal project. See, e.g., United States ex rel. Martin Steel Constructors, Inc. v. Avanti Constructors, Inc., 750 F.2d 759, 761 (9th Cir.1984), cert. denied, 474 U.S. 817, 106 S.Ct. 60, 88 L.Ed.2d 49 (1985) (hereinafter “Martin Steel”)', United States ex rel. I. Burack, Inc. v. Sovereign Constr. Co., 338 F.Supp. 657, 660 (S.D.N.Y.1972); United States ex rel. Tom P. McDermott, Inc. v. Woods Constr. Co., 224 F.Supp. 406, 409 (N.D.Okla.1963).

The district court was partially correct when it incorporated the “reasonable good faith” standard in its jury charges. See, e.g., United States ex rel. Krupp Steel Prod., Inc. v. Aetna Ins. Co., 831 F.2d 978, 980 (11th Cir.1987) (finding that supplier delivered goods to job site in good-faith belief that they were being used for bonded project). For example, in “Instruction No. 4,” the jury was told that Balzer was required to show, among other things, that it “in good faith had reason to believe that the materials were intended for the work specified in the contracts and covered by Fidelity and Deposit’s bonds.” (Emphasis added.)

The italicized words reveal the heart of this case. The error of Balzer and the trial court consists of expanding the “reasonable good faith” standard to embrace all possibly applicable payment bonds issued by the same surety rather than restricting it to resolve doubts about whether the supplies were used on the specific bonded job, or on a job bonded by another surety, or on an unbonded one. To extend the “reasonable good faith” standard in this manner alters each of the contracts entered into by the surety and converts them into one contract that provides for a penal sum equal to the aggregate sum of the several bonds.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States ex rel. Krol v. Arch Insurance
46 F. Supp. 3d 347 (S.D. New York, 2014)
Heath v. Heath
122 Cal. App. 4th 444 (California Court of Appeal, 2004)
Syro Steel Co. v. Hubbell Highway Signs, Inc.
424 S.E.2d 208 (Court of Appeals of North Carolina, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
895 F.2d 546, 36 Cont. Cas. Fed. 75,792, 1990 U.S. App. LEXIS 1073, 1990 WL 6377, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-balzer-pacific-ca9-1990.