United States Ex Rel. Hussmann Corp. v. Fidelity & Deposit Co.

999 F. Supp. 734, 1998 U.S. Dist. LEXIS 4330
CourtDistrict Court, D. New Jersey
DecidedMarch 30, 1998
DocketCivil Action 97-2559
StatusPublished
Cited by8 cases

This text of 999 F. Supp. 734 (United States Ex Rel. Hussmann Corp. v. Fidelity & Deposit Co.) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Hussmann Corp. v. Fidelity & Deposit Co., 999 F. Supp. 734, 1998 U.S. Dist. LEXIS 4330 (D.N.J. 1998).

Opinion

OPINION

IRENAS, District Judge.

Plaintiff Hussmann Corporation (“Hussmann”), a subcontractor, instituted this suit pursuant to the Miller Act, 40 U.S.C. § 270a et seq., against defendant Fidelity & Deposit *735 Company of Maryland (“Fidelity & Deposit”), the surety for C. Pyramid Enterprises, Inc. (“C. Pyramid”), the general contractor on a federal government contract. The Miller Act is federal legislation that provides a remedial cause of action for contract disputes involving federal building projects. Both Hussmann and Fidelity & Deposit have moved for summary judgment. Because we find that Hussmann’s Miller Act claim is timely and that there are genuine issues of material fact regarding Hussmann’s entitlement to payment from Fidelity & Deposit as surety for C. Pyramid, we will deny both parties’ motions for summary judgment and allow this case to proceed to trial.

I. BACKGROUND

On July 1, 1994, the Defense Commissary Agency, AETC/LGCR Contracting Squadron (“DeCA”) issued an Invitation For Bid (“IFB”), soliciting the services of prime contractors for the construction, renovation and complete alteration of a new supermarket to be built within the Commissary building at McGuire Air Force Base in Wrightstown, New Jersey (the “Commissary”). Craddock Aff. at ¶ 8; Exh. A to Craddock Aff. The supermarket was to be a large facility with over twenty check-out counters. St. Lawrence Aff. at ¶ 5. Building the new supermarket required new renovations to an existing Commissary facility and the installation of a new product refrigeration system within the facility itself. Craddock Aff. at ¶ 7.

In response to DeCA’s IFB, C. Pyramid prepared and submitted an August 23, 1994 bid to perform the construction, renovation and complete “refitting” of the supermarket within the Commissary. Craddock Aff. at ¶ 11; Exh. C to Craddock Aff. As C. Pyramid was the lowest responsible bidder, DeCA issued a Notice of Award to C. Pyramid for the Commissary project on October 12,1994. Exh. D to Craddock Aff. C. Pyramid thereafter became the prime contractor on BBA Project Number 795.04 (the “Government Contract”). As required by § 270a of the Miller Act, Fidelity & Deposit became C. Pyramid’s payment and performance surety. Craddock Aff. at ¶ 2.

After C. Pyramid was awarded the Government Contract, Mark Craddock, C. Pyramid’s Senior Vice .President, began negotiating the terms of an agreement for the design, engineering, and manufacturing of all refrigeration equipment to be installed at the Commissary with representatives of Tyler Refrigeration, Hill Refrigeration and Hussmann. Craddock Aff. at ¶ 13. As a result of Hussmann’s 60 years of experience in the refrigeration industry and C. Pyramid’s belief that Hussmann would best be able to provide technical support and consulting guidance, C. Pyramid chose to use Hussmann as the supplier of refrigeration equipment needed under the Government Contract. Craddock Aff. at ¶ 15.

On October 27, 1994, C. Pyramid and Hussmann entered into a written agreement in the form of a purchase order (the “Purchase Order”) whereby Hussmann agreed to supply certain commercial refrigeration equipment to C. Pyramid for the price of $700,000. Smith Aff. at ¶5. The Purchase Order states, and the parties essentially agree, that Hussmann’s contractual obligations' included the design and manufacturing of (1) the product refrigeration system, (2) the refrigeration unit coolers, (3) the air cool condensers, (4) the compressor systems, (5) the insulated cold storage rooms, and (6) a refrigeration monitoring system. Purchase Order, Exh. E to Craddock Aff. The parties dispute, however, whether Hussmann had any further obligations pursuant to the Purchase Order.

Hussmann shipped the refrigeration equipment specified in the Purchase Order directly to the Commissary, care of C. Pyramid, as required under the Purchase Order. The equipment was shipped on the following dates:.

Racks/Refrigeration Machines March 31,1995
Condensing Units April 19,1995
Coolers ■ September 13, 1995
Cases April 25,1995 September 13, 1995 October 6,1995 November 14,1995
Evaporator Coils February 14,1995
Condensers/Roof Equipment April 5,1995
Comtrol Controls May 4,1995
Miscellaneous Buyouts November 8,1995

Craddock Aff. at If 46; May 31, 1996 letter from Hussmann to DeCA, Exh. C to Supp. *736 Smith Aff. Thus, the last refrigeration equipment shipped by Hussmann, a delivery of cases, was shipped on November 14, 1995. Although it is unclear from the record on what date the government began operating the refrigeration system, it appears that by June 13, 1996, 90% of the system was in operation. June 13, 1996 Letter from Craddock to Smith, Exh. F to Craddock Aff.

In the summer of 1996, C. Pyramid requested the close-out items under the Purchase Order. Hussmann states that closeout items are typically provided as the final step in an “Equipment Only” job, and claims that under the Purchase Order, the close-out items consisted of operation and maintenance (“0 & M”) manuals for the refrigeration equipment, final drawings of the refrigeration equipment as installed at the Commissary, and on-site equipment service and maintenance training. Smith Aff. at ¶ 11. Fidelity & Deposit disputes that the supply of close-out items comprised the final step of the Purchase Order. Although the Purchase Order does not expressly state that 0 & M manuals or any other close-out items must be supplied as the final step under the contact, it does include a provision referencing a specification of the Government Contract which discusses operating and maintenance instructions. The first page of the Purchase Order states “ALL MATERIALS TO CONFORM TO SPEC. SECTIONS” followed by various specification section numbers. One of the numbers listed, 15688, has a section, “ § 1.06. Operating and Maintenance Instructions,” which details the operating and maintenance instructions required by the government. Section 1.06 states:

A____ The instructions shall include, but shall not be limited to, the following:
1. System layout showing piping, valves, and controls. One set of reproducible (mylar type) Record Drawings shall be provided for local engineer files, one set shall to [sic] go to HQ DeCA/ DFDM
2. Approved wiring and control diagrams with data to explain the detañed operation and control of each component. Include interface and connection to the refrigeration monitoring control systems (ROMS).
3. A control sequence describing system start-up, operation and shut-down.
4. Operating and maintenance (including lubrication) instructions for each piece of equipment.
5. Display case manufacturer’s buUetins, catalogue cuts and descriptive data, installation and operation data.
6. Parts lists and recommended spare parts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
999 F. Supp. 734, 1998 U.S. Dist. LEXIS 4330, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-hussmann-corp-v-fidelity-deposit-co-njd-1998.