United Structures of America, Inc. v. G.R.G. Engineering

9 F.3d 996
CourtCourt of Appeals for the First Circuit
DecidedNovember 18, 1993
Docket93-1354
StatusPublished
Cited by19 cases

This text of 9 F.3d 996 (United Structures of America, Inc. v. G.R.G. Engineering) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Structures of America, Inc. v. G.R.G. Engineering, 9 F.3d 996 (1st Cir. 1993).

Opinion

BREYER, Chief Judge.

The plaintiff, having supplied steel to a now bankrupt subcontractor, has sued the general contractor, seeking to recover payment for the steel from the bond that a federal statute, the Miller Act, requires certain general contractors to provide. 40 U.S.C. §§ 270a-270b. The general contractor says the steel was defective, and it wants to deduct from the promised purchase price the amount that it says it had to spend to cure the defects. The district court, relying upon a Ninth Circuit case, United States ex *997 rel. Martin Steel Constructors v. Avanti Steel Constructors, 750 F.2d 759 (9th Cir.1984), ce rt. denied, 474 U.S. 817, 106 S.Ct. 60, 88 L.Ed.2d 49 (1985), held that where the supplier has a contract with a subcontractor but not with the general contractor, the Miller Act forbids the general contractor from taking such “offsetting” deductions. We disagree with the Ninth Circuit. We therefore vacate the district court’s judgment.

I

Background

The Miller Act requires general contractors working on federal government projects to furnish a payment bond “for the protection of all persons supplying labor and material” to the project. 40 U.S.C. § 270a(a)(2). It permits a supplier who has a “direct contractual relationship with a subcontractor but no contractual relationship ... with the contractor furnishing” the bond to sue on the bond for “the balance ... unpaid at the time of institution” of the suit, and to recover “judgment for the sum or sums justly due him,” as long as he complies with certain notice requirements. Id. § 270b(a). Puerto Rico’s “Little Miller Act” sets up a similar scheme for work on projects undertaken by the Puerto Rican government. 22 L.P.R.A. §§ 47, 51.

The plaintiff, United Structures of America (“United”), supplied steel to a subcontractor on two projects, one for the United States government at Roosevelt Roads Naval Station, the other for the Puerto Rican government at Hato Rey Police Headquarters. Defendant G.R.G. Engineering (“GRG”) was the general contractor on both projects. The subcontractor did not pay United in full. When the subcontractor went bankrupt, United gave GRG proper notice, and then sued GRG (and GRG’s insurer) on the payment bond for the amounts it believed were still due, approximately $105,000 for the Roosevelt Roads project and $177,000 for the police station project.

United moved for summary judgment, attaching various bills and receipts in support of its claims. GRG opposed the summary judgment motion. An affidavit (and a few working papers) of Luis Marin Aponte, a GRG partner and licensed engineer, constituted GRG’s only effort to “set forth specific facts showing that there is a genuine issue” that might warrant a trial, Fed.R.Civ.P. 56(e). Marin’s affidavit said that GRG did not owe United any money because (1) United engaged in a fraudulent billing practice known as “front loading”; (2) GRG had to spend “$88,887 ... due to” United’s “noncompliance with the specifications of the equipment supplied” for the Roosevelt Roads project; and (8) GRG had to spend an additional “$107,622 ... to correct defects and/or deficiencies in the materials” that United “furnished” for the police station project.

The district court granted summary judgment in favor of United, holding (1) that this affidavit failed to provide, or to point to, any specific factual evidence supporting GRG’s “front loading” theory; (2) that the evidence regarding allegedly defective steel was irrelevant because the law does not give GRG “the right to assert a set-off defense”; and (3) that GRG, in any event, had not “offered specific evidence in support of’ its allegations, “for example, an affidavit prepared by an engineer testifying that the materials were indeed defective.”

GRG then moved for reconsideration. It pointed out that Marin, its affiant, was indeed a licensed engineer, and it provided a few additional documents and bills suggesting possible defects and related costs. The district court, although it acknowledged Marin’s professional qualifications, denied the motion for reconsideration, solely on the basis of the Ninth Circuit’s holding that the Miller Act does not “allow[ ] a set-off defense by a general contractor not in privity with” a supplier. Avanti, 750 F.2d at 762.

GRG now appeals, claiming primarily that the district court and the Ninth Circuit have not correctly interpreted the Miller Act with regard to the “set-off’ issue. We agree with GRG.

II

Analyzing the “Set-off”

In Avanti the Ninth Circuit considered a set of facts virtually identical to the facts *998 before us. A subcontractor on a government project bought steel from a supplier; the subcontractor went bankrupt; the supplier sued the general contractor on its Miller Act bond; and the general contractor asserted, as a defense, a claim of damages arising from “late and defective shipments.” Avanti, 750 F.2d at 760. The Ninth Circuit held that “a set-off defense is not available in a Miller Act claim in the absence of privity.” It added that “allowing a set-off defense by a general contractor not in privity with [the supplier] would unduly burden the enforcement of the rights created by the Act.” Id. at 762.

We disagree with the Ninth Circuit. We believe it appropriate to draw a distinction that the Ninth Circuit did not draw, namely a technical distinction between what the law normally calls a “setoff’ (or “set-off,” or “offset”), and what it calls “recoupment.” The law dictionary defines a “setoff’ as a “counter-claim demand which defendant holds against plaintiff, arising out of a transaction extrinsic of 'plaintiffs cause of action.” Black’s Law Dictionary 1230 (5th ed. 1979) (emphasis added). If Smith sues Jones for $10,000 for grain that Smith supplied, and Jones seeks to reduce the judgment by $5,000 representing Smith’s (unrelated) unpaid rental of Jones’ summer cottage, Jones is seeking a setoff. “Recoupment,” on the other hand, is “a reduction or rebate by the defendant of part of the plaintiffs claim because of a right in the defendant arising out of the same transaction. ” Id. at 1147 (emphasis added). If Smith sues Jones for $10,-000 for grain that Smith supplied, and Jones seeks to reduce the judgment by $5,000 representing Jones’ expenditure to dry out Smith’s (defectively) wet grain (or the cost of buying replacement grain, or the grain’s lost value), Jones is seeking a recoupment.

This distinction, although somewhat technical, is well established in the law. See, e.g., In re B &L Oil Co., 782 F.2d 155, 157 (10th Cir.1986); 1 David G. Epstein et al., Bankruptcy § 6-45, at 703 (1992) (“setoff involves mutual debts arising from unrelated transactions

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
M.D. Florida, 2026
Gaddis v. US Bank
D. Arizona, 2025
Gill v. Holbrook
W.D. Washington, 2023
Federal Deposit Insurance Corp. v. Arrillaga-Torréns
212 F. Supp. 3d 312 (D. Puerto Rico, 2016)
Finish Line v. J.F. Pate & Associates Contractors, Inc.
90 So. 3d 749 (Court of Civil Appeals of Alabama, 2012)
Transfer My Timeshares v Selway
2009 DNH 153 (D. New Hampshire, 2009)
United States v. Cook, John A.
Seventh Circuit, 2005
United States v. John A. Cook
406 F.3d 485 (Seventh Circuit, 2005)
Westinghouse Credit Corp. v. D'Urso
278 F.3d 138 (Second Circuit, 2002)
Clemente v. Comm. of MA
97 F.3d 1445 (First Circuit, 1996)
Botelho v. Citicorp Mortgage, Inc. (In Re Botelho)
195 B.R. 558 (D. Massachusetts, 1996)
FDIC v. DiStefano
839 F. Supp. 110 (D. Rhode Island, 1993)
Federal Deposit Insurance v. diStefano
839 F. Supp. 110 (D. Rhode Island, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
9 F.3d 996, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-structures-of-america-inc-v-grg-engineering-ca1-1993.