United States Ex Rel. Accoustical Concepts, Inc. v. Travelers Casualty & Surety Co. of America

635 F. Supp. 2d 434, 2009 U.S. Dist. LEXIS 61939, 2009 WL 2156909
CourtDistrict Court, E.D. Virginia
DecidedJuly 17, 2009
Docket1:08-mj-01030
StatusPublished
Cited by8 cases

This text of 635 F. Supp. 2d 434 (United States Ex Rel. Accoustical Concepts, Inc. v. Travelers Casualty & Surety Co. of America) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Accoustical Concepts, Inc. v. Travelers Casualty & Surety Co. of America, 635 F. Supp. 2d 434, 2009 U.S. Dist. LEXIS 61939, 2009 WL 2156909 (E.D. Va. 2009).

Opinion

MEMORANDUM OPINION

T.S. ELLIS, III, District Judge.

Plaintiff, a subcontractor, brings this Miller Act, 40 U.S.C. § 3131 et seq., suit against the co-sureties on payment bonds to recover for work performed on two federal construction projects pursuant to contracts with the projects’ general contractor. Relying on the Miller Act’s purpose of ensuring subcontractors’ prompt payment for their work on federal construction projects, plaintiff sought summary judgment on the ground that it has not been paid for its completed work furnishing labor and materials on the two federal projects. Defendants opposed summary judgment, arguing that whether plaintiff has been paid in full is in dispute given that they, as sureties, are entitled to rely on the general contractor’s claims against the subcontractor arising out of a non-federal construction project because each of the bonded federal construction subcontracts authorize the set off of such claims. In response, plaintiff contends that the Miller Act precludes sureties’ reliance on setoff provisions.

Accordingly, at issue on plaintiffs motion for summary judgment is whether Miller Act sureties are entitled to set off the general contractor’s claims against the subcontractor arising out of a non-federal project where, as here, the federal construction subcontracts contain provisions expressly allowing the general contractor to set off any claims on unrelated projects it has against the subcontractor. On February 2, 2009, after briefing and oral argument, an Order issued denying plaintiffs motion for summary judgment and granting defendants’ motion to stay pending resolution of litigation concerning the non-federal project. See United States ex rel. Acoustical Concepts, Inc. v. Travelers Cas. & Sur. Co. of America, No. 1:08cv1030 (E.D.Va. Feb. 2, 2009) (Order). Thereafter, the Court, sua sponte, lifted the stay for the purpose of reconsidering the February 2, 2009 Order. And in this connection, the parties were allowed to submit supplemental briefs and oral arguments on the questions presented. As a result of this reconsideration, it is clear that the February 2, 2009 Order must be vacated and that summary judgment in favor of plaintiff must be granted in part and denied in part.

I.

In 2006, plaintiff entered into contracts with The Whiting-Turner Construction Company (“Whiting-Turner”), a general contractor, to provide carpentry, drywall, and other services as a subcontractor on three projects: (i) construction of an engineering building at NASA’s Wallops Island Flight Center (“the Flight Center Project”); (ii) renovations at the Marine Corps Exchange in Quantico, Virginia (“the Quantico Project”); and (iii) Phase Two of Northrop Grumman’s DD(X) Engineering Test Center in Wallops Island, Virginia (“the DD(X) Project”). The subcontracts between Whiting-Turner and plaintiff for the two federal construction projects — the Flight Center Project and the Quantico Project — contain identical setoff provisions, which provide, in part, *436 that “[b]efore paying any amount due to the Subcontractor as provided herein-above, the Contractor,” ie., Whiting-Turner, may offset payment in the amount of any unrelated claims against the subcontractor. 1

Work on the two federal construction projects was secured by payment bonds posted by Whiting-Turner, as the principal, and defendants, as co-sureties. The payment bonds are standard Miller Act payment bonds and provide that

[t]he above obligation is void if the Principal promptly makes payment to all persons having a direct relationship with the Principal or a subcontractor of the Principal for furnishing labor, material or both in the prosecution of the work provided for in the contract identified above, and any authorized modifications of the contract that subsequently are made.

Compl. Ex. A at 2; id. Ex. C at 2 (emphasis added).

Plaintiff completed its work on the Quantico Project in April 2008. The parties dispute the completion date for plaintiffs work on the Flight Center Project; plaintiff asserts it completed work on December 3, 2007, while defendants contend plaintiff completed work in July 2007 and subsequently returned to the construction site only to provide repair work. Both parties agree that plaintiff has fully performed its obligations under the Quantico Project subcontract and the Flight Center Project subcontract.

A dispute exists between Whiting-Turner and plaintiff regarding plaintiffs performance under the non-federal DD(X) Project subcontract and, on September 5, 2008, Whiting-Turner filed an action against plaintiff in the Circuit Court for Baltimore County, Maryland, seeking to recover $1.1 million for breach of that subcontract. On September 29, 2008, plaintiff filed a counter-claim seeking to recover $471,587 for breach of the DD(X) Project subcontract and tortious interference with contractual relations.

Relying on the setoff provisions in its subcontracts with plaintiff for the federal construction projects, Whiting-Turner withheld payments it concedes it otherwise would have owed plaintiff under those subcontracts to offset its claims relating to the DD(X) Project. 2 On October 1, 2008, plaintiff filed the instant action against defendants, seeking to recover $ 149,113.94 for the Quantico Project and $77,102.37 for the Flight Center Project. 3 On November *437 3, 2008, Whiting-Turner amended its complaint in the Circuit Court of Baltimore County, Maryland, seeking a declaration (i) that Whiting-Turner properly deducted the balance otherwise payable to plaintiff relating to the Quantico and Flight Center Projects and (ii) that Whiting-Turner owes no further payments to plaintiff under either the Quantico Project subcontract or the Flight Center Project subcontract. 4 Plaintiff then filed a motion for summary judgment in this action, asserting that defendants do not genuinely dispute the amount owed for work on the Quantico and Flight Center Projects and that defendants, as sureties, are not entitled to rely on the setoff provisions contained within the subcontracts for those projects.

II.

The summary judgment standard is too well settled to require elaboration here. In essence, summary judgment is appropriate only where, on the basis of undisputed material facts, the moving party is entitled to judgment as a matter of law. Celotex v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). Importantly, to defeat summary judgment, the non-moving party may not rest upon a “mere scintilla” of evidence, but must set forth specific facts showing a genuine issue for trial. Id. at 324, 106 S.Ct. 2548; Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 252, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
635 F. Supp. 2d 434, 2009 U.S. Dist. LEXIS 61939, 2009 WL 2156909, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-accoustical-concepts-inc-v-travelers-casualty-vaed-2009.