K-Con, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJanuary 12, 2017
DocketASBCA No. 60686, 60687
StatusPublished

This text of K-Con, Inc. (K-Con, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
K-Con, Inc., (asbca 2017).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) K-Con, Inc. ) ASBCA Nos. 60686, 60687 ) Under Contract Nos. W912SV-13-F-0100 ) W912SV-13-F-0121 ) ;.'

APPEARANCES FOR THE APPELLANT: Robert J. Symon, Esq. Aron C. Beezley, Esq. Bradley Arant Boult Cummings LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney MAJ Christopher M. Coy, JA Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE WOODROW

In these appeals, appellant, K-Con, Inc., claims a total sum of $116,336.56 arising out of two completed construction contracts. K-Con's claim is based on increases in costs for materials and labor due to a two-year delay in the issuance of a notice to proceed after the contracts were awarded. According to K-Con, this delay was due solely to the government's decision to add the performance and payment bond requirements set forth at Federal Acquisition Regulation (FAR) clause 52.228-15, PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION, to each contract. In response, the government contends that FAR 52.228-15 was incorporated into the contracts by operation of law at the time of contract award pursuant to the doctrine set forth in G.L. Christian & Assocs. v. United States, 312 F .2d 418, 424, 427, ajf'd on reh 'g, 320 F .2d 345 ( 1963 ). Appellant has elected to proceed under the Board's accelerated procedure set forth in Board Rule 12.3.

The sole legal question presented by this appeal is whether the bonding requirements of FAR 52.228-15 were incorporated into Contract Nos. W912SV-13-F-0100 and W912SV-13-F-0121 by operation oflaw at the time of contract award. We conclude that they were.

FINDINGS OF FACT

On 23 August 2013, the United States Property and Fiscal Office for the State of Massachusetts (Army or government) issued a Request for Quotation (RFQ) No. 815306, for the design and construction of a laundry facility at Camp Edwards, Massachusetts (R4, tab 3). On 24 September 2013, the government awarded Task Order No. W912SV-13-F-0100 (Contract 0100) to appellant, K-Con, Inc., pursuant to the solicitation (R4, tab 1 at 1). The award was for a firm-fixed-price contract with a total contract value of $305,555.00 (id.).

On 5 September 2013, the Army issued RFQ No. 821234, for the construction of a communications equipment shelter at Camp Edwards, Massachusetts (R4, tab 2). On 26 September 2013, the government awarded Task Order No. W912SV-13-F-0121 (Contract 0121) to K-Con, Inc., pursuant to this solicitation. The award was for a firm-fixed-price contract with a total contract value of $356,400.00. (Id. at 27)

The contracting officer issued both solicitations utilizing the General Services Administration (GSA) eBuy system. The contracting officer used Standard Form 1449, Solicitation/Contract/Order for Commercial Items for both contracts (R4, tabs 2-3). Neither solicitation included an express requirement that the awardee was to provide performance and payment bonds, nor did the solicitations include FAR clause 52 .228-15, PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION.

Contract 0100, for the construction of a laundry facility, contains a contract line item number (CLIN) calling for the "[c]onstruction of a new pre-fabricated metal building at Camp Edwards" (R4, tab 1 at 4). Similarly, the relevant CLIN in Contract 0121 requires the contractor to "[c]onstruct Telecom Hut D" (R4, tab 2 at 30). The statements of work for both contracts include many construction-related tasks, including design and engineering, construction of a concrete building pad and asphalt paving, connections to utilities, installation of a pre-engineered metal structure, and installation of finishes such as flooring, insulation, drywall, painting, and wall covering (R4, tabs 1-2).

On 10 October 2013, after awarding both contracts to K-Con, but before issuing a notice to proceed for either contract, the government requested that K-Con provide performance and payment bonds for both contracts (R4, tab 9; answer ii 6). On 22 October 2013, K-Con informed the government that it was unable to provide bonding for the contracts. Instead, K-Con offered to divide each contract into three separate special item numbers within its GSA schedule contract, placing each line item of each contract within the $30,000 to $150,000 range in FAR 28.102(b ). According to K-Con, this "tripartite agreement" approach would separately secure each line item, in lieu of providing payment and performance bonds for each entire contract (R4, tab 12 at 103-08).

In an email dated 10 December 2013, the government acknowledged that it "fully understands that K-Con will need to charge the Government for the bonding fees" and required a certified receipt from the surety demonstrating that K-Con had paid for the bonds (R4, tab 12 at 102-03 ). Subsequently, on 29 January 2014, the government

2 informed K-Con that it would not accept a tripartite agreement for the contracts (R4, tab 13 at 109).

Nearly two years later, on 30 September 2015, K-Con provided the required bonding and the parties modified each contract to increase the total cost to compensate K-Con for the cost of the bonding fees (R4, tabs 26-27).

On 26 January 2016, K-Con submitted a request for equitable adjustment (REA) for each contract, requesting a total sum of $116,336.56 ($53,407.54 for Contract 0100 and $62,929.02 for Contract 0121) (R4, tabs 31, 32). Each REA claimed increases in costs for materials and labor (id.). Each REA also offered comparisons of cost documentation between invoices originating prior to K-Con 's submission of its offers and information gathered from its subcontractors or suppliers in January of 2016 (id.). K-Con also claimed costs for overhead, profit, and "bonding" (id.). Lastly, K-Con claimed an entitlement to an equitable adjustment for all cost escalation that occurred during the period between 24 September 2013 and 30 September 2015 as a result of its inability to obtain sufficient bonding (id.).

DISCUSSION

Under the so-called Christian doctrine, a mandatory contract clause that expresses a significant or deeply ingrained strand of public procurement policy is considered to be included in a contract by operation oflaw. Christian, 312 F.2d at 424, 427. Application of the Christian doctrine turns not on whether the clause was intentionally or inadvertently omitted, but on whether procurement policies are being "avoided or evaded (deliberately or negligently) by lesser officials." Christian, 320 F .2d at 3 51.

To be included in the contract by operation of law, the contract clause must be both mandatory and represent a significant public procurement policy. In this appeal, the bonding requirements of FAR 52.228-15 satisfy both of these requirements. Therefore, we conclude that FAR 52.228-15 must be incorporated into the contracts by operation of law.

I. FAR 52.228-15 Is Mandatory

We hold that FAR 52.228-15, PERFORMANCEANDPAYMENTBONDS- CONSTRUCTION, is a mandatory clause in a government construction contract. Specifically, both performance and payment bonds are required by statute. 40 U.S.C. §§ 3131-3134 (formerly known as the Miller Act) states, in relevant part:

(b) Type of Bonds Required. - Before any contract of more than $100,000 is awarded for the construction, alteration, or repair of any public building or public work of the Federal

3 Government, a person must furnish to the Government the following bonds, which become binding when the contract is awarded:

( 1) Performance bond. - A performance bond with a surety satisfactory to the officer awarding the contract, and in an amount the officer considers adequate, for the protection of the Government.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
K-Con, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/k-con-inc-asbca-2017.