United States v. Western Electric Co.

337 F.2d 568, 1964 U.S. App. LEXIS 4230
CourtCourt of Appeals for the Ninth Circuit
DecidedOctober 5, 1964
Docket19024
StatusPublished
Cited by43 cases

This text of 337 F.2d 568 (United States v. Western Electric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Western Electric Co., 337 F.2d 568, 1964 U.S. App. LEXIS 4230 (9th Cir. 1964).

Opinion

337 F.2d 568

The UNITED STATES of America, for the Use and Benefit of Barney AUSTIN, an individual, and Great American Insurance Company, Appellants,
v.
WESTERN ELECTRIC CO., Inc., and Merchants Fire Assurance Corporation of New York, Appellees.

No. 19024.

United States Court of Appeals Ninth Circuit.

October 5, 1964.

Wm. J. Conners, Anderson, McPharlin & Conners, Los Angeles, Cal., for appellants.

Marvin A. Freeman, Ivon B. Blum, Beverly Hills, Cal., for appellees.

Before CHAMBERS and KOELSCH, Circuit Judges, and JAMESON, District Judge.

JAMESON, District Judge:

In this Miller Act1 case, use plaintiff, Barney Austin, a subcontractor, and his surety, Great American Insurance Company, have appealed from a summary judgment in favor of the defendants Western Electric Co., Inc., a prime contractor, and its surety, Merchants Fire Assurance Corporation of New York.

Western Electric entered into a contract with the United States to construct Project Mercury, including tracking station 13 at Point Arguello, California. It entered into a subcontract with Burns & Roe, Inc., for engineering and construction work. In turn Burns & Roe issued to plaintiff Austin, and Austin accepted, a so-called purchase order whereby Austin agreed to do the architectural, structural and mechanical phases of the work to be done at station 13 by Burns & Roe under its subcontract.

Austin completed the work under his subcontract with Burns & Roe, but was unable to pay for all the labor and material furnished by others in the performance of this contract. Austin's surety, Great American, paid labor and material claims totalling $22,279.96. Plaintiffs' complaint claims a balance due from defendants in the sum of $111,465.11.2

Plaintiffs' complaint was filed on December 7, 1961, although plaintiffs contend that it was delivered to the clerk of the district court on December 6 and should have been filed as of that date.3

On December 8, 1962, defendants filed their motion for summary judgment on the grounds (1) that the suit was not instituted within one year from the date on which the last of the labor was performed or material supplied4; and (2) that the plaintiff Austin's notice of claim was insufficient for the reason that it did not state "with substantial accuracy the amount claimed" by plaintiff.5

On January 10, 1963, plaintiffs filed a notice of motion for an order correcting the filing date on the complaint to December 6, 1961, the date on which the complaint was delivered to the clerk.

The two motions were heard by the district court on February 4, 1963. The case had also been calendared for a pretrial conference on the same date. Counsel for plaintiff indicated that he was not ready for pretrial and that further discovery was necessary.6 The pretrial conference was continued to March 11, 1963. No conference was held.

An order was entered February 11, 1963, granting defendants' motion for summary judgment, and findings of fact, conclusions of law and judgment were entered February 21, 1963. An order was entered March 11, 1963, denying plaintiffs' motion to correct the filing date of the complaint.

Appellants appealed from the judgment and the order denying their motion to correct the filing date. On September 10, 1963, an order was entered in this court dismissing the appeal for the reason that neither the summary judgment nor the order was appealable, but suggesting that if the district court should see fit to make the determination and give the direction specified in Rule 54 (b)7 of the Federal Rules of Civil Procedure and enter judgment in conformity therewith, an appeal therefrom could be heard upon the briefs and record of the proceedings in the district court.

On October 16, 1963, the district court entered an order amending its order of February 11, 1963, to provide that the judgment entered in favor of the defendants should be a final judgment pursuant to Rule 54(b). On October 21, 1963, amended findings of fact, conclusions of law, and judgment were entered in conformity with the amended order and the provisions of Rule 54(b).

The summary judgment was granted on the first ground of defendants' motion, i. e., that plaintiffs' action was filed more than one year from the date on which the last labor was performed and material supplied by the plaintiff Austin. The district court did not pass upon the question of the sufficiency of the notice of the claim filed by Austin.8

The court found that plaintiff Austin "substantially completed the work and the furnishing of material * * * on or about October 25, 1960"; that the labor and material furnished subsequent to that date "were of a minor nature, such as cleanup, repair, correction or installing overlooked items as noted by Burns & Roe, Inc., in its punch list"; and that "written notice of nonpayment was given by plaintiff Austin to Western Electric on December 14, 1960, stating that the work of the subcontract * * * was completed on or about October 25, 1960".

Appellants contend, inter alia, that the "district court erred in weighing the evidence and resolving issues rather than determining that there were issues to be resolved in a regular trial". The record suggests that this may be true. There is no recital in the court order, findings of fact, or judgment that the pleadings, depositions, admissions, and affidavits "show that there is no genuine issue as to any material fact."9 Rule 56(c).

The findings of fact recite that "having considered all of the evidence and having examined all of the proofs offered by the respective parties", the court makes its findings of fact — a form customarily followed where the court has weighed the evidence and resolved the issues. Rule 52(a), by amendment effective March 19, 1948, specifically provides that, "Findings of fact and conclusions of law are unnecessary on decisions of motions" for summary judgment under Rule 56. We recognize, however, that findings of fact and conclusions of law are frequently used in granting motions for summary judgment.10 As suggested in Trowler v. Phillips, 9 Cir. 1958, 260 F.2d 924, 926, findings of fact, "while unnecessary", sometimes "provide a handy summary". On the other hand, "all too often a set of unnecessary findings of fact is the telltale flag that points the way to a discovery that summary judgment should not have been granted".

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Buckingham Township v. Wykle
157 F. Supp. 2d 457 (E.D. Pennsylvania, 2001)
Alaska Center for the Environment v. Browner
20 F.3d 981 (Ninth Circuit, 1994)
School District No. 1j, Multnomah County, Oregon v. Acands, Inc., a Pennsylvania Corporation E.J. Bartells Company, a Washington Corporation A.P. Green Refractories Company, School District No. 1j, Multnomah County, Oregon v. Acands, Inc., a Pennsylvania Corporation, and Fibreboard Corp., a Delaware Corporation as Successor in Interest to the Paraffine Companies, Inc., Pabco Products, Inc., Fibreboard Paper Products Corporation, Plant Rubber & Asbestos Works and Plant Rubber & Asbestos Co., School District No. 1j, Multnomah County, Oregon v. Acands, Inc., a Pennsylvania Corporation Armstrong Cork Company, Inc., a Delaware Corporation Atlas Asbestos Company, Inc., a Canadian Corporation, and Keene Corporation, a New York Corporation Individually and as Successor in Interest to the Baldwin Ehret Hill Company, School District No. 1j, Multnomah County, Oregon v. Acands, Inc., a Pennsylvania Corporation Armstrong Cork Company, Inc., a Delaware Corporation Atlas Asbestos Company, Inc., a Canadian Corporation, and Us Gypsum Company, a Delaware Corporation, School District No. 1j, Multnomah County, Oregon v. Acands, Inc., a Pennsylvania Corporation Armstrong Cork Company, Inc., a Delaware Corporation Atlas Asbestos Company, Inc., a Canadian Corporation, and Owens-Corning Fiberglass Corporation, School District No. 1j, Multnomah County, Oregon v. Acands, Inc., a Pennsylvania Corporation Armstrong Cork Company, Inc., a Delaware Corporation Atlas Asbestos Company, Inc., a Canadian Corporation, and Flintkote Company, a Delaware Corporation, School District No. 1j, Multnomah County, Oregon v. Acands, Inc., a Pennsylvania Corporation Atlas Asbestos Company, Inc., a Canadian Corporation, and Armstrong Cork Company, Inc., a Delaware Corporation
5 F.3d 1255 (Ninth Circuit, 1993)
United States v. Sun Engineering Enterprises, Inc.
817 F. Supp. 1009 (D. Puerto Rico, 1993)
United States v. W.H. Cates Construction Co.
972 F.2d 987 (Eighth Circuit, 1992)
JOHNSON BY JOHNSON v. Svidergol
757 P.2d 609 (Court of Appeals of Arizona, 1988)
City Electric v. Industrial Indemnity Co.
683 P.2d 1053 (Utah Supreme Court, 1984)
Pacific Legal Foundation v. Watt
539 F. Supp. 841 (C.D. California, 1982)
United States ex rel. Lank Woodwork Co. v. CSH Contractors, Inc.
452 F. Supp. 922 (District of Columbia, 1978)
United States v. E.J.T. Construction Co.
453 F. Supp. 435 (D. Delaware, 1978)
UNITED STATES, ETC. v. EJT Const. Co., Inc.
453 F. Supp. 435 (D. Delaware, 1978)
Peralta v. Martinez
564 P.2d 194 (New Mexico Court of Appeals, 1977)
United States v. Essential Construction Co., Inc.
363 F. Supp. 681 (S.D. New York, 1973)
Becker v. Koza
53 F.R.D. 416 (D. Nebraska, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
337 F.2d 568, 1964 U.S. App. LEXIS 4230, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-western-electric-co-ca9-1964.