United States v. Sun Engineering Enterprises, Inc.

817 F. Supp. 1009, 1993 U.S. Dist. LEXIS 4380
CourtDistrict Court, D. Puerto Rico
DecidedMarch 31, 1993
DocketCiv. 91-2297 (JAF), 92-1710 (JAF)
StatusPublished
Cited by6 cases

This text of 817 F. Supp. 1009 (United States v. Sun Engineering Enterprises, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Sun Engineering Enterprises, Inc., 817 F. Supp. 1009, 1993 U.S. Dist. LEXIS 4380 (prd 1993).

Opinion

OPINION AND ORDER

FUSTE, District Judge.

Two independent subcontractors brought separate suits against a common contractor and its surety pursuant to federal legislation that provides a remedial cause of action for contract disputes involving federal building projects. Both subcontractors allege that the contractor and its surety are jointly and severally liable for the full compensation agreed to under the respective subcontracts, in addition to interest on the unpaid subcontracts, attorneys’ fees, and court costs. The contractor avers that the money damages prayed for under the subcontracts are excessive given the subcontractors’ performances, or in the alternative, that the special federal law under which the subcontractors brought the suit bars these plaintiffs a federal remedy on statute of limitations grounds. Since similar issues are involved, as well as the existence of common defendants, the two suits have been consolidated before this court. The contractor and surety have moved for summary judgment against one of the two subcontractors, claiming that the subcontractor’s suit does not meet the time requirements of the federal statute.. The summary judgment motion is denied.

I.

Background

On March 23, 1990, Efigenio Curet Santiago, doing business as Curet Tech Services (“Curet”), entered into a subcontract with Sun Engineering Enterprises, Inc. (“Sun Engineering”), the contractor for federal project number 089984-89-B-0163 to renovate the lobby and offices of the United States General Post Office of San Juan, Puerto Rico. 1 Curet, a Puerto Rico entity, agreed to perform the installation of certain air-conditioning systems at the post office for Sun Engineering, also a Puerto Rico concern. The original amount of Curet’s subcontract was $56,000. Curet argues that an additional $1,609.57 is owed because of extra work completed at the request of contractor Sun Engineering. CNA Casualty of Puerto Rico (“CNA”) was the surety under the subcontract and furnished the United States with a performance and payment bond under number 3139917 of the contract.

Curet began its air-conditioning work and completed the contract between December 1990 and June 1991. The exact date is in dispute. Mr. Curet^Santiago, the owner of Curet, stated that the subcontract was completed in December of 1990. (Civil No. 91-2297, Docket Document No. 18, Motion for Summary Judgment, Exhibit A, Deposition of Curetr-Santiago, at 3-4,13). On February 11, 1991, Curet claims to have sent defendants an invoice for the unpaid portion of the subcontract. When Curet received no payments, a second letter dated March 12, 1992, was allegedly sent to Sun Engineering’s client, the United States, seeking assistance in forcing Sun Engineering to pay Curet the unpaid balance of the subcontract price. On February 27, 1991, according to the record, an architect had already inspected Curet’s work product and found several “deficiencies”. (Civil No. 91-2297, Docket Document No. 19, Motion Opposing Summary Judgment, Exhibit B, Letter to Sun Engineering’s President, Francisco Jimenez, from Architect Ismael Elias Cortés, of 8/7/1991, at 1-2). Curet was allegedly unaware of any “deficiencies” until May 6, 1991, at which point Curet was notified of the actions necessary to correct various “deficiencies” in order to sat *1011 isfy the United States and Sun Engineering. 2 Curet performed the requested tasks. In a sworn statement, Sun Engineering’s President, Francisco Jiménez (“Jiménez”), indicated that he was assured that the entire project was completed by May 17, 1991. (Civil No. 91-2297, Docket Document No. 18, Motion for Summary Judgment, Exhibit C, Sworn Declaration of Jiménez, at 1). The inspector, Architect Cortés, acknowledged his approval of Curet’s performance in a letter to Jiménez dated June 12,1991. (Civil No. 91-2297, Docket Document No. 18, Motion for Summary Judgment, Exhibit D, Letter from Architect Cortés to Jiménez of 6/12/1991, at 1).

On May 27, 1992, Curet filed suit with the Clerk of the United States District Court for the District of Puerto Rico pursuant to the Miller Act, 40 U.S.C. §§ 270a et seq., seeking the unpaid balance of the air-conditioning subcontract from Sun Engineering and CNA. 3 (Civil No. 92-1710, Docket Document No. 1, Complaint). Curet argues that Sun Engineering’s alleged breach of contract has cost Curet at least $17,965.57.

On July 7, 1992, following a motion by plaintiffs, Curet’s claim and that of the other subcontractor were consolidated by order of the court. (Civil No. 92-1710, Docket Document No. 7, Motion for Consolidation). On August 10, 1992, Defendants Sun Engineering and CNA moved for summary judgment against Plaintiff Curet, arguing that plaintiffs Miller Act claim is barred by the one-year statute of limitations set forth in the statute. 40 U.S.C. § 270b. (Civil No. 91-2297, Docket Document No. 18, Motion for Summary Judgment).

II.

Standard for Summary Judgment

Federal Rule of Civil Procedure 56(c) states that summary judgment “shall be rendered forthwith if the pleadings, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c) (emphasis added). Therefore, in deciding a summary judgment motion, there are essentially three inquiries to pursue: the materiality and genuineness of any factual dispute, and the entitlement to judgment as a matter of law. Id.; Román Figueroa v. Torres Molina, 754 F.Supp. 239, 240-41 (D.P.R.1990).

“ ‘[Gjenuine’ means that the evidence is such that a reasonable jury could resolve the point in favor of the nonmoving party.” United States v. One Parcel of Real Property with Bldgs., 960 F.2d 200, 204 (1st Cir.1992) (citation omitted). A “material” fact describes one that “might affect the outcome of the suit under the governing law.” Anderson v. Liberty Lobby Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986). See also Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 2553, 91 L.Ed.2d 265 (1986); Garside v. Osco Drug, Inc., 976 F.2d 77, 78 (1st Cir.1992).

Summary judgment may be granted even if there is a factual dispute so long as the fact at issue is

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. GE Supply v. G & C Enterprises, Inc.
29 F. Supp. 2d 49 (D. Puerto Rico, 1998)
R.E. Monks Construction Co. v. Aetna Casualty & Surety Co.
944 P.2d 517 (Court of Appeals of Arizona, 1997)
RE MONKS CONST. v. Aetna Cas. & Sur.
944 P.2d 517 (Court of Appeals of Arizona, 1997)
United States ex rel. Balf Co. v. Casle Corp.
895 F. Supp. 420 (D. Connecticut, 1995)
US ON BEHALF OF & FOR USE OF BALF v. Casle Corp.
895 F. Supp. 420 (D. Connecticut, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
817 F. Supp. 1009, 1993 U.S. Dist. LEXIS 4380, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-sun-engineering-enterprises-inc-prd-1993.