Southern Steel Company, Inc. v. United Pacific Insurance Company, Defendant-Counter-Defendant

935 F.2d 1201, 1991 U.S. App. LEXIS 14886, 1991 WL 112210
CourtCourt of Appeals for the Eleventh Circuit
DecidedJuly 15, 1991
Docket90-8795
StatusPublished
Cited by5 cases

This text of 935 F.2d 1201 (Southern Steel Company, Inc. v. United Pacific Insurance Company, Defendant-Counter-Defendant) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Steel Company, Inc. v. United Pacific Insurance Company, Defendant-Counter-Defendant, 935 F.2d 1201, 1991 U.S. App. LEXIS 14886, 1991 WL 112210 (11th Cir. 1991).

Opinion

PER CURIAM:

Southern Steel Company sued United Pacific Insurance Company as surety on a payment bond required by the Georgia counterpart to the federal Miller Act, O.C. G.A. Section 13-10-1, et seq., and Section 36-82-100, et seq. (Georgia’s “Little Miller Act”). The district court granted summary judgment for United Pacific. Because we find that there exists a genuine issue of material fact, we reverse.

I. Facts

Cobb County, Georgia engaged Noonan Kellos, Inc. (now known as Noonan-South, Inc.) as prime contractor to build a jail for the county. Noonan-South, as required by law, executed payment and performance bonds as principal, with United Pacific as surety. Noonan-South hired Roanoke Iron and Bridge Works, Inc. as a subcontractor to supply and install the detention equipment in the jail. Roanoke arranged to purchase various locking devices and other hardware from Southern Steel. From 1983 to 1986, Roanoke issued to Southern Steel a series of purchase orders for items used in locking systems. The parties have stipulated that Southern Steel shipped the last of the materials provided under these purchase orders no later than July 15, 1986.

In September 1986 Roanoke instituted bankruptcy proceedings. Shortly thereafter, Southern Steel notified Noonan-South that because of the substantial amount of money Roanoke owed Southern Steel for materials already delivered to the jail, Southern Steel would provide no additional materials to the project unless they were paid for in advance or at delivery. On November 17, 1986, Southern Steel wrote to Noonan-South to inform it that Southern Steel had a number of items that Roanoke had ordered for the Cobb County jail but for which it had not yet paid. Southern Steel wrote that the materials would be returned to inventory unless Noo-nan-South requested and paid for them. Noonan-South did so, and Southern Steel shipped the materials to the jail site around December 15, 1986. After August 1986 Noonan-South also ordered and paid for, and Southern Steel delivered, other materials for the jail.

In addition to the materials that Noonan-South ordered and paid for, Southern Steel *1203 shipped to the jail a number of other items for which it did not charge. The items provided on a “no charge” basis included screws, keys, an alien wrench, a strike plate, and at least ten reworked electric locks. The locks had to be repaired because they had burned out at the job site. These materials were shipped to the jail in late November and mid-December 1986.

On February 6,1987, Southern Steel sent to United Pacific by Federal Express written notice of its claim against the payment bond for the unpaid balance of all its invoices to Roanoke. 1 Southern Steel later filed suit against United Pacific, claiming United Pacific was liable to Southern Steel for the money owed to Southern Steel by Roanoke under the payment bond United Pacific provided for Noonan-South. United Pacific eventually filed a motion for summary judgment, asserting that Southern Steel was barred from recovering on the bond because it had failed to provide timely notice as required by Georgia’s Little Miller Act, O.C.G.A. Section 36-82-104(b). The notice provision of the statute reads as follows:

Every person entitled to the protection of the payment bond ... who has not been paid in full for labor or material furnished in the prosecution of the work ... shall have the right to bring an action on such payment bond ... for the amount, or the balance thereof, unpaid at the time of the commencement of such action and to prosecute such action to final execution and judgment for the sum or sums due him; provided, however, that any person having direct contractual relationship with a subcontractor, but no contractual relationship express or implied with the contractor furnishing such payment bond or security deposit, shall have the right of action upon the payment bond or security deposit upon giving written notice to the contractor within 90 days from the day on which such person did or performed the last of the material or machinery or equipment for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied. 2

United Pacific argued that Southern Steel had given notice of its claim against the payment bond more than ninety days after providing the last of the materials for which it made claim, and was therefore barred from recovery. Southern Steel filed a motion for partial summary judgment, seeking a determination that its notice had been timely given.

The district court granted summary judgment for United Pacific. In the district court’s opinion, the case turns on whether notice can be measured from any of the items provided by Southern Steel to Noonan-South at no charge in November and December 1986. The judge noted that notice must be measured from the last date of original contract performance, rather than the date of any corrective performance. See Ranger Constr. Co. v. Robertshaw Controls Co., 166 Ga.App. 679, 680, 305 S.E.2d 361, 362 (1983). In finding for United Pacific, the court reasoned as follows:

it appears that “no charge” items shipped within 90 days of the February 6 letter to United Pacific constituted corrective work in the nature of “reworked” lock assemblies or, in the case of the screws, keys, alien wrench, and strike plate, were of minimal value. This court holds that Southern Steel has not come forward with sufficient facts to show that the “no charge” items shipped within 90 days of the February 6 letter were original contract items, as opposed to corrective items. See Celotex Corp. v. *1204 Catrett, 477 U.S. 317, 106 S.Ct. 2548 [91 L.Ed.2d 265] (1986).

II. Discussion

As a preliminary matter, we note that because Georgia’s Little Miller Act is, as its nickname suggests, substantially similar to the federal Miller Act, Georgia courts look to federal law interpreting the Miller Act to guide their interpretation of the Little Miller Act. See Amcon, Inc. v. Southern Pipe & Supply Co., 134 Ga.App. 655, 656, 215 S.E.2d 712, 713 (1975); Porter-Lite Corp. v. Warren Scott Contracting Co., 126 Ga.App. 436, 438-39, 191 S.E.2d 95, 97 (1972).

On appeal, Southern Steel makes two arguments to explain why it believes the district court erred in granting summary judgment for United Pacific: First, it contends that the keys and most of the other material provided at no charge “relate back” to and complete earlier shipments of material supplied pursuant to purchase orders from Roanoke for which Roanoke never paid Southern Steel.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
935 F.2d 1201, 1991 U.S. App. LEXIS 14886, 1991 WL 112210, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-steel-company-inc-v-united-pacific-insurance-company-ca11-1991.