Ranger Construction Co. v. Robertshaw Controls Co.

305 S.E.2d 361, 166 Ga. App. 679, 1983 Ga. App. LEXIS 2293
CourtCourt of Appeals of Georgia
DecidedMay 3, 1983
Docket65361
StatusPublished
Cited by23 cases

This text of 305 S.E.2d 361 (Ranger Construction Co. v. Robertshaw Controls Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ranger Construction Co. v. Robertshaw Controls Co., 305 S.E.2d 361, 166 Ga. App. 679, 1983 Ga. App. LEXIS 2293 (Ga. Ct. App. 1983).

Opinion

Deen, Presiding Judge.

Dresco Mechanical Contractors, Inc. (Dresco) contracted with Ballenger Corporation f/k/a Ranger Construction Company (Ranger), to provide mechanical work relating to the construction of the Northwest Georgia Regional Hospital in Rome, Georgia, for which project Ranger was the general contractor. The Travelers Indemnity Company (Travelers) acted as surety on Ranger’s payment bond; United States Fidelity & Guaranty Company (USF&G) was surety on Dresco’s performance bond naming Ranger as obligee.

Dresco then contracted with Robertshaw Controls Company (Robertshaw) to provide and install temperature control systems in several buildings of the hospital complex. Several years later, Robertshaw filed suit in the State Court of Fulton County against Ranger and Travelers, alleging that it had completed performance under the contract, that Dresco had paid Robertshaw in part but that a balance of $45,137 remained, and that it had given Ranger and Travelers notice of Dresco’s default and demanded payment under the bond.

Ranger and Travelers in turn filed a third-party complaint against Dresco and USF&G, alleging that any liability of Ranger and Travelers to Robertshaw was secondary to that of Dresco and USF&G, thus entitling them to indemnification from Dresco and USF&G for any such liability. The matters proceeded to trial, where the trial court directed verdicts in favor of Robertshaw on its complaint against Ranger and Travelers, and against Ranger and Travelers on the third-party complaint against Dresco and USF&G.

In its appeal, Ranger enumerates as error the following: (1) that the trial court improperly directed verdict for Robertshaw because Robertshaw failed to prove adequately that it gave the required, timely notice of claim; (2) that the trial court improperly directed verdict for Robertshaw for the entire claim of $45,137, because there was evidence that Robertshaw actually had two contracts with Dresco and the required notice of claim was not timely, relative to the *680 first contract; (3) that the trial court erred in not granting Ranger’s motion for directed verdict on Robertshaw’s claim for relief under the theory of quantum meruit; (4) that the trial court erred in allowing Robertshaw to call Dresco’s president as a witness for purposes of cross-examination; (5) that the trial court improperly directed verdict for Dresco and USF&G on the third-party complaint. Held:

1. OCGA § 36-82-104 (b) (Code Ann. § 23-1708) provides that “any person having direct contractual relationship with a subcontractor, but no contractual relationship express or implied with the contractor furnishing such payment bond, shall have the right of action upon the payment bond upon giving written notice to the contractor within 90 days from the day on which such person did or performed the last of the labor or furnished the last of the material or machinery or equipment for which such claim is made ...” This court has previously emphasized that the timely written notice is a condition precedent to establishing a claim under a payment bond, and that the last labor or materials must be original contract performance rather than corrective performance. Porter-Lite Corp. v. Warren Scott Contracting Co., 126 Ga. App. 436 (191 SE2d 95) (1972).

In asserting that Robertshaw failed to meet this notice requirement, Ranger presents two arguments: (1) that there remained at least a factual question as to whether Robertshaw’s performance within 90 days of February 20,1976, the date of notice of claim, had been original performance under the contract or corrective work; (2) that actually two contracts existed between Robertshaw and Dresco, and because Robertshaw completed performance under the first contract around December 1974, the notice requirement had not been met concerning that portion of Robertshaw’s claim. We do not believe the evidence supports Ranger’s contentions.

It was undisputed that on December 3, 1974, Robertshaw and Dresco bifurcated their original contract, with one job ordér pertaining to all of the buildings in which Robertshaw had basically completed installation of the temperature control systems, and the other pertaining to the final building in which Robertshaw had yet to install the system. The amount to be billed for the latter job order totalled $14,311, which was deducted from the original contract price. Robertshaw sought the arrangement for internal accounting purposes so that it could submit its bill for the work completed. Considering the two job orders as of December 3, 1974, the subject matter and total price agreed upon in the original contract were unaltered. No additional consideration was extended for this bifurcation.

Notwithstanding the fact that no genuine modification *681 occurred, since there was no actual alteration of the original contract terms, we find crucial the fact that there was no additional consideration for the asserted modification. A written contract may be modified by a subsequent agreement, but such must be founded upon new consideration. J. E. M. Enterprises v. Taco Pronto, 145 Ga. App. 573 (244 SE2d 253) (1978); Houston v. Jefferson Standard Life Ins. Co., 119 Ga. App. 729 (168 SE2d 843) (1969). In this case, the original contract remained in force and controlled the work on the last building.

The primary question, then, is whether any of Robertshaw’s work on the project within 90 days of February 20,1976, constituted original performance under the contract, and not merely corrective work. Ranger here contends that the trial court erred in directing verdict for Robertshaw on this matter because a sufficient conflict in the evidence existed for jury resolution.

A directed verdict is appropriate where there is no conflict in the evidence as to any material issue and the evidence introduced, with all reasonable deductions therefrom, demands a particular verdict. OCGA § 9-11-50 (a) (Code Ann. § 81A-150). Where the evidence strongly supports, but does not demand, a certain verdict, the factual determination remains for the jury. Barber v. Atlas Concrete Pools, 155 Ga. App. 118 (270 SE2d 471) (1980). Further, the evidence should be construed in the light most favorable to the respondent to a motion for directed verdict. Francis v. Cook, 248 Ga. 225 (281 SE2d 548) (1981).

The pertinent testimony of Robertshaw’s employees was that the entire project had been completed in late December 1975; the last work for which Robertshaw had billed time under the contract had been performed in December 1975. Robertshaw returned after that date for punch list, or corrective, work. Ranger, in asserting that there was a factual issue, emphasized the other testimony that Robertshaw had also worked on punch list items before completion of the contract, and that the employees of Robertshaw could not tell from the job costs reports whether the work performed in December 1975 was original or corrective. Construing this evidence in the light most favorable to Ranger, we think it still demands a finding that original contract performance was completed in December 1975.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carroll v. Board of Regents of University System
751 S.E.2d 421 (Court of Appeals of Georgia, 2013)
Foster & Co. General Contractors, Inc. v. House HVAC/Mechanical, Inc.
627 S.E.2d 188 (Court of Appeals of Georgia, 2006)
In Re Lason, Inc.
314 B.R. 296 (D. Delaware, 2004)
Summerhill Neighborhood Development Corp. v. Telerent Leasing Corp.
528 S.E.2d 889 (Court of Appeals of Georgia, 2000)
Peripety Group, Inc. v. Smith
514 S.E.2d 262 (Court of Appeals of Georgia, 1999)
Trico Insurance Agencies, Inc. v. Selective Insurance Company of America
444 S.E.2d 119 (Court of Appeals of Georgia, 1994)
Ideal Pool Corp. v. Baker
377 S.E.2d 511 (Court of Appeals of Georgia, 1988)
Glen Oak, Inc. v. Henderson
369 S.E.2d 736 (Supreme Court of Georgia, 1988)
First Union Bank v. Daniel
368 S.E.2d 768 (Court of Appeals of Georgia, 1988)
Stephens v. Stephens
362 S.E.2d 118 (Court of Appeals of Georgia, 1987)
WESTERN HOST ATLANTA, INC. v. Bass
358 S.E.2d 312 (Court of Appeals of Georgia, 1987)
Fountain v. Metropolitan Atlanta Rapid Transit Authority
346 S.E.2d 363 (Court of Appeals of Georgia, 1986)
Clark v. Carla Gay Dress Co.
342 S.E.2d 468 (Court of Appeals of Georgia, 1986)
Gregory v. J. T. Gregory & Son, Inc.
338 S.E.2d 7 (Court of Appeals of Georgia, 1985)
Anderson v. Dunwoody North Driving Club, Inc.
335 S.E.2d 451 (Court of Appeals of Georgia, 1985)
Wilson v. Childers
329 S.E.2d 503 (Court of Appeals of Georgia, 1985)
Powell v. Clanton
326 S.E.2d 495 (Court of Appeals of Georgia, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
305 S.E.2d 361, 166 Ga. App. 679, 1983 Ga. App. LEXIS 2293, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ranger-construction-co-v-robertshaw-controls-co-gactapp-1983.