Foster & Co. General Contractors, Inc. v. House HVAC/Mechanical, Inc.

627 S.E.2d 188, 277 Ga. App. 595, 2006 Ga. App. LEXIS 160
CourtCourt of Appeals of Georgia
DecidedFebruary 14, 2006
DocketA05A2285
StatusPublished
Cited by1 cases

This text of 627 S.E.2d 188 (Foster & Co. General Contractors, Inc. v. House HVAC/Mechanical, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foster & Co. General Contractors, Inc. v. House HVAC/Mechanical, Inc., 627 S.E.2d 188, 277 Ga. App. 595, 2006 Ga. App. LEXIS 160 (Ga. Ct. App. 2006).

Opinion

Ellington, Judge.

Foster & Company General Contractors, Inc. (“Foster”) and Travelers Casualty & Surety Company of America (“Travelers”) appeal the trial court’s order (i) granting summary judgment to House HVAC/Mechanical, Inc. (“House”) and (ii) denying summary judgment to Foster and Travelers, on House’s breach of contract action. We reverse for the reasons set forth below.

Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. OCGA § 9-11-56 (c). A de novo standard of review applies to an appeal from an order either granting or denying summary judgment, and we view the evidence, and all reasonable conclusions and inferences drawn from it, in the light most favorable to the nonmovant.

(Citation omitted.) Ledford v. Smith, 274 Ga. App. 714, 715 (618 SE2d 627) (2005).

Terms of the Subcontract. On October 16, 2001, House, as subcontractor, and Foster, as contractor, entered into a subcontract (the “Subcontract”) pursuant to which House agreed to provide a heating, venting, and air conditioning system for the Clayton County Board of Education Building Complex (the “Project”) for a base contract price of $899,172. Travelers was the surety on Foster’s Project payment bond.

Under Paragraph 11.2.6 of the Subcontract, House was required to pay “for all materials, equipment and labor used in, or in connection with, the performance of [the] Subcontract through the period covered by previous payments received from [Foster]. . . .” Foster agreed to make progress payments and the final payment to House within seven working days after Foster received payment from the Clayton County Public Schools (the “Owner”). Paragraph 6.2 provided, however, that before the final payment, House, if required by Foster, was obligated to “submit evidence satisfactory to [Foster] that *596 all payrolls, bills for materials and equipment, and all known indebtedness connected with [House’s] Work [had] been satisfied.” Furthermore, pursuant to Paragraph 8.2.5 (b), Foster had

the absolute right to set off against any sums, monies, or amounts due or owing to [House] all claims, debts, costs, expenses, damages, liabilities or other obligations which [Foster] has incurred or might incur as a result of any acts, omissions, breaches, or negligence by [House] arising out of or related to any and all agreements, contracts, subcontracts, ... by and between [Foster] and [House], . . . the Project, ... or any other matters or dealings of any kind between [Foster] and [House].
Paragraph 12.6.1 further provided that if House defaults
and fails within three working days after receipt of written notice from [Foster] to commence and continue correction of such default or neglect with diligence and promptness, [Foster] may, after three days following receipt by [House] of an additional written notice, and without prejudice to any other remedy [Foster] may have, make good such deficiencies and may deduct the cost thereof from the payments then or thereafter due [House]....

MPI and Trane. This dispute concerns Foster’s right under the Subcontract to withhold or setoff monies Foster owed to House under the Subcontract on account of work performed or materials supplied to the Project by Georgia Trane Automation & Control (“Trane”) and Mechanical Products, Inc. (“MPI”). Trane’s involvement was straightforward. House acknowledges that, at the time it requested final payment from Foster, House owed Trane $27,214.58 for materials used by House on the construction of the Project, and there is no evidence that House ever paid Trane. MPI’s association with the Project and the parties is more complex.

House subcontracted a portion of its Project-related work to Amechco, Inc., and MPI supplied materials to Amechco in connection with the work. In August 2002, MPI billed Amechco for materials supplied by MPI and used by Amechco on the Project. In September 2002, MPI notified Foster that MPI had provided $13,874.48 in labor and materials to the Project at Amechco’s instance. In December 2002, Foster notified House that MPI was threatening a lawsuit against Amechco and Travelers, and Foster asserted the right under the Subcontract to withhold final payment to House until all bills associated with MPI’s work on the Project had been paid.

*597 Foster paid House $44,992.85 in January 2003, which was half of the retainage claimed by House. Foster received its final payment from the Owner in early July 2003. On July 14, 2003, House made a claim on Foster’s payment bond for the remainder of House’s retain-age in the amount of $44,992.85. In a letter to House, Foster replied that House’s bond claim was “out of line” because Foster had only received final payment from the Owner two weeks earlier, House had unpaid suppliers with invoices dating back to the fall of 2002, and House had failed to complete certain punchlist items.

In August 2003, Foster sent House photocopies of (i) a check to the order of MPI and House for $16,371.89, (ii) a check to the order of Trane and House for $27,215.58, and (iii) a check to the order of House for $1,229.94. Foster informed House that it would release these checks upon its receipt of executed releases and lien waivers from MPI, Trane, and House.

On October 29, 2003, MPI informed House and Foster that it would sign a release of lien upon its receipt of $13,874.48. According to the affidavit of Foster’s president, House subsequently authorized Foster to pay MPI $13,874.48 and to deduct this payment from the balance Foster owed to House for House’s work on the Project, provided that MPI agreed to release all claims against House, Foster, and Travelers. Foster’s president further averred that in November 2003, MPI agreed to the settlement arrangement and Foster sent a $13,874.48 check to MPI.

The lawsuit. On December 22, 2003, House filed this action for breach of contract and failure to honor the payment bond against Foster and Travelers. House subsequently moved for summary judgment, relying on evidence that it had completed all work called for by the Subcontract and had not been notified of any disputed work, defects in construction, or damages allegedly caused by House or its agents or representatives. Foster and Travelers filed a cross-motion for summary judgment. The trial court granted House’s motion for summary judgment and denied Foster’s and Traveler’s cross-motion, finding that House had proved its prima facie case but that Foster and Travelers had failed to submit any admissible evidence. However, the affidavit of Foster’s president appears in the record as an attachment to Foster’s brief in opposition to House’s motion for summary judgment, and House does not contend that the affidavit was inadmissible as evidence.

1. Foster contends that it was authorized to withhold final payment to House pending House’s satisfaction of House’s obligation to Trane and that the trial court therefore erred in granting summary judgment to House and in denying summary judgment to Foster on this issue. We agree.

*598

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dixson v. State
721 S.E.2d 555 (Court of Appeals of Georgia, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
627 S.E.2d 188, 277 Ga. App. 595, 2006 Ga. App. LEXIS 160, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foster-co-general-contractors-inc-v-house-hvacmechanical-inc-gactapp-2006.