United States Ex Rel. a & M Petroleum, Inc. v. Santa Fe Engineers, Inc.

660 F. Supp. 1111
CourtDistrict Court, S.D. Mississippi
DecidedFebruary 26, 1987
DocketCiv. A. S86-0133(NG)
StatusPublished
Cited by1 cases

This text of 660 F. Supp. 1111 (United States Ex Rel. a & M Petroleum, Inc. v. Santa Fe Engineers, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. a & M Petroleum, Inc. v. Santa Fe Engineers, Inc., 660 F. Supp. 1111 (S.D. Miss. 1987).

Opinion

MEMORANDUM OPINION

GEX, District Judge.

This is an action brought under the Miller Act, 40 U.S.C. Section 270a-270d to recover the cost of materials furnished by the use-Plaintiff, A & M Petroleum, Inc., (A & M) to or for Gulf/American Constructors, Inc., (Gulf/American) a subcontractor on a public works contract.

Defendant Santa Fe Engineers, Inc., (Santa Fe) was the general contractor to the United States of America under a contract denominated No. V101C-1263, Project No. S20-E56 that provided for renovation and modernization of various buildings at the Veterans Administration Hospital in Gulfport, Mississippi. Defendants Industrial Indemnity Company and United States Fire Insurance Company executed performance and payment surety bonds in favor of the United States of America in connection with the above referenced contract. On or about February 2, 1984, Santa Fe subcontracted the performance of a part of the work on the Gulfport Veterans Administration Hospital to Defendant Gulf/American, as reflected in subcontract agreement No. 476-1. In November of 1984, Gulf/American began to purchase petroleum products, specifically diesel fuel and related supplies such as pumps, filters and grease from use-plaintiff A & M, which were needed to fulfill Gulf/American’s contractual responsibilities on the Gulfport VA project. All of A & M deliveries were made pursuant to separate and distinct purchase orders *1112 placed by Gulf/American during the course of the protect as reflected below:

Date Invoice No. Amount
11/15/84 8927 $ 91.58
3/6/85 344491 466.36
4/9/85 1011 114.60
4/15/85 1096 124.56
4/16/85 344315 108.40
4/18/85 1191 131.19
4/22/85 344295 6.60
4/22/85 1230 124.46
4/22/85 1219 30.30
4/23/85 1262 39.60
4/24/85 1274 105.46
4/24/85 1269 19.30
4/26/85 1331 21,120.00
4/27/85 344213 50.16
6/5/85 1900 38.60

Gulf/American paid $932.72 on its A &' M account on July 23, 1985. Further payments were not forthcoming; A & M first gave notice to Santa Fe on August 8, 1985, that Gulf /American had not paid use-plaintiff’s invoices for materials delivered to the project site.

It is undisputed that the petroleum products delivered by use-plaintiff to Gulf/American were furnished and substantially consumed in prosecution of the work provided for in Santa Fe’s main contract with the United States of America thus subjecting the general contractor and its surety to liability for any unpaid claim for the cost of the materials. It is further uncontested that each delivery made by use-plaintiff to the project site was a separate, distinct and independent contract wholly unrelated to any prior or subsequent delivery. The parties have, however, filed cross-motions for summary judgment on the question of the timeliness of use-plaintiff’s notice to Santa Fe of its claim. A & M’s position is that, since it last furnished materials to Gulf/American at the project site on June 5, 1985, any notice received by Santa Fe within ninety (90) days after that delivery is sufficient under 40 U.S.C. Section 270b(a) to impose liability upon Santa Fe for the cost of all materials supplied by use-plaintiff on or before that date. Santa Fe counters that, as each delivery was a separate and distinct contract wholly unrelated to any prior or subsequent delivery, 40 U.S.C. Section 270b(a) requires that the general contractor receive notice within ninety (90) days after each delivery before liability may be imposed.

40 U.S.C. Section 270b(a) provides in pertinent part:

[A]ny person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond upon giving written notice to said contractor within ninety days from the date on which such person ... supplied the last of the material for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied ____

40 U.S.C. Section 270b(a) (1976).

The application of the notice provision of Section 270b(a) to a claim for goods furnished to a subcontractor on an open account basis was first discussed in Noland Co. v. Allied Contractors, Inc., 273 F.2d 917 (4th Cir.1959). Noland had furnished supplies on an as needed basis to one of Allied’s subcontractors. Noland’s relationship with the subcontractor commenced on December 13, 1954, and ended on April 6, 1955. Twelve sales transactions occurred over that time frame. Noland was not paid by the subcontractor; notice of Noland’s claim was forwarded to Allied on May 5, 1955. Allied contended that, since some of the deliveries of materials were made more than ninety days prior to the May 5th notice, it was liable only for the cost of those goods supplied within the ninety day period preceding the notice. The district court concluded that Allied’s interpretation of the notice provision was correct and afforded Noland relief with respect to only those deliveries made within ninety (90) days of May 5,1955. On appeal, the Fourth Circuit reversed stating:

[T]he Miller Act lends itself to the construction that if all the goods in a series of deliveries by the materialman to a subcontractor are used on the same government project, the notice is in time *1113 as to all of the deliveries if it is given within ninety days from the last delivery.

Id. at 920.

The Court balanced the equities between the materialman/use-plaintiff and the general contractor and determined that one of the central purposes of the Miller Act, the protection of laborers and suppliers on a government contract, compelled the conclusion that the use-plaintiff be allowed to recover the cost of all goods supplied to a subcontractor pursuant to a series of orders regardless of the time of delivery as long as notice was given to the general contractor within ninety days after the date of the delivery of the last supplies ordered.

At the same time the Fourth Circuit was deciding Noland, the Second Circuit addressed the issue before the Court today in

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. William L. Crow Construction Co.
826 F. Supp. 647 (E.D. New York, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
660 F. Supp. 1111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-a-m-petroleum-inc-v-santa-fe-engineers-inc-mssd-1987.