United States ex rel. Raymond A. Bergen, Inc. v. DeMatteo Construction Co.

467 F. Supp. 22, 1979 U.S. Dist. LEXIS 14915
CourtDistrict Court, D. Connecticut
DecidedJanuary 22, 1979
DocketNo. Civil B76-395
StatusPublished
Cited by4 cases

This text of 467 F. Supp. 22 (United States ex rel. Raymond A. Bergen, Inc. v. DeMatteo Construction Co.) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Raymond A. Bergen, Inc. v. DeMatteo Construction Co., 467 F. Supp. 22, 1979 U.S. Dist. LEXIS 14915 (D. Conn. 1979).

Opinion

MEMORANDUM OF DECISION ON CROSS MOTIONS FOR SUMMARY JUDGMENT

DALY, District Judge.

I

This is a subcontractor’s action under the Miller Act, 40 U.S.C. § 270a and § 270b, to recover on the prime contractor’s bond for materials furnished for use in the construction of a United States postal facility. Arising in the context of cross motions for summary judgment, the critical issue is whether the use plaintiff provided the prime contractor with notice of action “within ninety days from the date on which such person . . . furnished or supplied the last of the material for which such claim is made,” as required by the Act. 40 U.S.C. § 270b(a).1

[23]*23II

The following facts are undisputed.2 The United States employed the DeMatteo Construction Company (DeMatteo) as the prime contractor in the construction of a preferential mail center in Hartford, Connecticut. DeMatteo, with Travelers Insurance Company as surety, executed the requisite Miller Act bond. DeMatteo subcontracted to the Bridgeport Pipe Engineering Company (Bridgeport Pipe) the job of furnishing and installing the plumbing and air conditioning systems. Bridgeport Pipe, in turn, engaged Raymond A. Bergen, Inc. (Bergen), the use plaintiff, to provide louvers and dampers.3 Bergen employed the Ruskin Manufacturing Company (Ruskin) to manufacture based upon particular specifications the louvers and dampers in sections for assemblage at the construction site and to provide special clips, necessary to fasten the sections to each other and the building.

The sections were delivered to the Hartford job site on three occasions; the shipment involving the last section of louvers and dampers arrived on January 12, 1976. Subsequent to the final delivery, at the time of installation, Bridgeport Pipe discovered that an insufficient number of clips had been included in the last delivery and contacted Bergen about the deficiency.4 Bergen notified Ruskin who proceeded to send the clips to Bridgeport Pipe on February 27, 1976 and on March 4, Bridgeport Pipe received fifty additional clips. According to the undisputed affidavit of Ruskin’s vice president, the omission of the clips in the January 12 delivery was an oversight. Bergen did not charge Bridgeport Pipe for these clips which were valued at $100.

On May 28, 1976, Bergen notified DeMatteo that Bridgeport Pipe had failed to pay $25,550. due for the materials furnished to the Hartford project. DeMatteo and its surety disclaimed liability under the Miller Act on the grounds that plaintiff had failed to comply with the ninety-day notice requirement of the Act. Defendants contend that the notice period had expired ninety days after January 12, the delivery date of the final shipment of louvers and dampers. Plaintiff maintains that notice was timely since the delivery date of the additional clips properly commenced the notice period. Both parties have moved for summary judgment.

III

The question for this Court’s determination is whether the notice of May 28 which was within ninety days after the delivery of the additional clips but not within ninety days of the final shipment of louvers and dampers complies with the requirement of § 270b(a) and permits Bergen to recover for all materials furnished for use at the Hartford job site. In cases of this nature, the applicable legal test employed in determining when the notice period commences is “whether . . . the material is sup[24]*24plied as a ‘part of the original contract,’ or for the ‘purpose of correcting defects, or making repairs.’ ” U. S. for the Use of Noland Co. v. C. B. Andrews, 406 F.2d 790 (4th Cir. 1969); U. S. for the Use of State Electrical Supply Co. v. Hesselden Construction Co., 404 F.2d 774 (10th Cir. 1968).

The Second Circuit applied this test in U. S. for the Use of G. E. Co. v. H. I. Lewis Construction Co. Inc., 375 F.2d 194 (2d Cir. 1967) and held that the delivery of two fixtures which were clearly replacements and “which were not supplied or furnished as part of the original contract cannot revive Miller Act liability extinguished by the expired ninety-day period . . . ” Id. at 201. The Court stated that although the Act is remedial in nature and therefore should be construed broadly to permit subcontractors to recover, the ninety-day notice provision must be preserved as a strict condition precedent to recovery in order to protect the prime contractor against double payments and to prevent delay in settlements between contractors and subcontractors. Id.; See also U. S. for the Use of Edwards v. Thompson Construction Corp., 273 F.2d 873, 875-6 (2d Cir. 1959), cert. denied, 362 U.S. 951, 80 S.Ct. 864, 4 L.Ed.2d 869 (1960).

Defendants, although admitting that the factual situation here may be dissimilar to Lewis and the “replacement parts” line of cases, contend that the policy considerations govern nevertheless and urge this Court to extend the rationale in those cases to deny Bergen recovery. Defendants maintain that unless the rationale in Lewis is adopted here, a prime contractor would remain liable on an order delivered in a sealed but incomplete fashion until ninety days after the deficiency was discovered and remedied which could occur years after delivery of the alleged final shipment and after the prime contractor paid the defaulting subcontractor.5 Defendants contend that if the ninety-day notice period is permitted to run from the delivery date of the additional clips, DeMatteo would be denied the protection against double payment which the Second Circuit stated the notice provision was intended to provide.6 Lewis, supra.

IV

First, this Court focuses upon whether the facts before it merit a determination that the clips were or were not replacement parts to permit summary judgment. It is well settled that the fundamental precondition of summary judgment is that no genuine issue of material fact exists. See Heyman v. Commerce and Industry Insurance Co., 524 F.2d 1317 (2d Cir. 1975). Either by uncontested affidavit or by agreement between the parties, it is established in this case that the shipment of January 12 did not include the clips delivered on March 4, and that the additional clips were part of the original contractual obligation and necessary to install the louver and damper sections.

A comparison with the Lewis case highlights the factual distinction between re[25]*25placement parts and the parts involved herein.7 In Lewis,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States ex rel. Balf Co. v. Casle Corp.
895 F. Supp. 420 (D. Connecticut, 1995)
US ON BEHALF OF & FOR USE OF BALF v. Casle Corp.
895 F. Supp. 420 (D. Connecticut, 1995)
Insurance Co. of North America v. Genstar Stone Products Co.
656 A.2d 1232 (Court of Appeals of Maryland, 1995)
Kuchenski v. Kramer Sheet Metal, Inc.
377 N.W.2d 133 (North Dakota Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
467 F. Supp. 22, 1979 U.S. Dist. LEXIS 14915, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-raymond-a-bergen-inc-v-dematteo-construction-co-ctd-1979.