Garff v. JR Bradley Company

436 P.2d 428, 84 Nev. 79, 1968 Nev. LEXIS 312
CourtNevada Supreme Court
DecidedJanuary 23, 1968
Docket5335
StatusPublished
Cited by9 cases

This text of 436 P.2d 428 (Garff v. JR Bradley Company) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Garff v. JR Bradley Company, 436 P.2d 428, 84 Nev. 79, 1968 Nev. LEXIS 312 (Neb. 1968).

Opinions

[80]*80OPINION

By the Court,

Thompson, C. J.:

This is an appeal from summary judgments in favor of suppliers of materials and labor (J. R. Bradley Company and Ray Heating Products, Inc.) to a subcontractor (Monroe Plumbing and Heating), and against the general contractors (Ryberg & Garff Construction Company and U.S. Enterprises of Reno, Inc.) and their surety (Federal Insurance Company). The contractors and surety also appeal from the refusal of the district court to enter summary judgments for them.

The cases arise out of the construction of the Carson City law enforcement facility. The subcontractor failed to fully pay the suppliers. Consequently, the suppliers each brought suit upon the payment bond given by the general contractors and their surety pursuant to NRS 339.025(b). The amount claimed due each supplier is not disputed. A direct contractual relationship existed between each supplier and the subcontractor, thus placing each case within the provisions of NRS 339.035(2) providing for suit upon a payment bond only when a claimant has given the notices provided for by sub-paragraphs (a) and (b) thereof.1 Neither claimant gave the [81]*8130-day notice required by subparagraph (a). The general contractors, however, had actual knowledge of the matters specified in that subparagraph. Each claimant did give the 90-day notice required by subparagraph (b).

The general contractors and surety contend that compliance with the notice provisions is a precondition to a claim for relief on the bond. Since neither claimant gave the 30-day notice his claim for relief must fail. On the other hand, the claimants each argue that the coverage of the bond here given is broader than required by NRS 339.025(b),2 and, upon the authority of Royal Indemnity Co. v. Special Service, 82 Nev. 148, 413 P.2d 500 (1966), recovery on the bond is allowable. Subordinately, the claimants suggest that actual knowledge on the part of the contractors of the matters specified in subparagraph (a) of NRS 339.035(2) worked an estoppel against, or a waiver by, the contractors of any right to rely upon the claimants’ failure to give the 30-day notice.

In ruling for the suppliers and against the general contractors and surety, the district court did not reach the notice issue. That court reasoned that the holding of the Royal Indemnity case controlled this litigation and permitted recovery on the payment bond.

It is our opinion that the Royal Indemnity case is inapposite. It is also our view that the general contractors did nothing to create an estoppel or to waive their rights with regard to the 30-day notice requirement, and that compliance by the suppliers with such requirement is a precondition to suit on the bond. Accordingly, we reverse the summary judgments entered below, and remand with direction to enter summary judgment for the general contractors and surety in each case.

[82]*821. In the Royal Indemnity case we held that the surety was liable on a bond where, by expressly denying liability for prior materials supplied, the surety, by implication, accepted liability for materials supplied to the contractor after the date of the bonding agreement. There, the bond afforded coverage for labor and material bills incurred by the contractor, even though the contractor’s licensing statute pursuant to which the bond was furnished did not specifically require such coverage.

Royal Indemnity is not on point with the instant matter. The statute with which we are concerned (NRS 339.025(b)) requires the contractor to furnish a payment bond “solely for the protection of claimants supplying labor or materials * * * to any of his subcontractors, in the prosecution of the work provided for in such contract.” The bond here in question was given pursuant to the statute and conformed with it. The condition of the bond is: “if said contractor * * * shall fail to pay, or cause to be paid, all just debts contracted by such contractor or any of his subcontractors, for labor performed upon or materials furnished for the contractor, * * * then said surety shall pay * * * .” The bond did not provide a broader coverage than contemplated by the statute, thus removing this case from the reach of the doctrine announced in Royal Indemnity Co. v. Special Service, supra.

2. The statutory preconditions to suit upon a payment bond are specified in NRS 339.035(2) (a) and (b). The claimant must, within 30 days after furnishing the “first of such materials or performing the first of such labor” serve on the contractor a written notice of the nature of the materials furnished or labor performed, identifying the person contracting for the labor or materials, and the site of performance. The claimant must also, within 90 days after performing the last of the labor or furnishing the last of the material, give the contractor written notice of the amount claimed, and the name of the person for whom the work was performed or the material supplied. As before stated, the 30-day notice was not given by the claimants in this case; the 90-day notice was. The statute allows suit on the bond “only” if each notice is given.3

The claimants assert that the general contractors and surety are estopped to rely upon the failure of the claimants to comply [83]*83with the 30-day notice requirement, since the contractors had actual knowledge that the claimants had performed work and furnished materials. Such actual knowledge does not create an estoppel. The statute places a duty upon the suppliers to give the notices therein specified. The contractors did not represent to the claimants that they need not comply with the notice requirements. Mere knowledge on the part of the contractors that the claimants were on the job or supplied materials does not constitute a representation by the contractors that the claimants need not follow the statute in perfecting their claims for relief on the bond. Absent such a representation, and a reliance thereon, the doctrine of estoppel cannot apply. Woods v. Bromley, 69 Nev. 96, 241 P.2d 1103 (1952); Farmers & Merchants National Bank v. Eureka Land & Stock Co., 56 Nev. 218, 49 P.2d 354 (1935); State ex rel. Thatcher v. Court, 46 Nev. 133, 207 P. 1105 (1922). Neither did the contractors waive their rights to insist that the claimants comply with the preconditions to suit upon the bond. Nothing appears in the record to suggest that this occurred.

As we see it, contractors frequently are aware of the identity of the suppliers of materials to subcontractors; frequently know the identity of those performing labor for the subcontractor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cucinotta v. Deloitte & Touche, L.L.P.
302 P.3d 1099 (Nevada Supreme Court, 2013)
Amfac Distribution Corp. v. Housing Authority
688 P.2d 318 (Nevada Supreme Court, 1984)
Coast Electric Co. v. Industrial Indemnity Co.
144 Cal. App. 3d 879 (California Court of Appeal, 1983)
Day & Night Manufacturing Co. v. Fidelity & Casualty Co.
452 P.2d 906 (Nevada Supreme Court, 1969)
Garff v. JR Bradley Company
436 P.2d 428 (Nevada Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
436 P.2d 428, 84 Nev. 79, 1968 Nev. LEXIS 312, Counsel Stack Legal Research, https://law.counselstack.com/opinion/garff-v-jr-bradley-company-nev-1968.