Opinion

*149 OPINION

By the Court,

Zenoff, D. J.:

We are called upon to construe a bonding agreement between a professional surety and a contractor to determine whether a materialman, due and owed monies from the contractor, may recover against the bond.

The surety, Royal Indemnity Company, Inc., contracted a $3,000 bond with Darby Air Conditioning which provided:

“NOW, THEREFORE, if the Principal herein (Darby) shall for the period beginning with the date hereof and ending with the expiration of One Year from said date, faithfully comply with all of the provisions of Chapter 624 of the Revised Statutes of Nevada, as amended, then this obligation shall be null and void, otherwise to remain in full force and effect.
“THE LIABILITY OF THE SURETY herein shall be confined to unlawful acts, omissions, or defaults of the Principal occurring subsequent to the date hereof, and prior to the expiration of One Year from said date; provided, however, that the Surety shall in no event be liable for labor and material bills incurred by the principal prior to the date hereof.”

Appellant Royal Indemnity argues this agreement was not a “materialmen’s bond” but only ran to the statutory requirements of NRS 624.270 which, appellant insists, do not extend to simple breaches of contract to materialmen. 1

*150 The lower court allowed recovery in a summary judgment. We affirm.

1. It is unnecessary to decide the exact limitations of NRS 624.270. Even if, as appellant claims, the statute does not extend to materialmen’s contracts, a bond may be conditioned more broadly than the statute requires and “is good at common law, if it is entered into voluntarily by competent parties for a valid consideration, and is not repugnant to the letter or policy of the law * * County v. Feldschau, 101 Ore. 369, 199 P. 953 (1921) and authorities cited therein; 18 A.L.R. 1227; 9 C.J. 29. Thus we look exclusively to the particular bonding contract here in issue.

2. We first resort to general rules of contractual construction. Every word must be given effect if at all possible. As was noted in Reno Club v. Investment Co., 64 Nev. 312, 324, 182 P.2d 1011, 173 A.L.R. 1145 (1947), “[t]he court is not at liberty, either to disregard words used by the parties, descriptive of the subject matter or of any material incident, or to insert words which the parties have not made use of. It cannot reject what the parties inserted, unless it is repugnant to some other part of the instrument.” Also, Hoaglund v. City of Los Angeles, 103 Cal.App.2d 499, 229 P.2d 823 (1951); Johnston v. Miller, 326 Mich. 682, 40 N.W.2d 770 (1950); Musto v. Grosjean, 208 Cal. 453, 281 P. 1022 (1929).

3. For purposes of this dispute, the instant contract has three crucial provisions: (1) that full compliance *151 with Ch. 624 by Darby shall make the surety, Royal Indemnity’s, obligation “null and void”; (2) that Royal’s liability shall be “confined to unlawful acts, omissions, or defaults” of Darby; and (3) that Royal “shall in no event be liable for labor and material bills incurred by (Darby) prior to the date” of the bonding agreement. The problem is to give full effect to each of these provisions. If we accept appellant’s argument that materialmen’s defaulted bills were not included in the bond, there appears no purpose for Royal expressly denying liability for prior materials, thus, by implication accepting liability for materials procured after the date of the bonding agreement.

4. Royal argues that the provision for materials was surplusage; “the extraneous insertions of over-cautious attorneys.” We cannot so discard plain words in a valid contract.

Royal next argues that the provision for materials must be read in context with Ch. 624, which does not expressly provide for guarantying the payment of materialmen’s bills, and Royal was freed of all obligations if Darby “faithfully complied] with all of the provisions of Chapter 624.” We must attempt to reconcile “faithful compliance] with * * * Chapter 624” with the later clause whereby Royal Indemnity impliedly agreed to incur liability for materials obtained during the term of the bonding contract, though Ch. 624, standing alone, might not require such a bonding.

5. “If clauses in a contract appear to be repugnant to each other, they must be given such an interpretation and construction as will reconcile them if possible.” Quinerly v. Dundee Corp., 159 Fla. 219, 31 So.2d 533, 534 (1947); see Hull v. Burr, 58 Fla. 432, 50 So. 754, 765 (1909). It is only where clauses are totally irreconcilable that a choice may be made between them. Morgan v. Firestone Tire & Rubber Co., 68 Idaho 506, 201 P.2d 976 (1948). In the instant contract, compliance with Ch. 624 can be harmonized with payments for materials in either of two ways: (1) the contract only encompassed payments for “unlawful” materials — i.e., those *152 obtained incident to a violation of Ch. 624; or (2) the bonding contract assumed that failure to pay a due and owing bill to a materialman was not “faithful compliance] with all of the provisions of Chapter 624”— regardless of whether Ch. 624 required a bonding of such payments.

We cannot accept the interpretation as to “unlawful” materials. Parties to a bonding agreement seem unlikely to have singled out for protection materialmen supplying only wrongful contractors. Certainly Ch. 624 does not so require. “If one interpretation would lead to an absurd conclusion, then such interpretation should be abandoned and the one adopted which would be in accord with reason and probability.” Quinerly v. Dundee Corp., supra; see Hull v. Burr, supra.

6. It is our view that full compliance with Ch. 624, at least insofar as the instant parties and contract were concerned, encompassed payment of materialmen’s bills in an appropriate spirit of “financial responsibility.” See NRS 624.260. 2 Although the $5,000 limit of the statutory bond seems unrealistic when applied to the construction industry, it is the sum fixed by the legislature and can be changed by the legislature.

7. We are reinforced in these views by a final point. The bonding requirements incident to a new contractor’s license are expressly set forth in NRS 624.270, supra.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Middendorf Sports v. Top Rank, Inc.
954 F.3d 1142 (Eighth Circuit, 2020)
In re Danastorg
499 B.R. 8 (D. Massachusetts, 2013)
Bielar v. Washoe Health Systems, Inc.
306 P.3d 360 (Nevada Supreme Court, 2013)
Edelstein v. Bank of New York Mellon
286 P.3d 249 (Nevada Supreme Court, 2012)
Bell v. Leven
90 P.3d 1286 (Nevada Supreme Court, 2004)
Musser v. Bank of America
964 P.2d 51 (Nevada Supreme Court, 1998)
Eversole v. Sunrise Villas VIII Homeowners Ass'n
925 P.2d 505 (Nevada Supreme Court, 1996)
Quirrion v. Sherman
846 P.2d 1051 (Nevada Supreme Court, 1993)
Shelter America Corp. v. Ohio Casualty & Insurance Co.
745 P.2d 843 (Court of Appeals of Utah, 1987)
Caldwell v. Consolidated Realty & Management Co.
668 P.2d 284 (Nevada Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
413 P.2d 500, 82 Nev. 148, 1966 Nev. LEXIS 207, Counsel Stack Legal Research, https://law.counselstack.com/opinion/royal-indemnity-co-v-special-service-supply-co-nev-1966.