San Joaquin Blocklite, Inc. v. Willden

184 Cal. App. 3d 203
CourtCalifornia Court of Appeal
DecidedAugust 8, 1986
DocketNo. F004221; No. F004346
StatusPublished
Cited by1 cases

This text of 184 Cal. App. 3d 203 (San Joaquin Blocklite, Inc. v. Willden) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
San Joaquin Blocklite, Inc. v. Willden, 184 Cal. App. 3d 203 (Cal. Ct. App. 1986).

Opinion

Opinion

BEST, J.

These separate appeals were consolidated by order of this court. Both appeals arise from an action by plaintiff, San Joaquin Blocklite, Inc. (Blocklite) against defendants Willden Construction Company (Willden) and Canadian Indemnity Company (Canadian), Michael T. Miller and the State of California. Miller and the State of California are not parties to these appeals. Blocklite’s second amended complaint alleged pertinent causes of action as follows: (I) breach of contract, (II) enforcement of stop notice, (III) account stated, (IV) enforcement of bond, (V) quantum meruit, (VI) money had and received, and (VII) open book account. Causes of action I, III, V, VI and VII were against Willden and Michael T. Miller on the theory they were coventurers. Following the filing of motions by the parties, the trial court entered its order for partial summary judgment, holding that Blocklite had substantially complied with the notice requirements of Civil Code1 sections 3098 and 3091 with regard to causes of action II and IV. The trial court also entered its order for summary adjudication of issues dismissing causes of action I, III, V, VI and VII.

A court trial was subsequently held on causes of action II and IV which resulted in a judgment being entered in favor of Blocklite and against Canadian on its payment bond for $32,817.33, with interest, plus an attorney fee of $10,000. The judgment also provided all moneys held by the State of California pursuant to Blocklite’s stop notice be paid to Blocklite and that said moneys would be an offset against the judgment against Canadian.

Willden and Canadian appeal from the judgment. Blocklite filed a separate appeal from that portion of the court’s earlier order dismissing causes of action I, III, V, VI and VII.

The Facts

Defendant Willden was the general contractor on a state highway project known as the Atwater Sound Wall. Defendant Michael T. Miller, doing business as Miller Masonry, did the masonry work necessary to build -the sound wall on Highway 99 in Merced. Plaintiff Blocklite supplied Miller with the block for the wall. Miller failed to pay for all of the material supplied by Blocklite.

[364]*364Before entering upon the construction of the sound wall, Willden, as principal, and Canadian, as surety, made, executed and filed a payment bond with the Department of Transportation of the State of California (Caltrans) as required by sections 3247 and 3248.

The only evidence of compliance shown by Blocklite with the prerequisite notice under section 3098 (for the second cause of action) was a form routinely sent by Caltrans whenever the state requires that certain materials be tested. The only evidence of compliance shown by Blocklite with the prerequisite notice under section 3091 (for the fourth cause of action) was a letter sent to Willden dated January 7, 1981. However, it is apparently conceded by defendants Willden and Canadian that Willden had actual notice that Blocklite was a material supplier and that Miller’s account was not completely paid.

Discussion

I

Did Blocklite comply with section 3098?

Willden and Canadian contend that Blocklite may not recover under its stop notice, since it did not send a preliminary 20-day notice as required by section 3098. Section 3098 provides in pertinent part: “‘Preliminary 20-day notice (public work), stop notice’ means a written notice from a claimant that was given prior to the filing of a stop notice on public work, and is required to be given under the following circumstances:

“(a) In any case in which the law of this state affords a right to a person furnishing labor or materials for a public work who has not been paid therefor to file a stop notice with the public agency concerned, and thereby cause the withholding of payment from the contractor for the public work, any such person having no direct contractual relationship with the contractor . . . may file such a notice, but no payment shall be withheld from any such contractor, pursuant to any such notice, unless such person has caused written notice to be given to such contractor, and the public agency concerned, not later than 20 days after the claimant has first furnished labor, services, equipment, or materials to the jobsite, stating with substantial accuracy a general description of labor, service, equipment, or materials furnished or to be furnished, and the name of the party to whom the same was furnished. Such notice shall be served by mailing the same by first-class mail, registered mail, or certified mail, postage prepaid, in an envelope addressed to the contractor at any place he maintains an office or conducts his business, or his residence, or by personal service. ...” Blocklite admitted not sending a preliminary 20-day notice as required by section 3098, but argued to the trial court that Lloyd Willden’s actual knowledge of the material supplier, [365]*365plus a notice sent by the state to the effect that the materials would have to be tested, either excused compliance or constituted a kind of substantial compliance. The question thus presented is: Does section 3098 require strict compliance with its notice provisions? In its order for partial summary judgment, the trial court found: “1. That the Letter from the State of California dated September 11, 1980 (Exhibit ‘H’ to the Deposition of the Defendant, Lloyd J. Willden) was sufficient preliminary notice by the Plaintiff, San Joaquin Blocklite, Inc., a California corporation, doing business as Blocklite, to Lloyd J. Willden, as the general contractor, under the requirements of California Civil Code Section 3098; ...” By this finding, the trial court accepted, in effect, Blocklite’s contention that where the general contractor has actual notice of the existence and identity of a material supplier, compliance with the transmittal methods and notice requirements of the statute is not required.

In Harold L. James, Inc. v. Five Points Ranch, Inc. (1984) 158 Cal.App.3d 1 [204 Cal.Rptr. 494], this court noted that the courts have taken opposite approaches to the procedural aspects of the mechanic’s lien law. We noted that in IGA Aluminum Products, Inc. v. Manufacturers Bank (1982) 130 Cal.App.3d 699 [181 Cal.Rptr. 859] and Romack Iron Works v. Prudential Ins. Co. (1980) 104 Cal.App.3d 767 [163 Cal.Rptr. 869], a strict compliance analysis to section 3097 (§ 3097 prescribes the preliminary notice required to recover under stop notices in private works) was applied under factual circumstances involving service of the notice called for by that section. We further noted in Wand Corp. v. San Gabriel Valley Lbr. Co. (1965) 236 Cal.App.2d 855 [46 Cal.Rptr. 486], the court concluded that, with limited exceptions, the mechanic’s lien law should be given a liberal construction to avoid the determination of important property interests by technical defects of form.

After discussing the three cases mentioned above, we concluded as follows: “We do not regard the three cases discussed above as being irreconcilable. The general principles of liberal construction enunciated in Wand Corp. are still good law, subject to this refinement, added by Romack and IGA Aluminum

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Whitehead
517 A.2d 373 (Supreme Court of New Jersey, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
184 Cal. App. 3d 203, Counsel Stack Legal Research, https://law.counselstack.com/opinion/san-joaquin-blocklite-inc-v-willden-calctapp-1986.