Hub Construction Specialties, Inc. v. Esperanza Charities, Inc.

244 Cal. App. 4th 855, 198 Cal. Rptr. 3d 335, 2016 Cal. App. LEXIS 90
CourtCalifornia Court of Appeal
DecidedFebruary 8, 2016
DocketB263398
StatusPublished
Cited by2 cases

This text of 244 Cal. App. 4th 855 (Hub Construction Specialties, Inc. v. Esperanza Charities, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hub Construction Specialties, Inc. v. Esperanza Charities, Inc., 244 Cal. App. 4th 855, 198 Cal. Rptr. 3d 335, 2016 Cal. App. LEXIS 90 (Cal. Ct. App. 2016).

Opinion

Opinion

GRIMES, J.—

SUMMARY

A preliminary written notice to the property owner is a necessary prerequisite to the validity of a mechanic’s lien. The issue in this case is whether a mechanic’s lien is invalid because the plaintiff lienholder did not strictly *857 comply with the then-effective statutory requirement governing proof that the preliminary written notice was served on the defendant property owner by certified mail.

Defendant stipulated that the notice was served by certified mail, that the United States Postal Service Web site tracking certified mail items showed the notice was delivered, and that defendant actually received the notice. Despite these stipulations, defendant contends the lien is invalid because plaintiff has no return receipt, and the statute applicable at the time required plaintiff to prove the notice was served by “affidavit . . . accompanied either by the return receipt of certified or registered mail, or by a photocopy of the record of delivery and receipt maintained by the post office, showing the date of delivery and to whom delivered . . . .” (Civ. Code, former § 3097.1, subd. (a), enacted by Stats. 1975, ch. 46, § 2, p. 80 and repealed by Stats. 2010, ch. 697, § 16.) The trial court agreed and dismissed the case, concluding that plaintiff had not strictly complied with the statute.

We reverse the judgment. While strict compliance with the notice provisions of the mechanic’s lien law is required, the applicable precedents do not require or justify applying that rule to the statutory provisions governing proof that the required notice was properly given. A stipulation eliminates the need for proof. Accordingly, where it is stipulated that notice was given in the statutorily prescribed manner, to require further proof would elevate form over substance to a degree that cannot be countenanced in light of the long-established principle that the mechanic’s lien law is “remedial legislation, to be liberally construed for the protection of laborers and materialmen.” (Connolly Development, Inc. v. Superior Court (1976) 17 Cal.3d 803, 826-827 [132 Cal.Rptr. 477, 553 P.2d 637] (Connolly).)

FACTS

The parties stipulated to the pertinent facts as follows.

Plaintiff Hub Construction Specialties, Inc., supplied rebar and other materials to the general contractor on a construction project on property owned by defendant Esperanza Charities, Inc. The general contractor failed to pay plaintiff $81,857.55 for the materials, a claim plaintiff has determined is uncollectible.

On March 16, 2012, “[plaintiff] caused a ‘California Preliminary Notice’ to be mailed by Certified Mail, to [the general contractor], [defendant], and the project construction lender, ... as attested to by Proof of Service executed 9/28/12.”

*858 Plaintiff “furnished postage to the U.S. Postal Service sufficient to serve all certified mail items and possesses a ‘Certified Mailer Manifest for; 3-16-12’ reflecting [the general contractor, defendant and the construction lender] as addressees and bearing an Official Stamp of the United States Postal Service.”

Plaintiff did not request, and did not pay a fee to the United States Postal Service for, a “return receipt” for the notices.

“The U.S. Postal Service website tracks certified mailed items and the tracking for the certified mailed items indicates that they were all delivered. Further, [defendant] has acknowledged in verified discovery responses that it received the preliminary notice which [plaintiff] served. There is no signed return receipt.”

On December 12, 2012, defendant recorded a notice of completion, reciting that the project was completed on December 3, 2012. On December 27, 2012, plaintiff recorded a mechanic’s lien against the property in the claim sum of $81,857.55. On February 6, 2013, plaintiff filed a complaint to foreclose the mechanic’s lien.

The value of the rebar that plaintiff furnished to the project from February 24, 2012 (20 days prior to the preliminary notice), was $53,070.18, and interest through December 1, 2014, amounted to $9,287.25. Plaintiff sought a judgment for foreclosure of the mechanic’s lien, and defendant sought a judgment that the lien was invalid and an order expunging the lien.

The case was initially scheduled for a court trial on the stipulated facts, but the court ordered a modified summary judgment procedure instead (without separate statements, and based on the stipulated facts). After a hearing, the trial court denied plaintiff’s motion for summary judgment and ordered the property released from plaintiff’s lien. The court found plaintiff “cannot provide sufficient proof of service by documentation of the return receipt of certified mail, [or] a photocopy of the record of delivery and receipt maintained by the post office, showing the date of delivery and to whom delivered ... as required under the statute in effect at the time the effectiveness of the preliminary notice as given is sought to be established.”

Plaintiff filed a timely notice of appeal.

DISCUSSION

Plaintiff contends the absence of a return receipt does not bar enforcement of the mechanic’s lien, because proof of service is unnecessary where service *859 by certified mail has been admitted. Defendant contends the law in effect when plaintiff served the preliminary notice applies and must be strictly construed; because that law required a “return receipt” or a “record of delivery” to prove service of the notice, neither of which plaintiff has, plaintiff’s lien is unenforceable. 1

We conclude from the relevant authorities that, while the principle of strict construction applies to “the manner or form of serving notice upon an affected party” (Harold L. James, Inc. v. Five Points Ranch, Inc. (1984) 158 Cal.App.3d 1, 6 [204 Cal.Rptr. 494] (Harold L. James)), it does not extend to matters of proof in a case where the defendant has admitted that notice was served in the statutorily prescribed manner.

We begin by reciting the statutory provisions in effect when the preliminary notice was served, and then turn to the relevant case authorities.

1. The Statutory Background

Under current law, this case would not be before us. The law that became operative on July 1, 2012 — several months after plaintiff served the preliminary 20-day notice, but before execution of plaintiff’s affidavit of service— expanded methods of giving notice and methods of proving that notice was given. Defendant concedes that, under current law, the “certified mailer manifest” proffered by plaintiff “might well have sufficed as a record of ‘payment.’ ” 2 The statutes that were operative until July 1, 2012, however, stated as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
244 Cal. App. 4th 855, 198 Cal. Rptr. 3d 335, 2016 Cal. App. LEXIS 90, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hub-construction-specialties-inc-v-esperanza-charities-inc-calctapp-2016.