Wangler v. . Swift

90 N.Y. 38, 1882 N.Y. LEXIS 349
CourtNew York Court of Appeals
DecidedOctober 10, 1882
StatusPublished
Cited by24 cases

This text of 90 N.Y. 38 (Wangler v. . Swift) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wangler v. . Swift, 90 N.Y. 38, 1882 N.Y. LEXIS 349 (N.Y. 1882).

Opinion

Danforth, J.

According to the case made by the original complaint, one Jackson was engaged during September and October, 1870, in the construction of a bridge (for the city of Brooklyn) over Bushwick creek, and induced Sherman and Kiyler to furnish materials and perform labor thereon during those months to the amount of $2,584.39, which he agreed to pay. Without doing so he died, and Mary Jackson was appointed administratrix of his estate.

Thereafter, on the 23d of November, 1871, for a satisfactory consideration to him paid, the defendant agreed with her that he would pay Sherman and Kiyler such sum as should appear due to them from her intestate for work and material done and furnished by them in the construction of said bridge, under a certificate from the engineer in charge of said work * * * and hold her harmless from any claim of the said Sherman and Kiyler, which should be justified by the certificate of said engineer; ” they assigned their claim against the estate of Jackson to the plaintiff. In September and October, 1870, one John McOloskey was the engineer in charge of the construction of the bridge, and he, in writing, certified the above sum with interest to be due Sherman and Kiyler from said estate, by reason of such work and material. The certificate of McOloskey was before suit exhibited to the defendant by the plaintiff, and payment of the amount therein certified to be due has, since its presentation, been demanded by the plaintiff of the defendant, but he refuses to pay.

The defendant by answer denied, among other things, that McOloskey was the engineer in charge of the construction of the bridge at the time stated, and upon this issue much evidence was given upon the trial.

Before its conclusion, however, the trial judge ruled: that the certificate of the engineer was a condition precedent to the plaintiff’s right of recovery; that McOloskey was not engineer at any time, and that what he did amounted to nothing, so far *41 as this condition precedent is concerned. Before this ruling was made, it had appeared that one Faron was in charge of the bridge from September, 1871, to a time subsequent to and including the date of the agreement by the defendant, and from what passed between the plaintiff’s counsel and the court, it would seem that the judge held that the certificate of the engineer then in charge of the bridge would be required. Upon the plaintiff’s application, and against the objection and exception of the defendant, he was permitted to amend his complaint by alleging it. The plaintiff then put in evidence, against the defendant’s objection and exception, Faron’s certificate, which in form was no doubt a compliance with the terms of the defendant’s undertaking, and stated the sum above named to be due from the estate of Jackson. It did not appear that it had been exhibited to the defendant before the trial, or that he had received any notice of it whatever, and upon these grounds the defendant moved to dismiss the complaint. The court denied the motion and directed a verdict for the plaintiff.

Two questions arise : First, Did the agreement require a certificate from the engineer in charge of the bridge during September and October, 1870, the time the work and material were furnished by Sherman and Kiyler ? Second, If not, was the plaintiff’s cause of action complete without notice to the defendant of Faron’s certificate, and a demand under it of the sum ascertained to be due ?

First, We have no evidence of the agreement between the parties, except as it is set out in the pleadings, and from that our conclusion accords with the theory on which the action was brought and which led to the averment that McCloskeyj the engineer in charge of the work in September and October, gave the certificate and so enabled the plaintiff to allege performance of the condition precedent on which the defendant’s liability depended.

Jackson was dead. The defendant had no knowledge of the work done or the material furnished; the sum due was an unliquidated and uncertain amount to be ascertained by reference to matters known to Sherman and Kiyler, the other party *42 to the agreement. But it is obvious that Swift was not willing to accept a statement made by them, and before his obligation attached, the certificate of a third person was required. It must precede any recovery of the money due under the contract. Its procurement, therefore, was a necessary part of the plaintiff’s duty, if he would charge the defendant. It. was intended to exhibit the plaintiff’s claim, and establish it. We may reasonably infer, therefore, that the parties had in mind the engineer who prepared the plan and specifications, who knew what was to be done under the agreement of Sherman and Kiyler with Jackson, and by the latter under his agreement with the city, which was constructing the bridge ; who knew also what had been done, and who, knowing of the delivery of the materials and the work as it went on from day to day, was the person most likely, if not the only one, who was capable of answering from his own knowledge the inquiries called for by the agreement.

The bill included piles, excavation, bailing and drawing off water, lumber and plank for scaffold, labor in building and re-constructing it, driving piles, taking up and replacing the same. Much of the materials and work was evidently of- a temporary nature, necessary for the permanent structure which was to follow it, and of a character to be estimated only by a daily eye-witness, or one whose duty required his actual supervision of the work.

The defendant agreed to be bound by the determination of such a person, because from his knowledge the necessary information could be drawn. It is impossible to suppose that one having no personal knowledge of the work, or means of acquiring it, and whose connection with the structure began long after the services were rendered and material furnished, could have been selected by a person wholly ignorant as to these things, to determine, not only the quantity of each, but the amount due therefor.

The theory of the complaint accords with this view, and is, we think, the correct one. It agrees with the nature of the contract and the object which the parties had in mind in calling for the certificate. This conclusion leads to a new trial. *43 Circumstances not now in evidence may, however, appear upon another trial, if one shall be had, and affect the construction we give to this agreement. It seems best, therefore, to consider the second question; and upon this, too, we think the complaint is well drawn, and should have been adhered to. As the certificate was a necessary part of the plaintiff’s case, and to be procured by him, as without it the defendant could not know for what, or how much he was to pay, there could be no default on his part until informed of and shown a efertificate, and a demand made thereon by the plaintiff. Until then he could make no payment. His agreement is to -pay Sherman & Enyler the sum which should appear due, “under” the certificate, “ all the engineer should certify they were entitled to.” This fact, when ascertained, would be known to the plaintiff, but not the defendant, and he could not be hable to an action until the certificate was submitted to him, or otherwise brought to his attention, and a demand made under it. Until then his contract was not.absolute but conditional.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abeyta v. Atchison
336 P.2d 1051 (New Mexico Supreme Court, 1959)
Rebora v. British & Foreign Marine Insurance
180 N.E. 90 (New York Court of Appeals, 1932)
Vanderhoef & Co. v. Youmans, Inc.
85 Misc. 418 (Appellate Terms of the Supreme Court of New York, 1914)
Southern Manufacturing Co. v. R. L. Moss Manufacturing Co.
13 Ga. App. 847 (Court of Appeals of Georgia, 1913)
First National Bank v. . Story
93 N.E. 940 (New York Court of Appeals, 1911)
Toye v. United Dressed Beef Co.
141 A.D. 332 (Appellate Division of the Supreme Court of New York, 1910)
Bank of Commerce v. Broyles
120 P. 670 (New Mexico Supreme Court, 1910)
Korbly v. Loomis
88 N.E. 698 (Indiana Supreme Court, 1909)
Coplew v. Durand
95 P. 38 (California Supreme Court, 1908)
Heinemann v. Brasch
53 Misc. 552 (New York Supreme Court, 1907)
Packard v. Long Island Railroad
52 Misc. 98 (Appellate Terms of the Supreme Court of New York, 1906)
West Chicago Park Commissioners v. Schillinger
117 Ill. App. 525 (Appellate Court of Illinois, 1905)
Citizens' Bank of Buffalo v. Rung Furniture Co.
76 A.D. 471 (Appellate Division of the Supreme Court of New York, 1902)
Piehl v. Albany Railway
19 A.D. 471 (Appellate Division of the Supreme Court of New York, 1897)
Electric Lighting Co. of Mobile v. Elder Bros.
115 Ala. 138 (Supreme Court of Alabama, 1896)
Hand v. Shaw
18 Misc. 1 (Appellate Terms of the Supreme Court of New York, 1896)
Audsley v. Mayor of New York
74 F. 274 (Second Circuit, 1896)
Gay v. Haskins
11 Misc. 134 (Superior Court of Buffalo, 1895)
Fay v. Muhlker
20 N.Y.S. 671 (New York Court of Common Pleas, 1892)
Fulton v. Metropolitan Life Ins.
19 N.Y.S. 660 (New York Court of Common Pleas, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
90 N.Y. 38, 1882 N.Y. LEXIS 349, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wangler-v-swift-ny-1882.