Electric Lighting Co. of Mobile v. Elder Bros.

115 Ala. 138
CourtSupreme Court of Alabama
DecidedNovember 15, 1896
StatusPublished
Cited by33 cases

This text of 115 Ala. 138 (Electric Lighting Co. of Mobile v. Elder Bros.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Electric Lighting Co. of Mobile v. Elder Bros., 115 Ala. 138 (Ala. 1896).

Opinion

BBICKELL, C. J.

This was an action by appellees against the appellant to recover for the breach of a contract to pay the stipulated price for the boring of an artesian well. The correctness of the rulings of the trial court will depend largely upon the construction of the contract, which was in writing and is set out in haec verba in the first count of the complaint. The first count assigns as the breach the failure of the defendant to comply with the provisions of the fourth paragraph of the agreement. There was no objection made to the complaint. The special count declaring on the contract is followed by five common counts, claiming for work and labor done and materials furnished, &c.

The defense set up by many special pleas, the sustaining of demurrers to which constitutes the principal assignments of error, was that there had never been any satisfactory completion of the said well, or that said well as completed was not satisfactory to defendant, because [148]*148the latter, being the owner of-and operating -an electric lighting plant, and desiring a supply of water for use in its boilers for the purpose of generating steam, entered into said contract for, the purpose of securing said water, which facts the plaintiffs well knew, and that the water furnished by said well was wholly unfit for use in said boilers. This defense is based upon the theory that, inasmuch as the plaintiffs knew the purpose for which the water was wanted, and, by the terms of the contract, the work was -undertaken at their own risk and expense, and the payment of the compensation was made contingent upon its satisfactory completion, they, therefore, assumed the risk of procuring water suitable for use in defendant’s boilex*s, axid that, failing in this, there was no ‘ ‘ satisfactory completion ’ ’ of the well; axid consequently no such performance by plaintiffs as entitled them to demand the stipulated compensation. On the other hand, it is contended on behalf of the plaintiffs that, having in all respects complied with the provisions of the first three paragraphs of the contract, by boring a well at the designated place, and of the stipulated size and capacity, and procuring thereby deep strata water in the quantity agreed upon, without the use of any strainer to obtain a flow from intermediate strata, using in the work oxily first-class material and workmanship, supplied at their own expense, they are entitled to demand payment.

We cannot yield full assent to either proposition. In the construction of all contracts the object is to ascertain and, if-possible, effectuate the intention of the parties, so that performance may be enforced according to the sense in which they mutually understood it at the time it was made ; and to ascertain the intention it is necessary xiot only to examine the instrument itself, but also to consider the situation of the parties, the subject-matter, and the object it is intended to accomplish ; and every word and clause must be taken into consideration, and if possible, given some effect.—1 Brick. Dig. 386, § 161; Mason v. Alabama Iron Co., 73 Ala. 274. But, except in cases where mutual mistake or fraud is shown, a meaning cannot be forced into a contract in opposition to its text and repugnant to its terms. It is a rule of general application that whex’e parties have entered into written engagements with express stipulations, these [149]*149cannot be changed by implication. The presumption is, that, having expressed some, they have expressed all the conditions by which they intend to be bound. Blackman v. Dowling, 63 Ala. 306. “Construction is the building up with given elements, not the forcing of extraneous matter into the text.” Conceding that plaintiffs knew the purpose for which the water they had contracted to procure was wanted, and even knew that water of the quality which the well subsequently furnished would not be suitable for that purpose, the text of the contract, construed as a whole, precludes the construction that the parties intended that plaintiffs should assume the risk of procuring water of a suitable quality, and that payment should be contingent on their procuring such water; or that the defendant, after the whole work had been completed in substantial compliance with the requirements of the contract, should be able to avoid liability by basing its dissatisfaction, not on the quantity, but the quality of the water.

It may reasonably be assumed, in construing the contract, that both parties were ignorant of the quality of deep strata water that could be reached by the well. But both knew, or had reason to believe, that water from any intermediate strata would be unsuitable. And it was this ignorance as to the one and knowledge as to the other that probably led to the insertion in the contract of the third paragraph, the only one which makes any reference to the quality of the water, which reads : “The water flowing from said well is to be deep ' strata water, and no strainer will be placed to obtain a flow from intermediate or intervening strata, as water flowing from that source is likely to he of such quality as is not adapted to the use of the party of the second part.” The parties having in this paragraph provided that the water should be from deep strata, without any reference to its quality, and declared that water from any intermediate strata 'would not be suitable, we cannot conclude otherwise than that, either the defendant believed that the deep strata water would be suitable, or, being in ignorance as to its quality, it was the intention of the parties that he, and not the plaintiffs, should assume all risk as to its suitability. We are confirmed in this conclusion by the sixth and last paragraph of the contract, which may be considered, to some extent at least, as a construction of [150]*150the contract by the parties themselves, and is, therefore, entitled to great weight in ascertaining their intention in this respect. It reads : “It is the spirit of this agreement that the party of the first part undertakes the work herein proposed at its own risk and responsibility, and that failing in the supply of water to the quantity herein stipulated, and on the conditions above mentioned, it is to receive no pay from party of the second part.” "We construe the phrase “on the conditions above mentioned” to refer to the words “supply of water,” and not to anything in the fourth paragraph, as counsel for appellant insists, and the whole paragraph to mean, that if the well fails to supply water on the conditions above mentioned (that is, deep strata water, as provided in the third' paragraph), and the quantity stipulated (that is, 250 gallons at the surface and 700 gallons under the pump, as provided in the first paragraph), then plaintiffs are to receive no pay for their work. The clear expression in this paragraph of the contingencies upon the happening of which plaintiffs are to receive no compensation, precludes the construction that the parties intended that no compensation was to be received if the water supplied by the well should be of a quality unfit for use in defendant’s boilers. To adopt this construction and ingraft upon the contract such a condition, would be to imply a condition which is repugnant to its terms, and was not in the minds of the parties when they executed it. The presumption is that, having expressed some, they have expressed all the conditions by which they . intended - to be bound.

On the other hand, it is not to be supposed that the parties inserted any important word or clause in the contract without intending that some effect should be given to it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Health Maintenance Group v. Rutledge
459 So. 2d 889 (Court of Civil Appeals of Alabama, 1984)
Neumiller Farms, Inc. v. Cornett
368 So. 2d 272 (Supreme Court of Alabama, 1979)
Homa-Goff Interiors, Inc. v. Cowden
350 So. 2d 1035 (Supreme Court of Alabama, 1977)
Kennedy v. Henley
309 So. 2d 435 (Supreme Court of Alabama, 1975)
Mozley v. Boen
143 So. 2d 304 (Alabama Court of Appeals, 1962)
Jones v. Dumas Development Co.
229 S.W.2d 936 (Court of Appeals of Texas, 1950)
Schock v. Holleman
32 So. 2d 309 (Alabama Court of Appeals, 1947)
Norwood Hospital, Inc. v. Howton
26 So. 2d 427 (Alabama Court of Appeals, 1946)
Shelton v. Shelton
192 So. 55 (Supreme Court of Alabama, 1939)
Pollard v. Rogers
173 So. 881 (Supreme Court of Alabama, 1937)
Skagerberg v. Blandin Paper Co.
266 N.W. 872 (Supreme Court of Minnesota, 1936)
Wagner v. Alabama Farm Bureau Federation
143 So. 909 (Supreme Court of Alabama, 1932)
Manufacturers' Finance Acceptance Corp. v. Woods
132 So. 611 (Supreme Court of Alabama, 1930)
Utley v. Stevens
130 So. 405 (Supreme Court of Alabama, 1930)
Manufacturers' Finance Acceptance Corp. v. Woods
132 So. 608 (Alabama Court of Appeals, 1930)
Goodwin v. Adler
124 So. 108 (Supreme Court of Alabama, 1929)
Ex Parte Patrick
88 So. 837 (Supreme Court of Alabama, 1921)
Woods v. Postal Telegraph-Cable Co.
87 So. 681 (Supreme Court of Alabama, 1920)
Schofield v. School District No. 113
184 P. 480 (Supreme Court of Kansas, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
115 Ala. 138, Counsel Stack Legal Research, https://law.counselstack.com/opinion/electric-lighting-co-of-mobile-v-elder-bros-ala-1896.