Fay v. Muhlker

20 N.Y.S. 671, 1 Misc. 321, 48 N.Y. St. Rep. 699
CourtNew York Court of Common Pleas
DecidedNovember 7, 1892
StatusPublished
Cited by15 cases

This text of 20 N.Y.S. 671 (Fay v. Muhlker) is published on Counsel Stack Legal Research, covering New York Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fay v. Muhlker, 20 N.Y.S. 671, 1 Misc. 321, 48 N.Y. St. Rep. 699 (N.Y. Super. Ct. 1892).

Opinion

Bischoff, J.

This action was to foreclose a mechanic’s lien claimed under a notice filed June 7, 1884. At that time the law in force, relative to such liens in the city of New York, was Laws 1882, c. 410, §§ 1807-1823, “Consolidation Act, ” (chapter 379, Laws 1875,) which provided that, as a requisite to the acquisition of a valid lien, “every original contractor” must file with the county clerk of the county, “within sixty days after the completion of his contract,” a claim setting forth certain particulars, which, in so far as concerns this appeal, need not be here enumerated. The law did not, in express terms, as by section 15, c. 342, Laws 1885, provide that in an action brought to foreclose a lien, if the plaintiff should for any cause fail to establish its validity on the trial, he might, notwithstanding that fact, be permitted to recover a personal judgment against the party at whose instance the work was done, or the materials were supplied, as the case might be; and, in the absence of such a provision, this court has held in Hubbell v. Schreyer, 14 Abb. Pr. (N. S.) 284, (reversed upon other grounds, 56 N. Y. 604, opinion in full, 15 [672]*672Abb. Pr. [N. S.] 300,) that a personal judgment could be rendered for the indebtedness only which has accrued under a contract, and respecting which the lien is, at least, partly valid. See, also, McGraw v. Godfrey, 14 Abb. Pr. (N. S.) 397; Spencer v. Barnett, 35 N. Y. 94.

The claim filed was for $1,105, of which $500 was alleged to be due for the balance of the last payment specifically agreed to be made by defendant, pursuant to a written agreement entered into by the parties, upon the architect’s certificate that the buildings which plaintiff was to erect had been completed, and $605 for various items of extra work. It was not disputed on the hearing before the referee that the $500 item was unpaid, but as to this the defense was interposed that the architect’s certificate had not been procured. Plaintiff conceded that no certificate in writing had been had from the architect, and claimed that it was waived. Evidence to establish the fact of the waiver was introduced on plaintiff’s behalf, and its finding requested of the referee, but refused. The referee found, from abundant evidence, that all the work under the written agreement was fully performed by plaintiff; that plaintiff had performed extra work of the value of $280; that all the work, that done under the written agreement and the extra work, except an item of $55 of the latter which was for taking down and rebuilding the area walls, was completed before April 4, 1884; that the work of taking down and rebuilding the area walls was not completed until after April 7, 1884, and was done under an oral contract separate and distinct from the written agreement; that plaintiff’s claim of a lien was filed more than 60 days after all the work, except that of taking down and rebuilding the area walls, had been completed; that as to the work last excepted the claim of a lien was filed within 60 days after its completion; that there was due defendant upon his counterclaims $209; and from ttiese facts the referee concluded that plaintiff’s lien extended only to the item of $55 for taking down and rebuilding the area walls; that the lien was extinguished by the counterclaims; and directed judgment for the defendant for the amount of his counterclaims in excess of the amount for which plaintiff’s lien was adjudged valid.

By express stipulation of the parties, which may be found at the end of the case, all questions which might otherwise arise concerning the allowance of defendant’s counterclaims are eliminated from our consideration on this appeal. Though the written agreement did not expressly require the architect’s certificate to be in writing, such is implied by the word “certificate.” And. Law Dict. p. 160; 3 Amer. & Eng. Enc. Law, p. 59. Its procurement by plaintiff constituted a condition precedent upon the performance of which his right to payment was dependent, (St. John v. Potter, [Com. Pl. N. Y.] 19 N. Y. Supp. 230; Thomas v. Fleury, 26 N. Y. 26; Wyckoff v. Meyers, 44 N. Y. 143; Glacius v. Black, 50 N. Y. 145; Martin v. Leggett, 4 E. D. Smith, 255; Grube v. Schultheiss, 4 Daly, 207, affirmed, 57 N. Y. 669;) and, to maintain his right to recover the $500 item in this action, he was necessarily compelled to show either that the certificate was wrongfully withheld, or that it was waived. He undertook the latter, on the hearing before the referee, and cannot on this appeal be permitted to assume an attitude inconsistent with that taken on the trial. Home Ins. Co. v. Western Transp. Co., 51 N. Y. 93, 96; Stapenhorst v. Wolff, 65 N. Y. 596; Lockwood v. Quackenbush, 83 N. Y. 607; Wangler v. Swift, 90 N. Y. 38, 44; Wines v. Mayor, etc., 70 N. Y. 613; Codd v. Rathbone, 19 N. Y. 37, 39. If we assume that the architect's certificate was not waived, as found by the referee, and to the contrary of which he refused to find at plaintiff’s request, then plaintiff had not entitled himself by performance of the condition precedent to payment of the $500 item. If, on the other hand, we assume that the certificate was waived, and that the referee erred in finding that it was not, and in refusing to find that it was, then the fact remains that the work was performed before April 4, 1884, more than 60 days before the notice of lien was filed, and the errors referred to are im* [673]*673material, since the conclusion that the lien did not extend to this $500 would be inevitable; and errors which are immaterial and harmless afford no ground for reversal. Tenney v. Berger, 93 N. Y. 524; Thorne v. Turck, 94 N. Y. 90; Story v. Association, 95 N. Y. 474; Ellwanger v. Fish, 60 N. Y. 651.; Flannagan v. Maddin, 81 N. Y. 623; Downs v. Railroad Co., 56 N. Y. 664; and, as to equity cases, In re New York Cent. & H. R. R. Co., 90 N. Y. 343. In either case, therefore, the judgment appealed from would have been proper.

In what has been said above we assume that the referee correctly found that the work of taking down and rebuilding the area walls was rendered upon an independent employment, and that it was not a part of the work required of plaintiff under the written agreement, and we now proceed to demonstrate that this assumption is proper. The original written agreements entered into by the parties to this action required plaintiff to construct defendant’s buildings, and included the erection of the area walls. All this was done and completed before April 4, 1884. So plaintiff contended and testified, and so the referee found. Having done all he undertook to do, plaintiff was not required to do the work over again, in the absence of a provision to-that effect in the agreement. After the area walls had been erected and completed by plaintiff, they were suffered to become defective through no fault of his. So plaintiff further contended, so the referee further found, and uponi this theory plaintiff claimed to be entitled to, and was allowed to recover, $55 for doing the work of taking down and rebuilding the walls.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Russell & Gallagher v. Yesler Estate, Inc.
154 P. 188 (Washington Supreme Court, 1916)
Valley Lumber & Manufacturing Co. v. Driessel
93 P. 765 (Idaho Supreme Court, 1907)
Corotinsky v. Maimin
37 Misc. 777 (Appellate Terms of the Supreme Court of New York, 1902)
Kafka v. Levensohn
18 Misc. 202 (Appellate Terms of the Supreme Court of New York, 1896)
Pohalski v. Ertheiler
18 Misc. 33 (Appellate Terms of the Supreme Court of New York, 1896)
Lazarus v. Ludwig
17 Misc. 378 (Appellate Terms of the Supreme Court of New York, 1896)
Carter, Rice & Co. v. Howard
17 Misc. 381 (Appellate Terms of the Supreme Court of New York, 1896)
Allen v. Rector of the Church of the Beloved Discipline
16 Misc. 584 (Appellate Terms of the Supreme Court of New York, 1896)
Freudenheim v. Raduziner
36 N.Y.S. 815 (New York Court of Common Pleas, 1895)
Berner v. Kaye
35 N.Y.S. 181 (New York Court of Common Pleas, 1895)
Winch v. Farmers' Loan & Trust Co.
32 N.Y.S. 244 (New York Court of Common Pleas, 1895)
Kruger v. Braender
23 N.Y.S. 324 (New York Court of Common Pleas, 1893)
Sperry v. Hellman
21 N.Y.S. 1014 (New York Court of Common Pleas, 1893)
McGrath v. Mangels
20 N.Y.S. 869 (New York Court of Common Pleas, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
20 N.Y.S. 671, 1 Misc. 321, 48 N.Y. St. Rep. 699, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fay-v-muhlker-nyctcompl-1892.