St. John v. Potter

19 N.Y.S. 230, 46 N.Y. St. Rep. 883
CourtNew York Court of Common Pleas
DecidedJune 6, 1892
StatusPublished
Cited by3 cases

This text of 19 N.Y.S. 230 (St. John v. Potter) is published on Counsel Stack Legal Research, covering New York Court of Common Pleas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
St. John v. Potter, 19 N.Y.S. 230, 46 N.Y. St. Rep. 883 (N.Y. Super. Ct. 1892).

Opinion

Bischoff, J.

The action was brought to recover for work, labor, and services rendered and materials furnished for and at the request of the defendant in the removal and rebuilding of the foundation intended for the mausoleum to be erected for him at Rosedale Cemetery, Orange, N. J. The defense was that such services were performed and' the materials furnished under a written contract, pursuant to the terms of which payment was only to be made upon production of the architect’s certificate of approval, which had been omitted. The evidence taken upon the trial is not returned to us, and we are therefore to accept the facts as they were found by the referee, and to inquire only whether those facts sustain the conclusion that plaintiff is entitled to the judgment appealed from. Schwartz v. Weber, 103 N. Y. 658, 8 N. E. Rep. 728; Travis v. Travis, 122 N. Y. 449, 25 N. E. Rep. 920.

It appears that on August 30, 1888, the parties entered into a written contract by which plaintiff undertook “to erect and finish the new building known as the ‘Henry A. Potter Mausoleum,’ at Rosedale Cemetery, Orange, N. J., agreeably to the drawings and specifications made by John P. Hardenburgh, Jr., architect, and signed by the parties, and hereto annexed, within the time aforesaid, in a good, workmanlike, and substantial manner, to the satisfaction and under the direction of the said architect, to be testified by a writing or certificate under the hand of said architect,” and to “find and provide such good and proper Clark’s island granite as shall be proper and sufficient for the completing and finishing all the said granite work as per three-quarter inch scale drawing made by the architect, for the sum of four thousand four hundred dollars, ($4,400.00.)” It was also agreed by the parties that payment of [231]*231the several installments should only be made upon the plaintiff’s production, in each instance, of the architect’s certificate of the facts entitling him to the payment; that “the specifications and the drawings are intended to co-operate, so that any works exhibited in the drawings and not mentioned in the specifications, or vice versa, are to be executed the same as if it were mentioned in the specifications and set forth in the drawings, to the true meaning and intention of the said drawings and specifications, without any extra charge-whatsoever;” that “should the owner at any time during the progress of the said building request any alteration, deviation, additions, or omissions from the said contract, he shall be at liberty to do so, and the same shall in no way affect or make void the contract, but will be added to or deducted from the amount of the contract, as the case may be, by a fair and reasonable valuation;” that all differences which might arise respecting the true construction and meaning of the drawings and specifications should be referred to the architect for his final decision; and that, if there should be any dispute respecting the value of extra work, or work omitted, it should be determined by arbitration. It does not appear that the specifications referred to in the contract were produced upon the trial, none appear among the papers submitted, and it is conceded by appellant's counsel that they never had existence, and to this latter fact the present obscurity concerning the extent of plaintiff’s undertaking is apparently attributable. The drawings, however, were produced, and appear as defendant’s Exhibits 2 and 3, and from these it appears that the mausoleum was intended to consist of a superstructure of granite, the foundation of which was to be of brick. On the trial plaintiff disputed whether the services and materials for which she sought to recover in this action were among those required of her under the contract. The burden of proving that they were rested upon the defendant, and, if he has not sustained it, the referee’s finding that the services and materials mentioned in the complaint were rendered and furnished at the request of the defendant, and that they were reasonably worth the sum of $423.80, plainly authorized the judgment rendered. As matters of fact the referee also reported, at the req uest of the defendant, that, at the time of the execution of the contract, no work had as yet been performed, either upon the superstructure or its foundation; that a first foundation was built about October or November, 1888; that in April or May, 1889, before the building was completed, and after plaintiff had caused the granite work to be prepared and shipped from Maine to Orange, N. J., ready for use, defendant requested plaintiff to remove the foundation then built, and to rebuild it; that the services rendered and the materials furnished, for which recovery was sought in this action, were those rendered and furnished, in the removal and rebuilding of the foundation, and that such services and materials were not among those called for by the drawings; that plaintiff had failed to show that the services and materials were of the quality required by the contract, or that they were done or furnished to the satisfaction of the architect, nor had the latter’s certificate of approval been obtained or produced, or its nonproduction excused; that in May, 1889, plaintiff had demanded payment for the services and materials in suit, and that such payment was refused by the defendant because the architect’s certificate had not been given or produced; that plaintiff had not shown that she had offered to refer any dispute to the architect, or to have the value of the work ascertained by arbitration, as provided for in the contract.

It is conceded by respondent’s counsel, and too well settled in principle and by authority to admit of any dispute, that if one person agrees to perform services and furnish materials for another, under the direction of and subject to the approval of a third, to be attested by his certificate in writing before payment shall be required to be made, the production of the certificate will constitute a condition precedent upon the performance of which the right to enforce payment is dependent, and that unless the certificate is produced or [232]*232waived, or its nonproduction sufficiently excused, no recovery can be had for the services •performed and the materials furnished. The sole question, therefore, upon this appéal is, do the facts reported show the services and materials rendered and furnished in the removal and rebuilding of the foundation to have been among those undertaken by plaintiff by the contract? If they do, .then the judgment is erroneous. If they do not, then plaintiff’s recovery was proper. Manifestly the referee assumed the facts insufficient to show that they were, and treated the service and materials as independent of the contract and unaffected by its provisions, and upon the tenableness of this assumption the validity of the judgment must depend. Can we say that the referee erred ? The contract provided that plaintiff should erect and finish the building agreeably to certain drawings and specifications, and to these we are referred to ascertain the extent of plaintiff’s obligation. But there 'were no specifications. How, then, can we say what was required of plaintiff? Our attention is directed to the clause which provides that the specifications and drawings are intended to co-operate, and it is urged that, if the foundation is apparent from the drawings, the building of it must be taken to be among the work which plaintiff has promised to perform. But this same clause says that the work which plaintiff is expected to do when it is exhibited in the drawings is work not mentioned in the specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mullen v. Cohen
34 Misc. 398 (City of New York Municipal Court, 1901)
Wagener v. Butler
27 N.Y.S. 350 (New York Court of Common Pleas, 1894)
Fay v. Muhlker
20 N.Y.S. 671 (New York Court of Common Pleas, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
19 N.Y.S. 230, 46 N.Y. St. Rep. 883, Counsel Stack Legal Research, https://law.counselstack.com/opinion/st-john-v-potter-nyctcompl-1892.