Valley Lumber & Manufacturing Co. v. Driessel

93 P. 765, 13 Idaho 662, 1907 Ida. LEXIS 94
CourtIdaho Supreme Court
DecidedDecember 7, 1907
StatusPublished
Cited by51 cases

This text of 93 P. 765 (Valley Lumber & Manufacturing Co. v. Driessel) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Valley Lumber & Manufacturing Co. v. Driessel, 93 P. 765, 13 Idaho 662, 1907 Ida. LEXIS 94 (Idaho 1907).

Opinions

SULLIVAN, J.

This is an action brought to foreclose a materialman’s lien under the provisions of the mechanic’s lien law of this state. One Driessel was the owner of the premises and contracted with one Morrison for the construction of a dwelling-house on the premises described in the complaint. It is alleged in the amended complaint that the plaintiff, who is respondent here, is a corporation organized under the laws of the state of Washington, and doing business in the town of Lewiston, Idaho; that said Driessel is the owner of the premises described in the complaint, and that the defendant Morrison was the contractor and agent of Driessel, and as such agent entered into a contract with the respondent, whereby it was to furnish the material for the construction of a certain dwelling-house; that the respondent furnished the material between the twenty-third day of November, 1904, and the fifteenth day of March, 1905, which material was actually used in the construction of said building, of the agreed value of $552.47; that there was thereafter paid on said account $300.98, leaving a balance due of $251.49, together with interest thereon, and that the plaintiff, within sixty days from March 15, 1905, the date of furnishing the last item of said lumber, duly filed its claim of lien on the [667]*667eleventh day of May, 1905, in the office of the recorder of Nez Perce county. The defendants filed a general demurrer to the complaint, which was overruled by the court. They thereafter filed a joint answer, denying the material allegations of the complaint, except the corporate existence of the plaintiff, and admitted that Driessel was the owner of the premises described in the complaint. The cause was tried by the court without a jury and judgment was rendered in favor of the respondent. This appeal is from the judgment and order denying a new trial.

It appears from the testimony in the case that there were two contracts entered into between Morrison and Driessel. The first was for the building and construction of a dwelling-house which was completed on January 16, 1905, and the respondent rendered him a bill, or a statement, on the 20th of January, for all the lumber that he had used in the construction of said dwelling-house. It also appears from the record that Driessel rented the house before or about the time it was completed, and the tenants took possession thereof. Thereafter they desired a porch built on to said house, and it would appear that they expressed their desire to Driessel and he consented to have a porch built, and on the 13th of March, 1905, fifty-nine days after the delivery of the last item of material under the first contract, he entered into another contract with Morrison for the construction of said porch, and on that date Morrison ordered the lumber for its construction from the respondent, to the amount of about $25, and the respondent furnished the lumber for said porch on the thirteenth and fifteenth days of March. The respondent filed its materialman’s lien on the eleventh day of May, 1905, fifty-seven days after furnishing the last material for the porch.

It is first contended by counsel for appellant that as there were two separate contracts, one for the construction of the house and the other for the construction of the porch, that said contracts had no connection with each other and were entirely separate and severable, and that the last one cannot be tacked on to the first, and thus keep alive the materialman’s [668]*668lien for the material furnished for the construction of the house for more than sixty days after its completion under the first contract.

The evidence shows beyond a doubt that the house was constructed under one contract and the porch under another and separate contract. It also shows that the house was completed about the sixteenth day of January, 1905, and that the owner leased the house about the time of its completion and the tenants took possession. It also appears that the owner lived in Genesee, Latah county; that he went to Lewiston on the 13th of March and his tenants persuaded him to have said porch constructed, and on that date he made a contract with the appellant Morrison to erect said porch. The contract for the porch was not made until about fifty-nine days after the respondent had furnished the last material for the construction of the house.

The court in its findings of fact virtually finds that the house and porch were constructed under one contract, but that finding is not supported by the evidence. The secretary of the respondent company testified that he did not know the house was completed on or about the sixteenth day of January, but his testimony is not very clear on that point. He testified further that Morrison told him that he put the lumber furnished on the 13th and 15th of March into the porch, while Morrison swears positively that the house was built under one contract and the porch under another and separate contract. The fact that the respondent presented Morrison with an itemized statement of all the lumber furnished for the construction of the house on the 20th of January, 1905, is very suggestive of the fact that the respondent was informed that the’building was completed, as Morrison testified on the completion of a building the company furnished him an itemized statement of the material furnished and that he checked it over to ascertain whether or not it was correct, but does not testify that he informed respondent that the contract was completed or that it had knowlédge of that fact. There is no positive testimony in the record showing that the respondent had information that the house and [669]*669the porch were constructed under separate contracts. The circumstance of respondents furnishing an itemized statement of the lumber used in the construction of the house, to say the least, is suggestive and significant. If the record showed that the respondent had such information, the rule laid down in Central Loan & Trust Co. v. O’Sullivan, 44 Neb. 834, 63 N. W. 5, would apply. In that opinion, the court said: “A materialman cannot tack one contract to another so as to procure a lien for all the materials furnished under separate contracts by filing his claim within the required time from the date of furnishing material pursuant to one contract”; and in Schulenberg v. Vrooman, 7 Mo. App. 133, the court said: “Where all the items of an account except the last few were supplied under one contract and that contract was executed and the transaction closed, held, that the time for filing a lien could not be extended by furnishing on a new request additional articles and adding them to the completed account.” On this point see, also, Fay v. Muhlker, 20 N. Y. Supp. 671; Scott v. Cook, 8 Mo. App. 193; Sanford v. Frost, 41 Conn. 617; Frankoviz v. Smith, 34 Minn. 403, 26 N. W. 225.

It is contended by counsel for respondent that it had no knowledge that Morrison and Driessel had one contract for the house and one for the porch, and that the contract, so far as it was concerned, was continuous and entire and the time within which to file a lien dated from the date of the last item of material furnished. That, no doubt, was the theory upon which the trial court rendered its decision.

Among other authorities cited by respondent is the case of Darlington Lumber Co. v. Karris, 107 Mo. App. 148, 80 S. W. 688. In that case the company and one Taylor agreed to the estimate of the lumber to be used in the Harris building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michael L. Kelly v. Pamela Wagner
393 P.3d 566 (Idaho Supreme Court, 2017)
Hap Taylor & Sons, Inc. v. Summerwind Partners, LLC
338 P.3d 1204 (Idaho Supreme Court, 2014)
Credit Suisse AG v. Teufel Nursery, Inc.
321 P.3d 739 (Idaho Supreme Court, 2014)
Franklin Building Supply Co. v. Sumpter
87 P.3d 955 (Idaho Supreme Court, 2004)
Barlow's, Inc. v. Bannock Cleaning Corp.
647 P.2d 766 (Idaho Court of Appeals, 1982)
Dairy Equipment Co. of Utah v. Boehme
442 P.2d 437 (Idaho Supreme Court, 1968)
Boone v. P & B LOGGING COMPANY
397 P.2d 31 (Idaho Supreme Court, 1964)
Homefinders v. Lawrence
335 P.2d 893 (Idaho Supreme Court, 1959)
Standard Lumber Co. v. Fields
187 P.2d 283 (Washington Supreme Court, 1947)
Dolton v. Green
164 P.2d 795 (California Court of Appeal, 1945)
Ideal Cement Stone Co. v. Dohse
16 N.W.2d 151 (Nebraska Supreme Court, 1944)
Building Supplies, Inc. v. Gillingham
135 P.2d 832 (Washington Supreme Court, 1943)
American Home Benefit Ass'n v. United American Benefit Ass'n
120 P.2d 1010 (Idaho Supreme Court, 1942)
John Hancock Mutual Life Insurance v. Girard
64 P.2d 254 (Idaho Supreme Court, 1936)
Rasmussen v. Fresno Traction Co.
32 P.2d 1091 (California Court of Appeal, 1934)
Bannock Lumber & Coal Co. v. Tribune Co.
4 P.2d 662 (Idaho Supreme Court, 1931)
Shaw Supply Co., Inc. v. Morgan
282 P. 492 (Idaho Supreme Court, 1929)
Gallafent v. Tucker
281 P. 375 (Idaho Supreme Court, 1929)
Lewin Lumber Co. v. Guttman
27 Ohio N.P. (n.s.) 69 (Court of Common Pleas of Ohio, Hamilton County, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
93 P. 765, 13 Idaho 662, 1907 Ida. LEXIS 94, Counsel Stack Legal Research, https://law.counselstack.com/opinion/valley-lumber-manufacturing-co-v-driessel-idaho-1907.