Standard Lumber Co. v. Fields

187 P.2d 283, 29 Wash. 2d 327, 175 A.L.R. 309, 1947 Wash. LEXIS 380
CourtWashington Supreme Court
DecidedDecember 1, 1947
DocketNo. 30296.
StatusPublished
Cited by23 cases

This text of 187 P.2d 283 (Standard Lumber Co. v. Fields) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Standard Lumber Co. v. Fields, 187 P.2d 283, 29 Wash. 2d 327, 175 A.L.R. 309, 1947 Wash. LEXIS 380 (Wash. 1947).

Opinion

Jeffers, J.

This is an appeal by defendants, Floyd F. Fields and wife, from a judgment entered March 19, 1947, in favor of plaintiff, Standard Lumber Company, a corporation.

Plaintiff instituted this action against defendants to foreclose a lien for materials furnished by plaintiff for use in the construction of a grain elevator, bunkhouse, and shop, on land owned by defendants. It is alleged that defendant Floyd Fields, on a date unknown to plaintiff, entered into a contract with J. J. Berry, under the terms of which Berry was to construct and build, simultaneously, upon the southeast quarter of section 32, township 16 north, range 40, E.W.M., a grain elevator, bunkhouse, and shop; that thereafter, on or about June 27, 1945, plaintiff agreed to sell and deliver, upon Berry’s order, building materials and supplies for use in the construction of such buildings upon the premises; that on or about June 27, 1945, plaintiff commenced to deliver the materials and supplies to Berry for the purpose aforesaid, and continued such deliveries from time to time, the last delivery being made on or about December 1, 1945.

It is further alleged that written notice of the delivery of materials was mailed to defendant Floyd Fields within five days after the first delivery; that the reasonable and agreed value of the materials furnished was $2,248.99, and according to the terms of sale, payment was to be made within thirty days of delivery; that there was paid on account $580.59, leaving a balance due of $1,677.90, including $9.50 interest.

It is further alleged that plaintiff, within ninety days after December 1, 1945, the date the last materials were *330 furnished, duly filed with the auditor of Whitman county its claim of lien.

Defendants demurred to the complaint on the ground that there was a defect or nonjoinder in parties defendant in not naming the contractor, J. J. Berry, as a party defendant. The demurrer was overruled. A motion made by defendants for a bill of particulars was granted, as modified. Plaintiff furnished a bill of particulars, which shows the approximate date of each delivery, description of materials, price, credits, and a balance due of $1,677.90. This bill of particulars covers some five pages, and shows the approximate date of the first delivery as June 27, 1945, and the last delivery being made on or about December 1, 1945.

Defendants answered the complaint, admitting the ownership of the property, the corporate existence of plaintiff, and that they entered into a contract with J. J. Berry, but denying that by the terms of the contract Berry was to construct the buildings simultaneously, and denying the other material allegations of the complaint. Defendants alleged affirmatively that they entered into two separate contracts with Berry, the first on or about June 23, 1945, for the construction of a grain elevator with flathouse and a bunkhouse, and the second on or about September 5, 1945, for the construction of a shop building.

It is further alleged that Berry ceased work on the elevator and bunkhouse on or about September 1, 1945, and that none of the materials were used in, or delivered for use in, such buildings after that date; that plaintiff’s right to file a lien for materials used in the elevator and bunkhouse expired ninety days after September 1, 1945.

It is further alleged that the contract to construct the shop building was a separate and distinct contract from the contract to build the grain elevator, and that plaintiff did not give defendants notice that it would claim a lien against the shop building.

It is also alleged that, by reason of a conversation between M. C. Mink, plaintiff’s agent, and defendant Floyd Fields, plaintiff waived its lien and is estopped from main *331 taining this action; that all sales of materials made by plaintiffs after September 1, 1945, were illegal and void, because they were made without plaintiff requiring a priority therefor, although plaintiff knew that defendants’ priority extended only to the grain elevator and not to the shop building, and that such priority expired September 1, 1945; also that such sales were made in violation of conservation order L-41.

Plaintiff, by its reply, admitted that J. J. Berry commenced building the shop building on or about September 5, 1945, but denied the other affirmative matter contained in defendants’ answer.

As shown by the memorandum opinion filed by the trial court, which is made a part of the statement of facts, it was the theory of the court that, even though there were two separate contracts entered into between the owner and the contractor for the construction of the buildings, when the plaintiff, which is seeking to foreclose its lien, established the fact that it furnished the material to the contractor under one continuous contract with him, then, if defendants seek to defeat the right of foreclosure on the ground that there were two separate and distinct contracts, after showing their existence they must go further and either show that plaintiff had actual knowledge that two contracts existed or prove such facts and circumstances as would amount to constructive' notice to the materialman and put it on inquiry to ascertain whether or not two contracts did, in fact, exist. The memorandum opinion states:

“In this case the furnishing of the materials was continuous and there are no such circumstances as would tend to show that the plaintiff had notice of the completion of the original contract, and that another contract had been entered into between the owner and the builder. The burden so to do was on the defendants. They have not sustained the burden of proving such knowledge. The plaintiff last furnished materials on December 1, 1945, and thereafter the claim of lien was timely filed in the office of the county auditor on February 15, 1946.”

The court concluded that plaintiff was entitled to a decree against defendants foreclosing its hen upon the prem *332 ises for $1,672.50, together with interest and an attorney’s fee of $250. A decree to that effect was entered March 19, 1947, and this appeal by defendants followed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shelcon Construction Group, LLC v. Haymond
351 P.3d 895 (Court of Appeals of Washington, 2015)
Shelcon Construction Group v. Scott Haymond
Court of Appeals of Washington, 2015
Mannington Carpets, Inc. v. Hazelrigg
973 P.2d 1103 (Court of Appeals of Washington, 1999)
District Heights Apartments v. Noland Co.
95 A.2d 90 (Court of Appeals of Maryland, 1998)
CKP, Inc. v. GRS Construction Co.
821 P.2d 63 (Court of Appeals of Washington, 1991)
S.K. Drywall, Inc. v. Developers Financial Group, Inc.
819 P.2d 931 (Arizona Supreme Court, 1991)
Trane Co. v. Brown-Johnston, Inc.
739 P.2d 737 (Court of Appeals of Washington, 1987)
Amfac Distribution Corp. v. Union Rock & Materials Corp.
711 P.2d 607 (Court of Appeals of Arizona, 1985)
Portland Electric & Plumbing Co. v. Dobler
672 P.2d 103 (Court of Appeals of Washington, 1983)
Confinement Specialists, Inc. v. Schlatter
626 P.2d 223 (Court of Appeals of Kansas, 1981)
Olson v. Scholes
563 P.2d 1275 (Court of Appeals of Washington, 1977)
Galvanizer's Co. v. State Highway Commission
509 P.2d 73 (Court of Appeals of Washington, 1973)
Brandt v. Impero
463 P.2d 197 (Court of Appeals of Washington, 1969)
Brower Co. v. Noise Control of Seattle, Inc.
401 P.2d 860 (Washington Supreme Court, 1965)
Den Adel v. Blattman
357 P.2d 159 (Washington Supreme Court, 1960)
Anderson v. Taylor
347 P.2d 536 (Washington Supreme Court, 1959)
Bank of Hawaii v. Char
43 Haw. 316 (Hawaii Supreme Court, 1959)
Monarch Lumber Co. v. Wallace
314 P.2d 884 (Montana Supreme Court, 1957)
Dealers Supply Co. v. First Christian Church
276 S.W.2d 769 (Court of Appeals of Tennessee, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
187 P.2d 283, 29 Wash. 2d 327, 175 A.L.R. 309, 1947 Wash. LEXIS 380, Counsel Stack Legal Research, https://law.counselstack.com/opinion/standard-lumber-co-v-fields-wash-1947.