Western Hardware & Metal Co. v. Maryland Casualty Co.

177 P. 703, 105 Wash. 54, 1919 Wash. LEXIS 541
CourtWashington Supreme Court
DecidedJanuary 9, 1919
DocketNo. 14793
StatusPublished
Cited by6 cases

This text of 177 P. 703 (Western Hardware & Metal Co. v. Maryland Casualty Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Hardware & Metal Co. v. Maryland Casualty Co., 177 P. 703, 105 Wash. 54, 1919 Wash. LEXIS 541 (Wash. 1919).

Opinion

Parker, J.

The plaintiff, "Western Hardware & Metal Company, seeks recovery upon a bond executed by the defendant, Maryland Casualty Company, as surety, under Rem. Code, § 1159, relating to security for the furnishing of labor, material and supplies for the carrying on of public work. Trial in the superior court for King county, sitting without a jury, resulted in findings and judgment in favor of the plaintiff, from which the defendant ha's appealed to this court.

The controlling facts may be summarized as follows : On May 15,1916, Musgrove & Blake, copartners, entered into a contract with Seattle School District No. 1, by which they agreed to furnish the material for, and install, a heating and ventilating plant in the West Queen Anne schoolhouse, for the sum of $12,758. On May 20, 1916, Musgrove & Blake, as principals, and appellant casualty company, as surety, executed a bond in the sum of $19,137 to secure the faithful performance of the contract, and also conditioned, as provided by Rem. Code, § 1159, that Musgrove & Blake:

“Shall pay all laborers, mechanics, and subcontractors and materialmen, and all persons who shall supply such person or persons or subcontractors with provisions and supplies for the carrying on of such work. . . .”

On May 29, 1916, Musgrove & Blake sublet the furnishing and installing of the sheet metal work of the heating plant to Joe Zimmerer, doing business as Zimmerer Manufacturing Company, whereby he agreed to furnish the material for, and install, all the sheet metal work of the plant for the sum of $2,167; Zimmerer then being the owner of and conducting a sheet metal shop in ¡Seattle wherein he pressed and worked sheet metal into such form as was necessary for whatever jobs he might have had on [56]*56hand. On June 2, 1916, Zimmerer, not having sheet metal on hand for the performance of his subcontract, purchased from respondent, Western Hardware & Metal Company, of Seattle, dealers in heavy hardware of that nature, sheet metal of the value of $766.93, for the purpose of performing his subcontract, with the distinct understanding on the part of both himself and the respondent that the sheet metal so furnished was for his subcontract and was to go into, and become a part of, the heating and ventilating plant. Soon thereafter the whole of the sheet metal so purchased by Zimmerer of respondent was delivered by respondent to him at his shop. Thereafter, on June 5, 1916, respondent notified Musgrove & Blake that it had so furnished and delivered to Zimmerer material for the performance of his subcontract, and that they and their surety would be held for the payment of the purchase price therefor, and also advising them of the amount of the purchase price. This notice was given strictly in compliance with the provisions of § 1159-1 of Rem. Code, respondent manifestly having in view the possible necessity of a suit upon the bond to recover the purchase price of the material so furnished. The material was delivered by respondent to Zimmerer at his shop, because it was there that Zimmerer was going to press the sheet metal into form for use in the construction of the heating plant. It was material well adapted to that purpose, and we think the evidence plainly warrants the conclusion that it would necessarily have to be pressed into proper form for use in the structure at some shop having proper tools and appliances therefor, rather than upon the premises where it was to be finally put in place. It is plain, we think, that Musgrove & Blake knew that Zimmerer was going to do the pressing and shap[57]*57ing of the material in his shop, and that he was doing so with the express knowledge and consent of Mus-grove & Blake. Only about $140 worth of the material so furnished and delivered actually went into and became a part of the structure. To this extent appellant casualty company conceded that respondent was entitled to recover upon the bond, and made tender of that amount accordingly. Before completing his subcontract, Zimmerer went into bankruptcy and failed to complete it. What became of the portion of the metal so furnished by respondent which did not go into the plant does not appear with certainty, though the evidence points to the conclusion that Zimmerer disposed of it elsewhere. It is plain that respondent was in nowise responsible for the failure of Zimmerer to place all of the sheet metal in the plant. On March 7, 1917, the contract being completed by Mus-grove & Blake with other sheet metal so far as was necessary, the plant was accepted by the school district. On March 13,1917, respondent, not having been paid for the material so furnished by it to Zimmerer, filed its claim therefor against the bond with the proper officers of the school district. This was done timely and in strict compliance with Rem. Code, § 1161, with a view to enforcing the claim of respondent against the bond and appellant as surety thereon. Soon thereafter this action was commenced, resulting in judgment rendered therein as above noticed.

It is contended in appellant’s behalf that it is not liable upon its bond for the purchase price of that portion of the sheet metal furnished by respondent which was not actually used in the construction of the heating and ventilating plant. Counsel for appellant invoke the law announced in some of the lien decisions, holding that actual use of material in the construction [58]*58of a building is indispensable to tbe creation of a lien right in the one furnishing it. We have recognized, that there is generally an analogy between mechanics’ and materialmen’s lien statutes and bonding statutes such as ours, since the latter are generally for the purpose of providing security for labor and material in lieu of security therefor by lien upon property which would be subject to lien under private ownership. This analogy, in so far as a claimant’s rights as against the property or the bond are concerned, would seem to be complete when both the lien and bonding statutes define the work and material the payment for which is secured by the lien or the bond, in substance the same. Clough v. Spokane, 7 Wash. 279, 34 Pac. 934; National Surety Co. v. Bratnober Lumber Co., 67 Wash. 601, 122 Pac. 337. Our mechanics’ and materialmen’s lien statute, in so far as it specifies the furnishing of material for which a lien may be asserted by the one furnishing it, reads:

“Every person . . . furnishing material to be used in the construction ... of any . . . building . . . has a lien upon the same for the . . . material furnished by each, respectively, .' . . and every contractor, subcontractor, architect, builder or person having charge, of the construction, alteration or repair of any property subject to the lien as aforesaid, shall be held to be the agent of the owner for the purposes of the establishment of the lien created by this chapter. ’ ’ Bern. Code, § 1129. .

Our bonding statute, in so far as it relates to .the securing of payment for material, provisions and supplies for the carrying on of public work, provides that such bond shall be conditioned that the contractor ' shall:

“. . . pay all laborers, mechanics and subcontractors and materialmen, and all persons who shall supply such person or persons, or subcontractors, with [59]*59provisions and supplies for the carrying on of such work, . . .” Rem. Code, § 1159.

It would seem, therefore, that, since our lien statute secures by lien payment for “furnishing material to be used in the construction,”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Standard Lumber Co. v. Fields
187 P.2d 283 (Washington Supreme Court, 1947)
Hall & Olswang v. Aetna Casualty & Surety Co.
296 P. 162 (Washington Supreme Court, 1931)
Warming v. Hargis
294 P. 248 (Washington Supreme Court, 1930)
Haskell v. McClintic-Marshall Co.
289 F. 405 (Ninth Circuit, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
177 P. 703, 105 Wash. 54, 1919 Wash. LEXIS 541, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-hardware-metal-co-v-maryland-casualty-co-wash-1919.