Huttig Bros. Manufacturing Co. v. Denny Hotel Co.

32 P. 1073, 6 Wash. 122, 1893 Wash. LEXIS 240
CourtWashington Supreme Court
DecidedMarch 23, 1893
DocketNo. 689.
StatusPublished
Cited by22 cases

This text of 32 P. 1073 (Huttig Bros. Manufacturing Co. v. Denny Hotel Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Huttig Bros. Manufacturing Co. v. Denny Hotel Co., 32 P. 1073, 6 Wash. 122, 1893 Wash. LEXIS 240 (Wash. 1893).

Opinion

*124 The opinion of the court was delivered by

Scott, J.

Several actions were brought in the superior court of King county to foreclose liens against a hotel building and the ground upon which the same is situated, for materials furnished therefor; the Denny Hotel Company being the owner and Fabian S. Potvin the contractor for the erection of said building. The causes were consolidated and tried together by virtue of an order of the superior court, and three appeals have been taken from the decree therein rendered. The Denny Hotel Company appeals from the decree establishing' the lien of Huttig Brothers Manufacturing Company; and the Huttig Brothers Manufacturing Company and the Bridge & Beach Manufacturing Company appeal from the provisions of said decree establishing the mortgage lien of the Cornell University as prior to their said liens. The appeal of the Denny Hotel Company as against Huttig Brothers Manufacturing Company will be first discussed.

Said plaintiffs claimed a lien for materials furnished for said hotel to said Potvin as contractor, amounting to $21,-000, and it appears that of this amount only $2,300'was used in the construction of the building, said building never having been completed, and said contractor having abandoned work thereon. It is contended by the appellant, the Denny Hotel Company, that there can be no lien for materials furnished which were not used in the construction of the building; and it is further contended that the right to a lien for the.materials that were used was lost in consequence of the respondent having intermingled said claim with the claim for materials not used'. It is conceded that said materials were all furnished under a contract between said respondent and said contractor, and that the same were specially designed and made for said building, and are necessary to the completion of the building; that they have *125 been delivered and are now upon the premises at the building. It further appears that the only reason why the same have not been used is in consequence of the contractor having suspended work. Under such circumstances we think the right to a lien for all of said materials exists.

A further point is made by the appellant to the effect that there can be no lien for the reason that the contract between the hotel company and Potvin released the hotel company from liability for liens; and that the sub-contractors were bound to take notice of this provision in the original contract. Whether or not such claim be well founded as a matter of law, we find no such provision in the contract in question. On the contrary, it contemplates that there may be liens upon said building, and provides, in case of an indebtedness created by said contractor at any time exceeding §20,000 for labor on, or materials used in or about, said building, which would be or might become a lien thereon, that the hotel company at its option may apply any balance due or to become due said contractor to the payment of said indebtedness.

The further point is made that said respondent, being a foreign corporation, has no right to a lien because of not having complied with the laws of this state relating to foreign corporations doing business within the state. It appears that copies of the articles of incorporation were filed and the appointment of an agent made before the suit was commenced, but after the filing of the lien notice. We think this was a sufficient compliance with the law in this respect.

It is contended that the materials had not all been furnished when the claim of lien was filed, and that a party can have no lien for materials which have not been furnished at or prior to the filing of the lien notice. It appears that two lien notices were filed, one on March 7, 1891, which was ruled out by the court at the trial on the ground that *126 it was prematurely filed; but a subsequent notice filed May 13,1891, after the delivery of all the materials, was admitted. The last portion of the materials had been shipped and were on their way here when the first notice was filed, but had not yet arrived. If in consequence of this the first notice was prematurely filed, it would not deprive the respondent of the right to file another notice after all the materials had been delivered. '

It is contended that an attorney for a foreign corporation cannot verify a mechanic’s lien notice for such corporation unles's he is specially authorized by appointment, which must be filed in the secretary of state’s office. Sec. 1667, Gen. Stat., provides, that such a claim may be veri-, fied by the claimant or some other person.' We see no reason why a claim could not be verified by an attorney of-the corporation, as was done in this instance.'

It is contended that there can be no lien in this case because the materials were not furnished from the commencement on the credit of the building and premises, but were furnished solely on the credit of the contractor. This claim is not well fouñded. After an examination of the proofs we do not find anything to indicate an intention upon the part of the respondent to waive the right to a lien, or to furnish said materials solely upon the credit of the contractor, or that the same were so furnished. We think the contrary fairly appears.

It is contended that a portion of these materials were furnished after the contractor had abandoned said contract, and that there can be no lien for such materials for that reason. It does not appear that the contractor permanently severed his relations as contractor with the hotel company until about March, 1891. Some work was done along at various times up till about that time, and the contractor had charge of the building. The most that can be claimed is that there was a partial cessation of the work at *127 that time on account of differences between the hotel company and said contractor, but said suspension was not complete, and it was not known that it would be permanent until about March, 1891; and it appears that the materials in question were all shipped before said time, and in pursuance of a contract made by the respondent with said contractor prior thereto and when he was prosecuting the work, and this point is untenable.

The court allowed an attorney's fee of §2,000, aiid the appellant alleges that this is excessive. There was proof to show that such services were worth from §1,500 to §2,-500, none of the witnesses placing the value thereof below §1,500. However, we are satisfied that the sum allowed was much too large. It is not the policy of the law to allow large or exorbitant attorneys’ fees.

As to the appeal of the Huttig Brothers Manufacturing Company against the Cornell University, it appears that the contract between the hotel company and Potvin was entered into July 22, 1889, and the construction of the building was commenced thereunder in August following. The Huttig Brothers Manufacturing Company, a foreign corporation, contracted with Potvin to furnish certain materials for said building, and commenced the preparation of said materials at its place of business in the State of Iowa, in January, 1890, and commenced to deliver the same in September, 1890.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Geo Exchange Systems, LLC v. Cam
65 P.3d 11 (Court of Appeals of Washington, 2003)
Beall Pipe & Tank Corp. v. Tumac Intermountain, Inc.
700 P.2d 109 (Idaho Court of Appeals, 1985)
Warming v. Hargis
294 P. 248 (Washington Supreme Court, 1930)
Kellison v. Godfrey
281 P. 733 (Washington Supreme Court, 1929)
Ludlow Valve Manufacturing Co. v. Fidelity & Casualty Co.
217 P. 282 (Supreme Court of Kansas, 1923)
Western Hardware & Metal Co. v. Maryland Casualty Co.
177 P. 703 (Washington Supreme Court, 1919)
Atlantic Terra Cotta Co. v. Moore Construction Co.
80 S.E. 924 (West Virginia Supreme Court, 1914)
Lindley v. McGlauflin
109 P. 118 (Washington Supreme Court, 1910)
A. E. Sutton & Co. v. Coast Trading Co.
96 P. 428 (Washington Supreme Court, 1908)
National Fertilizer Co. v. Fall River Five Cents Savings Bank
82 N.E. 671 (Massachusetts Supreme Judicial Court, 1907)
Littell v. Saulsberry
82 P. 909 (Washington Supreme Court, 1905)
Pacific States Savings, Loan & Building Co. v. Dubois
83 P. 513 (Idaho Supreme Court, 1905)
Potvin v. Denny Hotel Co.
79 P. 940 (Washington Supreme Court, 1905)
Keene Guaranty Savings Bank v. Lawrence
73 P. 680 (Washington Supreme Court, 1903)
Chicago Mill & Lumber Co. v. Sims
74 S.W. 128 (Missouri Court of Appeals, 1903)
Home Savings & Loan Ass'n v. Burton
56 P. 940 (Washington Supreme Court, 1899)
La France Fire Engine Co. v. Town of Mt. Vernon
37 P. 287 (Washington Supreme Court, 1894)

Cite This Page — Counsel Stack

Bluebook (online)
32 P. 1073, 6 Wash. 122, 1893 Wash. LEXIS 240, Counsel Stack Legal Research, https://law.counselstack.com/opinion/huttig-bros-manufacturing-co-v-denny-hotel-co-wash-1893.