Pacific States Savings, Loan & Building Co. v. Dubois

83 P. 513, 11 Idaho 319, 1905 Ida. LEXIS 78
Idaho Supreme Court·Decided August 14, 1905·Published·Cited by 11 cases

Opinions

SULLIYAN, J.

— This action was commenced by A. J. Turley and others to foreclose certain mechanics’ and laborers’ liens against the property of the respondent Dubois. The appellant corporation, among a number of others, was made a party defendant. During the progress of the case the court made an order changing the parties in said action, [323]*323so that thereafter all further proceedings in said action were entitled “Pacific States Savings, Loan & Building Company, Appellant, v. Jesse K. Dubois,” and certain other parties, as defendants. The appellant company was the owner and holder of two mortgages upon the property involved in this ease — one for the sum of $20,000, which was filed for record in the proper recorder’s office on the twenty-third day of January, 1904; and the other for $10,000, which was filed for record in the proper recorder’s office on the eighteenth day of June, 1904, which mortgages were executed by said Dubois and his wife to the said appellant corporation to secure the payment of said sums. The court, after hearing the evidence, held as a matter of law that the liens of all laborers, materialmen or contractors relate hack to the time of the commencement of the building, irrespective of the question as to whether the work was done, the material furnished, or the contract entered into prior or subsequent to the time that the mortgages of the appellant corporation were filed for record. From the judgment of the court declaring that said liens were prior to the mortgage liens of the appellant, this appeal was taken.

In this ease the contract to erect said building was not let to anyone, but the owner employed men to furnish and do the rockwork, employed others to furnish the brick, others to furnish other material, others to furnish and do the plumbing, etc., and others to do the carpenter work, etc. Several errors are assigned, some of which go to the sufficiency of certain of the liens filed, but the main question is whether or not the claim of liens of persons performing labor upon or furnishing materials for the construction of the building on the premises referred to in the complaint relates in each ease back to the time of the commencement of said building, or whether the lien attaches in favor of such parties from the date on which the labor was commenced to be performed, or the material was commenced to be furnished. It is conceded that if all of said liens relate back to the time of the commencement of the building, irrespective of the time when the labor was commenced to be performed or the [324]*324material was commenced to be furnished, then the judgment should be affirmed as to that question, and if not, said judgment should be reversed. That question involves a construction of the statutes of this state relating to mechanics’ liens, and particularly involves the construction of section 5 of the mechanic’s lien law, found at page 148 of the Session Laws of 1899, which section is as follows: “The liens provided for in this chapter are preferred to any lien, mortgage, or other encumbrance, which may have attached subsequent to the time when the building, improvement or structure was commenced, work done, or materials were commenced to be furnished; also to any lien, mortgage or other encumbrance of which the lienholder had no notice, and was unrecorded at the time the building, improvement or structure was commenced, work done, or materials were commenced to be furnished.”

Counsel for respondents contend that under the provisions of said act the lien of laborers and materialmen in all cases, regardless of when they performed the labor or furnished the material, attached from the time of the commencement of the erection of the building, regardless of whether the structure was erected under an original contractor or by the owner of the premises; and it is conceded by counsel for appellant that if all of said liens relate back to the time of the commencement of the building, irrespective of the time when the labor was commenced to be performed or the material began to be furnished, the judgment should be affirmed on that question. It is conceded that the work done by some of the lien claimants, and the material furnished by some of the materialmen, was commenced to be done and furnished subsequent to the recording of the mortgages above referred to; and it is contended by appellant that under the provisions of said section 5 above quoted all such liens are subsequent to the mortgages. We will proceed and analyze the first half of section 5, and divide it into sentences, which sentences we think will clearly show the intent of the legislature in enacting it: 1. “The liens provided for in this chapter are preferred to any liens, mortgages or other encum[325]*325brances which may have attached subsequent to the time when the building, improvement or structure was commenced.” This would include all liens that are entitled to date from the commencement of the construction of a building, improvement, or structure of any kind. All of said liens are referred to any mortgage given subsequent to the commencement of such building, etc. 2. “The liens provided for in this chapter are preferred to any lien, mortgage or other encumbrance which may have attached subsequent to the time when the work was commenced to be done. ’ ’ That provision prefers all liens for work or labor, which work or labor was begun prior to the filing of a mortgage, but begun after the commencement of the erection of the building, etc., by a person or persons not theretofore connected with the construction of the building, and entitled to a separate and distinct lien from thoso who commenced the building. 3. “The liens provided for in this chapter are preferred to any lien, mortgage or other encumbrance which may have attached subsequent to the time when the materials were commenced to be furnished.” That provision prefers all liens for material, which material was commenced to be furnished prior to the recording of a mortgage, and which was commenced to be furnished some time after the commencement of the building, etc. Separating said section into distinct sentences as above, it seems clear to me that, when mortgages and other liens are involved in the foreclosure of mechanics’ and materialmen’s liens, the time or date when the building was commenced, or the laborer begun to work, or the materialman commenced to furnish the material, must be taken into consideration in determining the priority of such liens over such mortgage lien. All liens for labor commenced and materials commenced to be furnished prior to recording said mortgages are prior and r.uperior liens to said mortgages, and the liens of all laborers for labor commenced, and materialmen for material commenced to be furnished, subsequent to the recording of said mortgages, are subordinate to said mortgages, when such work is done and material furnished by persons not theretofore’connected with the construction of the build[326]*326ing. If that were not intended, why did not the legislature simply say that all liens for labor and material furnished in the erection or construction or repair or change of a building took effect from the commencement of the construction of such building or of such repair or change?. It is clear to me that the legislature intended to make all liens for work commenced and material commenced to be furnished after the recording of a mortgage subsequent and inferior thereto, especially when such work is done and materials furnished by persons who had no connection with the erection of the building until after the recording of the mortgages.

Free access — add to your briefcase to read the full text and ask questions with AI

Pacific States Savings, Loan & Building Co. v. Dubois, 83 P. 513, 11 Idaho 319, 1905 Ida. LEXIS 78 (Idaho 1905).

83 P. 513 (Pacific States Savings, Loan & Building Co. v. Dubois) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

ACI Northwest, Inc. v. Monument Heights, LLC
342 P.3d 618 (Idaho Supreme Court, 2015)
Ultrawall, Inc. v. Washington Mutual Bank
25 P.3d 855 (Idaho Supreme Court, 2001)
Bouten Construction Co. v. H.F. Magnuson Co.
992 P.2d 751 (Idaho Supreme Court, 1999)
Beall Pipe & Tank Corp. v. Tumac Intermountain, Inc.
700 P.2d 109 (Idaho Court of Appeals, 1985)
Aladdin Heating Corp. v. Trustees of Central States
563 P.2d 82 (Nevada Supreme Court, 1977)
White v. Constitution Mining & Milling Co.
55 P.2d 152 (Idaho Supreme Court, 1936)
International Mortgage Bank v. Whitaker
255 P. 903 (Idaho Supreme Court, 1927)
Mine & Smelter Supply Co. v. Idaho Consolidated Mines Co.
118 P. 301 (Idaho Supreme Court, 1911)