Haxtun Steam Heater Co. v. Gordon

50 N.W. 708, 2 N.D. 246, 1891 N.D. LEXIS 48
North Dakota Supreme Court·Decided November 18, 1891·Published·Cited by 10 cases

Opinion

The opinion of the court was delivered by

Bartholomew, J.

This is a contest for priority between plaintiff, the Haxtun Steam Heater Company, a mechanic’s lien holder, and the defendant, the Dakota Investment Company, a mortgagee. There was a decree below for the plaintiff, and the investment company appeals. Section 5478 of our Compiled Laws reads as follows: “ The liens for labor done or things furnished shall have priority in the order of the filing of the accounts thereof, as aforesaid, and shall be preferred to all other liens and incumbrances which may be attached to or upon said building, erection, or other improvement, and to the land on which the same is situated, or either of them, made subsequent to the commencement of said build[249] ing, erection, or other improvement.” The unquestioned facts are these: One Gordon was the owner of certain lots in the city of Grand Forks, upon which he desired to erect an hotel building. On Angust 12,1889, he commenced the erection of said building. August 17, 1889, Gordon executed to the appellant a mortgage upon said lots for the sum of $10,550. That said mortgage was properly recorded on August 19, 1889. That in October, 1889, Gordon entered into a contract with the respondent, by which respondent agreed to place a steam heating apparatus in said building, which was furnished and put in place in November and December of that year, and before the completion of the building; and within the required time respondent furnished and filed the necessary documents to perpetuate its lien for the unpaid amount due for such heating apparatus. The appellant introduced certain evidence, which, on motion of respondent, was subsequently stricken out by the court as immaterial. This action of the court is assigned as error. The rejected evidence showed that before the building was commenced Gordon procured an architect to make plans and specifications therefor; that there was no general contractor for the erection of the building, but that Gordon contracted with various parties for different lines of material and work as the same were needed; that said plans and specifications were always used as the basis upon which such contracts were made; that said plans and specifications contemplated heating said building with stoves, and not by steam, but included a smoke stack for future use, as it would be cheaper to put it in then than afterwards; that said plans and specifications, and the submission of bids by different contractors thereunder, formed the basis upon which appellant made the loan to Gordon; that after such loan was perfected, and the mortgage executed and recorded, the plans for said building were so far changed as to substitute a steam heating apparatus for stoves; that said change was made at the solicitation of respondent’s agent, and when made, and when the contract for the steam heating apparatus was entered into, respondent had both actual and constructive notice of the mortgage to the appellant. This statement uncovers the contention of the parties. Respondent [250] claims that under the statute its lien has priority over any mortgage on the lots made subsequent to the commencement of the building, although prior to the time when respondent made its contract with Gordon and. furnished any part of its labor and materials. The appellant, .on the other hand, insists that, as it parted with its money and took its security on the basis of the plans and specifications as they then existed, it is by law entitled to priority over any lien for labor-or materials subsequently furnished for purposes not then contemplated in the plans and specifications of the building then being erected; that as to the steam heating apparatus furnished by respondent it was so far a change of and enlargement upon the originul building that as to it, and the inception of a lien therefor, the building was not commenced, in the sense of the statute, until the contract for such apparatus was entered into. All of the errors assigned are but different methods of bringing forward this one claim, and the case presents but the single question.

Free access — add to your briefcase to read the full text and ask questions with AI

Haxtun Steam Heater Co. v. Gordon, 50 N.W. 708, 2 N.D. 246, 1891 N.D. LEXIS 48 (N.D. 1891).

50 N.W. 708 (Haxtun Steam Heater Co. v. Gordon) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Frank J. Klein & Sons, Inc. v. Laudeman
311 A.2d 780 (Court of Appeals of Maryland, 1973)
State Ex Rel. Alden Corp. v. Village of Solon
7 N.E.2d 550 (Ohio Supreme Court, 1937)
Winkworth Fuel & Supply Co. v. Bloomsbury Corp.
253 N.W. 304 (Michigan Supreme Court, 1934)
Schroeter Bros. Hardware Co. v. Croatian "Sokol" Gymnastic Ass'n
58 S.W.2d 995 (Supreme Court of Missouri, 1933)
McConnell v. Frost
45 S.W.2d 777 (Court of Appeals of Texas, 1931)
State Loan Co. v. White Earth Coal Mining Brick & Tile Co.
157 N.W. 834 (North Dakota Supreme Court, 1916)
Pacific States Savings, Loan & Building Co. v. Dubois
83 P. 513 (Idaho Supreme Court, 1905)
Bastien v. Barras
84 N.W. 559 (North Dakota Supreme Court, 1900)
Turner v. St. John
77 N.W. 340 (North Dakota Supreme Court, 1898)
James River Lumber Co. v. Danner
57 N.W. 343 (North Dakota Supreme Court, 1893)