Trane Co. v. Brown-Johnston, Inc.

739 P.2d 737, 48 Wash. App. 511
CourtCourt of Appeals of Washington
DecidedAugust 28, 1987
Docket7789-6-III
StatusPublished
Cited by13 cases

This text of 739 P.2d 737 (Trane Co. v. Brown-Johnston, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trane Co. v. Brown-Johnston, Inc., 739 P.2d 737, 48 Wash. App. 511 (Wash. Ct. App. 1987).

Opinion

Green, J.

Summary judgment was entered in favor of The Trane Company and Grinnell Fire Protection Services foreclosing their construction liens against ISC Systems Corporation and Baugh Industrial Contractors, Inc. ISC and Baugh appeal.

The dispositive issue is whether an issue of material fact exists as to Trane's and Grinnell's knowledge there was more than one contract between ISC, the property owner, and Baugh, the general contractor, so as to require them to file two claims of lien.

During 1981-82 ISC began to develop a plan for a manufacturing and warehousing complex at its Liberty Lake property. The complex was to be built in phases. On September 7, 1982, ISC entered into a written contract with Baugh, a general contractor, for the phase one construction of the manufacturing building. Baugh subcontracted the mechanical work to Brown-Johnston. Brown-Johnston in turn subcontracted the heating and air conditioning system (HVAC) to Trane and the fire protection work to Grinnell. *513 Phase one construction began in May 1983 and was substantially completed in February 1984.

On June 30, 1983, Baugh and ISC entered into a written contract for construction of the phase two warehouse building. Baugh advised ISC it would be more economical if the major subcontractors for phase one were used to perform the phase two work, which they did. Baugh paid Brown-Johnston for work completed, but Brown-Johnston went bankrupt and failed to pay Grinnell and Trane.

On August 16, 1983, Trane sent ISC a notice of intent to lien for materials supplied to that date. On March 27, 1984, Trane sent a notice of intent to lien for materials not included in the prior notices. Subsequently, Trane filed a lien. Grinnell also sent a notice of intent to lien and later filed it. Both parties, Grinnell and Trane, brought this action to foreclose their liens and both moved for summary judgment. The motions were granted and they were awarded their attorney fees and costs. ISC and Baugh appeal.

Summary judgment is appropriate if the pleadings, depositions and admissions on file, together with the affidavits, show there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law. CR 56(c); Del Guzzi Constr. Co. v. Global Northwest Ltd., 105 Wn.2d 878, 882, 719 P.2d 120 (1986). On review of a summary judgment, the appellate court places itself in the position of the trial court and assumes facts most favorable to the nonmoving party. Del Guzzi, at 882. The burden is on the moving party to prove no genuine issue of fact exists which could influence the outcome at trial. Hartley v. State, 103 Wn.2d 768, 774, 698 P.2d 77 (1985). While generally a question of fact is properly left to the trier of fact, when reasonable minds could reach but one conclusion, questions of fact may be determined as a matter of law. Hartley, at 775. The nonmoving party is given the benefit of any factual doubt when a summary judgment is made. Hartley, at 777. Of course, after the moving party has established a prima facie case, the non- *514 moving party must set forth specific facts which sufficiently rebut the moving party’s contention and disclose a genuine issue as to a material fact; the nonmoving party cannot merely claim contrary facts nor rely on speculation, argumentative assertions that unreasonable factual issues remain " or on affidavits considered at face value." Meyer v. UW, 105 Wn.2d 847, 852, 719 P.2d 98 (1986). With these principles in mind, we turn to the statutes governing the liens at issue in this case.

RCW 60.04.020 provides in pertinent part:

Every person, firm or corporation furnishing materials or supplies . . . to be used in the construction ... of any . . . building . . . shall give to the owner or reputed owner of the property ... a notice in writing, which notice shall cover the material, supplies or equipment furnished . . . during the sixty days preceding the giving of such notice as well as all subsequent materials, supplies or equipment furnished . . . No materialmen's lien shall be enforced unless the provisions of this section have been complied with . . .

RCW 60.04.060 provides:

No lien created by this chapter shall exist, and no action to enforce the same shall be maintained, unless within ninety days from the date ... of the cessation of the performance of such labor, the furnishing of such materials, or the supplying of such equipment, a claim for such lien shall be filed for record as hereinafter provided, . . .

Since labor and materialmen's liens are creatures of statute and are in derogation of common law, they must be strictly construed. Dean v. McFarland, 81 Wn.2d 215, 219-20, 500 P.2d 1244, 74 A.L.R.3d 378 (1972); Wells v. Scott, 75 Wn.2d 922, 925, 454 P.2d 378 (1969). Generally, after a contract is completed, the time for filing a claim of lien cannot be extended or the right revived by furnishing material or performing labor upon a new contract and tacking the same to the original contract. Boise Cascade Corp. v. Pence, 64 Wn.2d 798, 801, 394 P.2d 359 (1964); Anderson v. Taylor, 55 Wn.2d 215, 217, 347 P.2d 536, 78 *515 A.L.R.2d 1161 (1959) (quoting Swensson v. Carlton, 17 Wn.2d 396, 405, 135 P.2d 450 (1943)). However, where the lien claimant is not a party to either contract because either he furnished material or labor to a contractor who has two or more contracts with an owner, or to a subcontractor who has two or more subcontracts in connection with the same project, the general rule is not applicable, unless the lien claimant was aware of the fact there were two or more contracts. Anderson, at 217; Standard Lumber Co. v. Fields, 29 Wn.2d 327, 338, 187 P.2d 283, 175 A.L.R. 309 (1947). The burden is then on the owner who is claiming there were two or more contracts to prove the lien claimant had actual or constructive notice of the two or more contracts. Anderson, at 217; Standard Lumber, at 338-39.

Standard Lumber is on point with the instant case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Clarity Capital Management Corporation, V. Aretha Ryan
Court of Appeals of Washington, 2021
Wa State Dept Of Ret (drs), V Kevin Dolan
Court of Appeals of Washington, 2014
Weaver v. Spokane County
275 P.3d 1184 (Court of Appeals of Washington, 2012)
Mearns v. Scharbach
103 Wash. App. 498 (Court of Appeals of Washington, 2000)
McMann v. Benton County
946 P.2d 1183 (Court of Appeals of Washington, 1997)
Michelsen v. Boeing Company
826 P.2d 214 (Court of Appeals of Washington, 1991)
Schoneman v. Wilson
785 P.2d 845 (Court of Appeals of Washington, 1990)
Ruffer v. St. Frances Cabrini Hospital
784 P.2d 1288 (Court of Appeals of Washington, 1990)
Hemenway v. Miller
776 P.2d 710 (Court of Appeals of Washington, 1989)
Rubbelke v. Strecker
765 P.2d 314 (Court of Appeals of Washington, 1988)
ITT Rayonier, Inc. v. Bell
752 P.2d 398 (Court of Appeals of Washington, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
739 P.2d 737, 48 Wash. App. 511, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trane-co-v-brown-johnston-inc-washctapp-1987.