Del Guzzi Constr. Co. v. Global Northwest Ltd., Inc.

719 P.2d 120, 105 Wash. 2d 878, 1986 Wash. LEXIS 1142
CourtWashington Supreme Court
DecidedMay 22, 1986
Docket52161-1
StatusPublished
Cited by123 cases

This text of 719 P.2d 120 (Del Guzzi Constr. Co. v. Global Northwest Ltd., Inc.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Del Guzzi Constr. Co. v. Global Northwest Ltd., Inc., 719 P.2d 120, 105 Wash. 2d 878, 1986 Wash. LEXIS 1142 (Wash. 1986).

Opinion

Pearson, J.

In this case, Global Northwest, Ltd., Inc., a minority subcontractor, challenges a summary judgment entered against it in Clallam County Superior Court. Global brought suit against Clallam County and Kennedy Engineers, Inc., alleging breach of contract and negligence for cost overruns incurred by Global as a result of its failure to meet soil compaction density specifications during construction of the Sekiu-Clallam Bay sewerage project. The *880 Superior Court concluded that the statute of limitation barred Global's negligence claim and dismissed the contractual claim because Global was not a third party beneficiary. We now affirm the judgment entered against Global.

Facts

In April 1973, the County retained Kennedy to design, plan, and supervise construction of the Sekiu-Clallam Bay sewerage system for Clallam County Utility Improvement District 73-1. In late 1974, the County contracted with Del Guzzi Construction Co., Inc., for construction of the project. Seventy-five percent of the funding for construction was obtained from the Environmental Protection Agency (EPA), 15 percent from the Washington Department of Ecology, and the balance was borne by the County.

In the original bidding, Del Guzzi was the low bidder; but due to an error, Del Guzzi subsequently informed the County that an additional $400,000 would be needed for removing trench excavation material and backfilling the trenches with material that would meet compaction density requirements. The County then rejected all bids and rebid the project to include the extra costs for soil removal and compaction. Del Guzzi again was the low bidder.

To obtain federal funding, minority participation was required. Subsequently, in February 1975, Del Guzzi subcontracted with Global. Global began work in March and by September became aware that its compaction effort was unsatisfactory. Global also discovered that Del Guzzi had identical compaction problems prior to the signing of Global's subcontract, and that Del Guzzi knew the native trench material would not compact to the required specifications.

In early 1976, Global began to compile its extra costs for the removal, replacement and recompaction efforts. In the fall of 1976, Global submitted a change order request to the County and Kennedy, pursuant to the contract provisions set forth in the prime contract between the County and Del Guzzi. The subcontract between Global and Del Guzzi pro *881 vided, inter alia, that Global would be bound by all the terms of the prime contract.

The project was completed by December 1976, and in August 1977 the County and Del Guzzi approved Global's change order request, conditioned on the approval of additional funding by the EPA. All of the parties protected themselves by hold harmless agreements, providing that the submission of the change order request was not an acknowledgement of liability or a waiver of any defenses.

In May 1978, the EPA tentatively informed Global it would deny its request. Nevertheless, Global submitted further information to the EPA, and attempted other contact with EPA officials in Washington, D.C. Neither of these efforts proved fruitful.

In November 1978, Del Guzzi filed a complaint for damages against Global in the sum of $77,147.20 for expenses incurred in completing a portion of Global's contract. In April 1979, the EPA formally rejected Global's request and recommended that other means of recovery be instituted.

In April 1980, Global answered Del Guzzi's complaint by admitting that Del Guzzi had incurred certain expenses in assisting Global in completion of the contracts in question, but denied that Del Guzzi was damaged in the amount of $77,147.20. Further, Global counterclaimed for cost overruns in the amount of $334,799.82, plus 10 percent for profit. Global also commenced a third party action for negligence and breach of contract against the County and Kennedy. Global contended the County knew of Global's lack of experience, and therefore the County owed it a higher degree of duty. Furthermore, Global argued that Kennedy, as the County's agent, drafted specifications that permitted use of native fill material and thereby warranted that such material would be acceptable.

In May 1982, the County and Kennedy moved for summary judgment against Global. On May 26, 1982, Global filed a motion for leave to amend its answer, counterclaim and third party complaint against the County, Kennedy and Del Guzzi.

*882 Following the June 4 summary judgment hearing, the court issued a memorandum opinion dismissing Global's claims. The court dismissed Global's tort claim on the ground Global had failed to toll the applicable statute of limitation. The court dismissed Global's contract claim because Global was not a third party beneficiary of either the contract between Kennedy and the County or the contract between the County and Del Guzzi. 1 The court also denied Global's motion to amend its pleadings. Global filed a notice of appeal with the Court of Appeals. The case was transferred to this court pursuant to RAP 4.3.

I

Summary judgment is appropriate "if the pleadings, depositions . . . and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law." CR 56(c). Hartley v. State, 103 Wn.2d 768, 774, 698 P.2d 77 (1985).

On review of summary judgment, we place ourselves in the position of the trial court, assuming facts most favorable to the nonmoving party, in this case Global. Hartley, at 774. Additionally, the burden is on the moving party to prove there is no genuine issue as to a fact which could influence the outcome at trial. Hartley, at 774. Because the facts of this case are basically undisputed, the question we must determine is whether the County and Kennedy were entitled to judgment as a matter of law.

II

The first issue for the court is whether Global's negligence action against the County and Kennedy is barred by the builder limitation statute, RCW 4.16.310. Initially, we must determine if Global's claim falls within the parameters of RCW 4.16.300, which provides:

*883 RCW 4.16.300

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morgan Aiken Iii, V. Rocio Sanchez & Marta Becerra
Court of Appeals of Washington, 2024
Park South LLC v. Denali Construction LLC
Court of Appeals of Washington, 2024
Al-Bustani v. Alger
W.D. Washington, 2023
Us Bank National Association v. Denise M. Stanton
Court of Appeals of Washington, 2019
Sharon Shepard v. David Holmes
Court of Appeals of Washington, 2014
Keithly v. Sanders
285 P.3d 225 (Court of Appeals of Washington, 2012)
Sligar v. Odell
233 P.3d 914 (Court of Appeals of Washington, 2010)
Kim v. Moffett
156 Wash. App. 689 (Court of Appeals of Washington, 2010)
Nakata v. Blue Bird, Inc.
191 P.3d 900 (Court of Appeals of Washington, 2008)
Kwiatkowski v. Drews
176 P.3d 510 (Court of Appeals of Washington, 2008)
Ives v. Ramsden
142 Wash. App. 369 (Court of Appeals of Washington, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
719 P.2d 120, 105 Wash. 2d 878, 1986 Wash. LEXIS 1142, Counsel Stack Legal Research, https://law.counselstack.com/opinion/del-guzzi-constr-co-v-global-northwest-ltd-inc-wash-1986.