Gregory Tadych Et Ano., V. Noble Ridge Construction, Inc.

CourtCourt of Appeals of Washington
DecidedJuly 19, 2021
Docket81948-8
StatusUnpublished

This text of Gregory Tadych Et Ano., V. Noble Ridge Construction, Inc. (Gregory Tadych Et Ano., V. Noble Ridge Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gregory Tadych Et Ano., V. Noble Ridge Construction, Inc., (Wash. Ct. App. 2021).

Opinion

IN THE COURT OF APPEALS FOR THE STATE OF WASHINGTON

GREGORY M. TADYCH and No. 81948-8-I R. SUE TADYCH, a married couple, DIVISION ONE Appellants, UNPUBLISHED OPINION v.

NOBLE RIDGE CONSTRUCTION, INC., a Washington Corporation; and WESCO INSURANCE CO., a foreign surety, Bond No.46WB025486,

Respondents.

ANDRUS, A.C.J. — Gregory and R. Sue Tadych challenge the summary

judgment dismissal of their complaint against Noble Ridge Construction Inc. (NRC)

for breach of their construction contract. The trial court dismissed the Tadychs’

complaint, concluding that a one-year claim limitations period had expired, making

their claim time barred. The Tadychs argue that the claim limitation clause is

unenforceable or, alternatively, that NRC should be estopped from asserting it.

We disagree and affirm the dismissal.

FACTS

In 2012, the Tadychs and NRC entered into a written agreement for the

construction of a custom home in south Seattle. The Tadychs received a draft of

Citations and pin cites are based on the Westlaw online version of the cited material. No. 81948-8-I/2

the contract on July 22, 2012, and reviewed it for a few weeks before they signed

it. They did not seek legal advice, and they signed the contract without requesting

any changes to its terms.

For a base price of $485,068, NRC, as the contractor, agreed to provide all

necessary labor and materials to construct the Tadychs’ residence “in accordance

with the Plans and Specifications and (if applicable) Changes Orders accepted and

agreed to by the parties hereto.” The plans and specifications were incorporated

by reference into the agreement. The Tadychs and NRC agreed that neither party

would deviate from the plans and specifications without a mutual written

agreement to do so. NRC further agreed it would “supervise and direct the Project

using reasonable skill and attention and shall satisfy the building codes and

standards of municipalities or other governmental agencies with jurisdiction over

the Project.”

The contract provided that the project would be deemed completed when

the building official with jurisdiction over the project established that the home had

been built in accordance with the approved plans and specifications and permits,

and issued a certificate of occupancy. Upon substantial completion and before

occupancy, NRC and the Tadychs agreed they would meet at the project site for

a walk-through inspection and prepare a list, referred to as a “punchlist,” identifying

all components of the project that needed to be completed or corrected.

The contract’s warranty provision provided in pertinent part:

Warranty. . . . Any claim or cause of action arising under this Agreement, including under this warranty, must be filed in a court of competent jurisdiction within one year (or any longer period stated in any written warranty provided by the Contractor) from the date of

-2- No. 81948-8-I/3

Owner's first occupancy of the Project or the date of completion as defined above, whichever comes first. Any claim or cause of action not so filed within this period is conclusively considered waived. . . .

In December 2013, as the project neared completion, the Tadychs worked

with NRC to develop a punchlist of incomplete items. One issue they listed was

that “rainwater pools at the landing at the bottom of the stairs.” Greg Tadych

testified that he personally expressed concern to NRC about this issue throughout

the course of the construction. To address pooling rainwater, NRC sketched a

proposed modification to the landing proposing to slope it away from the door

threshold toward a drain scupper. Greg Tadych testified NRC implemented this

fix. The parties’ revised punchlist, dated April 2, 2014, reflects that NRC poured a

sloped cement surface on the landing and installed tile to direct rain water toward

the gutter. The punchlist identified this line item as “closed.”

Another item on the December 2013 punchlist was “[n]umerous nicks and

cracks on the stucco exterior walls.” The revised April 2014 punchlist indicated

that “[s]ome work has been done on stucco” and the item remained “open.” There

is no indication in the record that NRC performed any further work on the exterior

stucco to address the identified cracks.

The Tadychs moved into the home on April 8, 2014. The City of Seattle

Department of Planning and Development conducted its final site inspection on

April 15, 2014, and approved the residence for occupancy on April 23, 2014.

Sue Tadych testified that in late January or early February 2015 she felt a

“shift” in the home “as though there had been some unexpected movement in the

Project’s structure.” She reported that “in February 2015 she was working in the

-3- No. 81948-8-I/4

first floor office/bedroom at the NW corner when she heard ‘a loud rubbing noise’

and it ‘felt as though the house shifted south and then down.’” After this event, she

noticed that the door to the back patio was no longer even with the casing, there

were “humps in the flooring when walking into the master closet and the powder

room on the second floor that were not present before the event,” the bathtub was

no longer level and tilted to the south, floor tiles under and adjacent to the toilet

came loose, doors to the roof deck no longer shut properly, and cracks in the

drywall appeared.

In February 2015, concerned about this incident, the Tadychs engaged

Construction Dispute Resolution, Inc. (CDR) to review NRC’s work. According to

the consultant agreement the Tadychs signed, CDR provides “consulting and

expert witness services relative to construction litigation.” For the sum of $1,300,

CDR agreed to “[r]eview flooring issues and shift of structure. Advise Client as

requested.”

CDR raised concerns about the adequacy of the home’s construction in its

correspondence with the Tadychs. On March 2, 2015, CDR prepared a written

report indicating it had identified deviations from the architectural plans and the

potential risk of inadequate ventilation of the interstitial areas within the framing of

the home. CDR wrote

All enclosed roof and exposed deck areas together with parapet walls and railings need to be ventilated unless they are completely filled with foam insulation. This is due to the fact that water may condense within the spaces where a conditioned space is adjacent to an unconditioned space; for instance a roof or exterior wall.

....

-4- No. 81948-8-I/5

[I]n just looking at the photographs of your home and comparing them to the details on the plans we are concerned that there is insufficient ventilation in your walls and roof structures. We are unclear as to whether the architect had issued different designs/directions for the builder to achieve the ventilation required but the lack of 6 inch round holes around your building to ventilate the roof areas and the fact that the metal copings are tight to the walls at your roof parapets indicate the ventilation may not be in place. Together with that, at the roof deck, there is no parapet cap flashing at the metal clad railings. It is a mystery how these are vented.

In summary, either we assume that somehow the architect and builder have achieved the necessary code mandated ventilation as dictated by the plans or some investigative work will have to occur to verify

(Emphasis added). It also stated that the stairs and railings did not conform to the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walter Implement, Inc. v. Focht
730 P.2d 1340 (Washington Supreme Court, 1987)
City of Seattle v. Kuney
311 P.2d 420 (Washington Supreme Court, 1957)
Arrow Transportation Co. v. A. O. Smith Co.
454 P.2d 387 (Washington Supreme Court, 1969)
Rottinghaus v. Howell
666 P.2d 899 (Court of Appeals of Washington, 1983)
Ruff v. County of King
887 P.2d 886 (Washington Supreme Court, 1995)
Robinson v. City of Seattle
830 P.2d 318 (Washington Supreme Court, 1992)
Hartley v. State
698 P.2d 77 (Washington Supreme Court, 1985)
Del Guzzi Constr. Co. v. Global Northwest Ltd., Inc.
719 P.2d 120 (Washington Supreme Court, 1986)
Ruth v. Dight
453 P.2d 631 (Washington Supreme Court, 1969)
Nelson v. McGoldrick
896 P.2d 1258 (Washington Supreme Court, 1995)
Rouse v. Glascam Builders, Inc.
677 P.2d 125 (Washington Supreme Court, 1984)
YAKIMA ASPHALT v. Dept. of Transp.
726 P.2d 1021 (Court of Appeals of Washington, 1986)
Marsh v. General Adjustment Bureau, Inc.
592 P.2d 676 (Court of Appeals of Washington, 1979)
Silverhawk, LLC v. Keybank Nat. Ass'n
268 P.3d 958 (Court of Appeals of Washington, 2011)
Syrett v. Reisner McEwin & Associates
24 P.3d 1070 (Court of Appeals of Washington, 2001)
Peterson v. Groves
44 P.3d 894 (Court of Appeals of Washington, 2002)
1000 Virginia Ltd. Partnership v. Vertecs Corp.
146 P.3d 423 (Washington Supreme Court, 2006)
Sabey v. Howard Johnson Co.
5 P.3d 730 (Court of Appeals of Washington, 2000)
Dix v. ICT Group, Inc.
161 P.3d 1016 (Washington Supreme Court, 2007)
Absher Construction Co. v. Kent School District No. 415
890 P.2d 1071 (Court of Appeals of Washington, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Gregory Tadych Et Ano., V. Noble Ridge Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/gregory-tadych-et-ano-v-noble-ridge-construction-inc-washctapp-2021.