Wetzel & T. Ry. Co. v. Tennis Bros.

145 F. 458, 75 C.C.A. 266, 1906 U.S. App. LEXIS 3988
CourtCourt of Appeals for the Fourth Circuit
DecidedMay 1, 1906
DocketNo. 638
StatusPublished
Cited by26 cases

This text of 145 F. 458 (Wetzel & T. Ry. Co. v. Tennis Bros.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wetzel & T. Ry. Co. v. Tennis Bros., 145 F. 458, 75 C.C.A. 266, 1906 U.S. App. LEXIS 3988 (4th Cir. 1906).

Opinion

WADDIRR, District Judge.

On the 23d day of September, 1903, the Tennis Bros. Company filed its bill in equity in the United States Circuit Court for the Northern District of West Virginia, against the Wetzel & Tyler Railway Company, to enforce its mechanic’s lien for the amount of the agreed price of certain labor actually performed by the plaintiffs in behalf of the defendant in the construction of its railway pursuant to a contract theretofore entered into between them, and also for the recovery of damages for breach of contract in not permitting the plaintiff to wholly perform such contract. To this bill a demurrer was filed and overruled by the court; a'nd thereupon the defendant railway company duly answered, denying generally the allegations of the bill, and particularly that there had been a modification made in the contract after its execution, relating to the supervision and construction of certain car barns, powerhouse, and supplies furnished therefor; and also that said plaintiffs had failed to keep the contract on its part; the defendants contention being that C. C. Tennis had not personally supervised the construction of the road as was contemplated; that the work done was negligently performed; that the track as completed was imperfect and defective, caused by the failure of the plaintiff to personally supervise the same as aforesaid; to employ competent men for the work, and to furnish sufficient and suitable implements and • materials for the same. A general replication was duly filed to this answer, and issue joined thereon; and thereafter, on the 23d day of June, 1904, a cross-bill was filed by the railway company praying for affirmative relief against the plaintiff, the Tennis Bros. Company, and asking damages in the sum of $50,000, against it for its failure to properly perform the contract entered into by it in connection with the construction of said road, and on account of which the railway was forced into the hands of a receiver subsequent to the institution of this suit. To this cross-bill the Tennis Bros. Company demurred, which demurrer was overruled; and thereupon an answer was duly filed denying generally the averments of said bill. To such answer, a replication was made, and issue joined thereon, and, without reference to a master, a mass of evidence was taken by the parties respectively, and the cause submitted to the court for hearing on the riierits; and a final decree was duly entered on .the 23d day of August, 1905, from which both parties appealed.

The decision of the lower court was, in effect, that no recovery could be had upon the cross-bill, and the same was dismissed; that the plaintiff, the Tennis Bros. Company, were entitled to recover only for the amount of labor and work done under their contract of the 15th of April, 1903, up to the time of the cancellation thereof by the defendant, to wit, for the sum of $12,898.45, being principal and interest due as of the date of the decree; and that no recovery could be had [461]*461by it, either on account of its estimated profits, arising by reason o£ the failure of the defendant to allow it to perform the contract on its part, or because of the alleged work and labor done and supervision and construction of the car barns and power house, because of an alleged modified agreement; and said court further decreed that for the amount above specified, said Tennis Bros. Company was entitled to a lien upon the property of the defendant railway company, enforceable in this cause, and for which the defendant’s property should be sold. In the view we take, it will not be necessary for this court to enter into a discussion of all of the various assignments of error made upon the appeal and cross-appeal by the parties respectively, further than to say that the same have been fully considered, and except as herein specifically referred to, are believed to be without merit.

At the threshold, we deem it proper to say that we fully concur in the action of the lower court in its ruling upon the four questions specifically passed upon by it, namely, in the dismissal of the cross-bill ; the ascertainment thal the plaintiff was only entitled to recover, under the circumstances of this case, for the actual work and labor done and performed under its contract, as distinguished from what it claimed on account of estimated profits; that nothing should be allowed it on account of its rights arising from the so-called “modified contract” respecting the construction of the car barns and powerhouse of the defendant company; and that the amount decreed the plaintiff was properly ascertained by th'e lower court. Wc shall likewise not attempt to give reasons in detail for these conclusions; or review the voluminous evidence contained in the record, but will content ourselves in this regard upon these four questions, by a reference to the able and convincing opinion of the learned judge of the court below, as containing our views thereon.

Coming to the right of the plaintiff to recover at all by reason of the contract, and die mechanic's lien claimed pursuant thereto, it is earnestly insisted that the plaintiff corporation is not entitled to the benefit of the mechanics’ liens act of West Virginia; that it had no standing in court to maintain such a suit, if entitled to such relief, because of its failure properly to qualify itself as a corporation to do business under the laws of the state of West Virginia; that it had forfeited its right to a mechanic’s lien by reason of the agreement to accept bonds in lieu of money, in part payment of the amount to become due; that it did not have the first lien upon the property of the defendant company; and in no event, should the lower court in this proceeding have decreed in its favor, because of the pendency of a suit in the federal court sitting in the state of Pennsylvania, and in which the property of the defendant company was being administered. These questions we will consider in the order named:

First. It is earnestly insisted that the Tennis Bros. Company is not entitled to a mechanic’s lien, because it is a corporation; that only individuals are given such lien under the West Virginia statute; and that in no event can a lien be sustained for a claim arising under the contract of employment involved here, or for the character of service contemplated by the contract. The lien is claimed under sec[462]*462tion 7 of chapter 75 of the Code of West-Virginia of 1899, which provides that:

“Every workman, laborer, or other person, who shall do or perform any work or labor, by virtue of any contract, for any incorporated company doing business in this state, shall have a lien for the value of such work upon all the real estate and personal property of said company, and such lien shall have priority over any lien created by deed or otherwise on such real estate, or personal property, subsequent to the time when the said labor was performed, but there shall be no priority of lien as between the parties claiming under the provisions of this section; provided, that no lien shall be created under this section for labor performed more than nine months before such lien was recorded.”

The lien was duly claimed under the statute, and no contention is made on that account; but it is insisted that the same cannot be maintained for the reasons above stated. Can a corporation claim the benefit of this statute, and secure a lien thereunder ? This depends upon the interpretation to be given to the language “or other person” in the act, and whether corporations are embraced therein for a claim otherwise entitled to the benefits of the act. The Code of West Virginia, 1899, § 17, c. 13, subd. 9, says:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A Guy Named Moe, LLC v. Chipotle Mexican Grill of Colorado, LLC
135 A.3d 492 (Court of Appeals of Maryland, 2016)
Quarles v. Miller
Fourth Circuit, 1996
Jack Long Logging Co. v. Pyramid Mountain Lumber, Inc.
387 P.2d 712 (Montana Supreme Court, 1963)
Orange Theatre Corp. v. Rayherstz Amusement Corp.
139 F.2d 871 (Third Circuit, 1944)
Caird Engineering Works v. Seven-Up Gold Mining Co., Inc.
111 P.2d 1267 (Montana Supreme Court, 1940)
Bloch v. Bell Furniture Co.
157 A. 390 (New Jersey Court of Chancery, 1931)
Gallagher v. Campodonico
5 P.2d 486 (Appellate Division of the Superior Court of California, 1931)
Chesapeake & O. Ry. Co. v. Coffey
37 F.2d 320 (Fourth Circuit, 1930)
Gammon v. Howard W. Scott, Inc.
16 F.2d 902 (Fourth Circuit, 1927)
Franklin Sugar Refining Co. v. Egerton
288 F. 698 (Fourth Circuit, 1923)
McDonald-Weist Logging Co. v. Cobb
278 F. 167 (Ninth Circuit, 1921)
Kimball v. Sundstrom & Stratton Co.
92 S.E. 737 (West Virginia Supreme Court, 1917)
City of Charlotte v. Atlantic Bitulithic Co.
228 F. 456 (Fourth Circuit, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
145 F. 458, 75 C.C.A. 266, 1906 U.S. App. LEXIS 3988, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wetzel-t-ry-co-v-tennis-bros-ca4-1906.