Bannock Lumber & Coal Co. v. Tribune Co.

4 P.2d 662, 51 Idaho 226, 1931 Ida. LEXIS 122
CourtIdaho Supreme Court
DecidedOctober 27, 1931
DocketNo. 5709.
StatusPublished

This text of 4 P.2d 662 (Bannock Lumber & Coal Co. v. Tribune Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bannock Lumber & Coal Co. v. Tribune Co., 4 P.2d 662, 51 Idaho 226, 1931 Ida. LEXIS 122 (Idaho 1931).

Opinion

LEE, C. J.

—Plaintiff and respondent, Bannock Lumber & Coal Company, sought to foreclose a materialman’s lien against defendant and appellant, The Tribune Company, Ltd. Both parties are Idaho corporations. Respondent claimed a balance Of $1734.40 due for materials furnished from May 1, 1928, to August 21, 1928, under a contract between appellant and one, Elmer T. Peterson, dated April *228 27, 1928, for the repairing and remodeling of the former’s building; it ashed for interest and $200 attorney’s fees.

Appellant’s answer consisted of specific denials and five affirmative defenses charging in effect that respondent had agreed to furnish Peterson the materials for $1500, that some $600 of the amount actually demanded was an overcharge, a substantial part thereof being for materials furnished under a subsequent and independent contract of which respondent had full knowledge.' That prior to the filing of the claim of lien both Peterson and respondent had been fully paid, to the latter’s knowledge, and that the first contract having been completed before July 28, 1928, and the last material having been furnished thereunder on July 12, 1928, the time for filing a lien had expired, and that the claim thereof filed on October 18, 1928, was void and unenforceable.

As controlling facts, the court found that under the contract of April 27th,

“Elmer T. Peterson began the remodeling and finishing of the said building under the said contract, and the plaintiff, Bannock Lumber & Coal Company, at various times and dates between the 1st day of May, 1928, and the 21st day of August, 1928, at the special instance and request of the said Elmer T. Peterson, as contractor furnished to the said Elmer T. Peterson, and delivered the same to him on the premises above described, lumber and other materials which materials were used in and about the said building for the purpose of remodeling and finishing the said building under the terms of the said contract.”

It further found:

“That the said lumber and other materials so furnished by the said plaintiff to the said Elmer T. Peterson under said contract, was of the reasonable value of Two Thousand Forty-eight and 05/100 Dollars ($2,048.05) on which the said defendant Peterson has paid, at various dates and times, only the sum of Three hundred Seventy-one and 95/100 dollars ($371.95) leaving a balance due to the plaintiff of One Thousand Six hundred Seventy-six and 10/100 *229 Dollars, ($1,676.10), which said sum is now due and owing to plaintiff.”

Conclusions in conformity therewith followed; and judgment of foreclosure was entered for $1676.10, $234.64 interest and $200 attorney’s fees. The Tribune Company appealed. Chief among the errors urged is the count’s failure to make findings on certain issues raised by the affirmative defenses, to wit, that:

“Respondent herein at all times knew of the payment by the appellant to Peterson of the amount of the estimates and thereby waived its right to a lien.
“The work and materials performed or furnished in August, 1928, was a part of the original contract.
“Officials of respondent were acquainted with the terms of contract and issuance of architect’s certificates.
“Peterson furnished a material list to respondent and respondent agreed that the materials necessary would be furnished for $1500.
“Respondent knew the terms of the contract and by reason of secretary-treasurer of respondent acting as Peterson’s agent in operating the books, controlling bank; account, etc., it was estopped from asserting a lien.
“Payment of August items for materials by appellant to Peterson and Peterson’s turning the check over to respondent’s Secretary-treasurer for cashing, and that by so doing, payment was made of August items, for material and that if such payment were made, the lien would be void.”

As has been noted, the court found directly that the materials furnished in August were used in “remodeling and finishing the said building under the terms of the said contract,” referring to the contract of April 27th. The burden of proof was upon appellant to establish its affirmative defenses. Unless that burden had been discharged it was unnecessary for the court to make findings thereon. And, had the burden been discharged, findings, unless material, were not required. In this connection is the alleged knowledge of respondent that appellant had paid Peterson the full amount of the estimate and its ac *230 quaintance with the terms of the contract and issuance of architect’s certificates.

Granted that respondent did know these things, of what effect would such knowledge have been in the face of the contract itself and the disposition of the payments made thereunder? Respondent knew that the contract provided that “The Owner, without invalidating the contract, may make changes by altering, adding to or deducting from the work, the contract sum being adjusted accordingly. All such work shall be executed under the conditions of the original contract.” The contract specifically provided for a counter “according to details which will be furnished.” Notwithstanding this provision, Peterson, in attempting to show that the August items had been furnished under a subsequent contract, deposed as follows:

“Q. Now, Mr. Peterson, I notice on Exhibit 1, on the back of sheet 2 thereof, items for August 4th, 6th, 17th and 21st, marked ‘Mill’; were those items furnished to you by the plaintiff, Bannock Lumber & Coal Company, for the purpose of being used for remodeling that building? A. That was an after consideration. The blue-print said that all cabinet work and counters was to be furnished by the owner, and" that was not in my contract, but they decided, after the job was completed, to let me do that for them, also, and I told them how much it would be, and they told me to go ahead and make it, and then I went and ordered the material from the mill and it was milled out by the planing mill and was charged to the same job, and that is where those items come in.
“Q. Then, as I understand it, the items that were used, and received from the plaintiff under dates of August 4th, 6th, 17th and 21st, were ordered from them by you and used after the completion of your contract to remodel the building? A. Yes sir, and that was an extra consideration, and that belonged in the counters.”

We, then, have this situation. The architect’s certificate of completion issued on July 28th, a fact not shown to have been known to respondent; the owner, in pursuance of his *231 contract right, “adding to” the work already done by ordering the contractor “to panel and door the back of the counter”; the contractor going to respondent on August 4th, ordering materials and telling the manager to “charge them to the Tribune job.” What job? Peterson says it was the “same job,” the only Tribune job at the time on respondent’s books. Peterson says he had theretofore told respondent’s manager that the Tribune job had been completed : the manager denies it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mack v. . Colleran
32 N.E. 604 (New York Court of Appeals, 1892)
Valley Lumber & Manufacturing Co. v. Driessel
93 P. 765 (Idaho Supreme Court, 1907)
Valley Lumber & Manufacturing Co. v. Nickerson
93 P. 24 (Idaho Supreme Court, 1907)
Mack v. Colleran
136 N.Y. 617 (New York Court of Appeals, 1892)
Jefferson v. Church of St. Matthew
43 N.W. 74 (Supreme Court of Minnesota, 1889)

Cite This Page — Counsel Stack

Bluebook (online)
4 P.2d 662, 51 Idaho 226, 1931 Ida. LEXIS 122, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bannock-lumber-coal-co-v-tribune-co-idaho-1931.