Ahlgren v. Walsh

158 P. 748, 173 Cal. 27, 1916 Cal. LEXIS 354
CourtCalifornia Supreme Court
DecidedJuly 6, 1916
DocketS. F. No. 6935.
StatusPublished
Cited by13 cases

This text of 158 P. 748 (Ahlgren v. Walsh) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ahlgren v. Walsh, 158 P. 748, 173 Cal. 27, 1916 Cal. LEXIS 354 (Cal. 1916).

Opinion

SHAW, J.

The defendant, Julia A. Walsh, appeals from the judgment, and also from an order denying her motion for new trial.

The action was begun to recover an installment of a contract entered into between the plaintiff and the defendants, whereby the plaintiff agreed to construct certain portions of a nine flat frame building for the defendants upon a lot in San Francisco. The contract was executed on October 25, 1905. The contract price was $23,763, to be paid “at times and in the manner following, to-wit: First:—$1000 when concrete foundations are built. Second:—$2400, when the frame is up. Third:—$2200 when building is enclosed and roof completed. Fourth:—$4000 when brown coat of mortar is on. Fifth:—$2500 when the plastering and outside mill work is finished.” The remainder was payable in further installments until the completion. They are not important to our discussion. The installment sued for was the fifth which, by the part of the contract just quoted, was to be paid “when the plastering and outside mill work was finished.” To this clause, however, there was a proviso, as follows:

“Provided that when each payment or installment shall become due, and at the final completion of the work, certificates in writing shall be obtained from said architect, stating that the payment or installment is due or work completed, as the *30 case may be, and the amount then due; and the said architect shall at said times deliver said certificates under his hand to the contractor, or, in lieu of such certificate, shall deliver to the contractor, in writing, under his hand, a just and true reason for not issuing the certificates, including a statement of the defects, if any, to be remedied, to entitle the contractor to the certificate or certificates. And, in the event of the failure of the architect to furnish and deliver said certificates, or any of them, or in lieu thereof the writing aforesaid, within three days after the times aforesaid, and after demand therefor made in writing by the contractor, the amount which may be claimed to be due by the contractor and stated in the said demand made by him for the certificates, shall, at the expiration of said three days, become due and payable, and the owner shall be liable and bound to pay the same on demand. In case the architect delivers the writing aforesaid in lieu of the certificate, then a compliance by the contractor with the requirements of said writing shall entitle the contractor to the certificate.”

The contractor proceeded with the performance of the work and had earned and received four installments provided by the contract, amounting to nine, thousand six hundred dollars, and had also finished the plastering and outside mill work. This work was completed and the fifth installment earned on the 17th of April, 1906, at noon. Early the next morning the earthquake of 1906 occurred whereby the structure was greatly damaged. It was immediately followed by the great fire, which, on the next day, completely destroyed the building. The architect had not then made a certificate that the fifth installment had been earned by the finishing of the work therein specified and was due and payable. About thirty days afterward the plaintiff demanded that the architect issue the certificate as required by the contract, and also demanded of the defendants payment of said sum of two thousand five hundred dollars. The architect refused to give the certificate and the defendants refused to pay the installment.

The effect of the fifth clause of the contract, taken alone, and with respect to the conditions of payment, may best be shown by paraphrasing its provisions so as to connect those which relate to the fifth installment, thus:‘ The owner agrees, in consideration of the performance of this agreement by the *31 contractor, to pay to said contractor $23,763.00, at times and in the manner following: Fifth:—$2500, when the plastering and outside mill work is finished, provided, that when each installment shall become due, a certificate in writing shall be obtained from said architect, stating that the installment is due and the amount then due.” The second clause provided that the contractor was to do the work “under the direction and supervision and subject to the approval of said architect.”

Upon such a contract there could be no doubt that the certificate of the architect must be given before the installment becomes presently payable and before any right of action therefor accrues. (Coplew v. Durand, 153 Cal. 279, [16 L. R. A. (N. S.) 791, 95 Pac. 38], and cases cited.) If there were no other provision in the contract the plaintiff could not recover.

The complaint does not allege that the parties, after the fire, mutually abandoned the contract, so far as reconstruction of the building is concerned. The evidence indicates that they did, but in the absence of an allegation, such abandonment, if it occurred, cannot be made the foundation of a recovery by plaintiff.

The general rules governing the rights of the parties to a building contract, where the building to be erected is partially constructed and is destroyed by fire before full completion, in cases where the contract is entire and contains no express provisions regarding their rights in that contingency, are not seriously controverted. If, in such a case, the parties do not rescind or abandon, but stand upon the contract, it controls their rights. The contractor and the owner each must perform his part of the contract. If the whole price is due upon completion, the contractor must complete it before he can lawfully demand payment. If it is payable in installments during the progress of the work, he cannot recover an installment earned but not paid at the time of the fire, until the reconstruction has proceeded to the stage necessary to make it due. He must stand the loss resulting from the fire and must replace at his own expense the structure that is destroyed. When he has done so, he may recover the full contract price. He is not excused from completing the performance of the contract by the fact that the fire has destroyed the structure already made. It is nevertheless *32 possible for him to begin again and rebuild the entire building. Such destruction does not prevent performance within the meaning of section 1511 of the Civil Code. (Wilmington T. Co. v. O’Neil, 98 Cal. 5, [32 Pac. 705]; Barrere v. Somps, 113 Cal. 97, 104, [45 Pac. 177, 572] ; Sample v. Fresno Flume etc. Co., 129 Cal. 222, 228, [61 Pac. 1085] ; Wilson v. Alcatraz eta. Co., 142 Cal. 182, [75 Pac. 787]; Polack v. Pioche, 35 Cal. 416, 422, [95 Am. Dec. 115]; 30 Am. & Eng. Ency. of Law, 1249; Civ. Code, sec. 1439.) There are cases which hold that upon such a contract if the contractor neglects to complete the performance after such destruction, the owner may recover from him the installments which had been paid prior to the destruction. (Green v. Wells, 2 Cal. 584; Tompkins v. Dudley, 25 N. Y. 272, [82 Am. Dec. 349].)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

No.
Colorado Attorney General Reports, 1975
Kennedy v. Reece
225 Cal. App. 2d 717 (California Court of Appeal, 1964)
Patrick J. Ruane, Inc. v. Parker
185 Cal. App. 2d 488 (California Court of Appeal, 1960)
Creith Lumber, Inc. v. Cummins
163 Ohio St. (N.S.) 264 (Ohio Supreme Court, 1955)
Bank of America v. Engleman
225 P.2d 597 (California Court of Appeal, 1950)
People v. Buckles
134 P.2d 8 (California Court of Appeal, 1943)
Berylwood Investment Co. v. Graham
111 P.2d 467 (California Court of Appeal, 1941)
Gelgud v. Los Angeles Rock & Gravel Co.
58 P.2d 673 (California Court of Appeal, 1936)
Orr v. Forde
282 P. 429 (California Court of Appeal, 1929)
Caldwell v. Western Development Co.
203 P. 158 (California Court of Appeal, 1921)
Realty & Rebuilding Co. v. Rea
194 P. 1024 (California Supreme Court, 1920)
Hamer v. Ellis
180 P. 30 (California Court of Appeal, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
158 P. 748, 173 Cal. 27, 1916 Cal. LEXIS 354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ahlgren-v-walsh-cal-1916.