Hansen v. Andersen

71 N.W.2d 921, 246 Iowa 1310
CourtSupreme Court of Iowa
DecidedSeptember 20, 1955
Docket48717
StatusPublished
Cited by5 cases

This text of 71 N.W.2d 921 (Hansen v. Andersen) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hansen v. Andersen, 71 N.W.2d 921, 246 Iowa 1310 (iowa 1955).

Opinions

Wennerstrum, J.

Plaintiff’s action is for damages claimed to have resulted because the defendant, a building contractor, failed to construct a granary in accordance with the original plans and specifications, as claimed to have been agreed upon by the parties. Upon submission to a jury of the several issues involved a verdict Avas returned for the plaintiff. The defendant filed a motion for judgment notwithstanding verdict and, in the alternative, a motion for new trial. Honorable M. H. Kepler, the trial judge, became ill shortly thereafter and subsequently died. He did not rule on the motions. At a later date these respective motions were submitted to the Honorable William P. Butler, one of the judges of the Twelfth Judicial District. Rule 367, R. C. P. He overruled the motions as presented. From the judgment and the ruling on the several motions the defendant has appealed.

The plaintiff OAvns and operates a 280-aere farm in Cerro Gordo County, Iowa. During March of 1951 he conferred with the defendant relative to the building of a granary. Plaintiff contemplated the construction of a building similar to plans furnished by a company which makes and sells elevators for installation in such buildings. He, however, informed the defendant he desired to have the building built 8 feet longer than was contemplated in the plans and 2 feet wider. The proposed building as then contemplated would be 40 feet long and 29 feet wide, with a 13-foot driveway instead of an 11-foot driveway, as provided for by the original plans. Prior to the commencement of the Avork the plaintiff and the defendant dis[1312]*1312cussed the effect of the extra two feet in the width of the building and the matter of compensating for the increased width in connection with the general plans for it. The structure was completed late in July 1951. Although there was some complaint to the defendant about matters other than those which were the basis of the suit, the plaintiff paid the defendant for his services and those of his employees on November 8, 1951. At that time the plaintiff made no comment relative to the manner in which the building had been constructed, the length of the rafters, and the place and elevation of the chutes.

During November 1951 the plaintiff began the hauling of the crop of corn for that year to the bins. Trouble developed, however, in getting the corn to slide down the chutes and in particular to the bins at the end of the building. At that time it was observed by the plaintiff the cribs did not appear to hold as many bushels of corn as was contemplated. Later the plaintiff measured the attic height and it was discovered there were only 6 feet of attic space while the plans called for 7 feet of such space. This 7-foot height was necessary for the chutes to function properly. It was also observed the lower rafters of the hip roof were 12 feet 7 inches in length while the plans called for rafters 14 feet in length. This shortening of the rafter length resulted in a loss of bin capacity of 800 bushels of corn and a loss of 300 bushels in the cribs or a total loss of capacity in the building of 1100 bushels of corn.

There is some evidence that before the rafters were erected, the length of which is complained of, the plaintiff and the defendant and a foreman for the defendant discussed the pitch of the roof and the necessary length of the rafters. There was some experimentation on the ground relative to the proposed pitch of the roof and the necessary length of the rafters. The defendant maintains that at no time did the plaintiff complain to him of any defects in the construction and the first he knew of any objections was when he received a letter from the plaintiff’s attorney.

The plaintiff claims as a basis for his action in damages (1) the completed building had a 6-foot attic instead of a 7-foot attic as provided for in the plans and specifications; (2) unnecessary lumber was put into the building by the defendant; [1313]*1313(3) the shortening of the length of. the lower rafters of 'the hip roof from 14 feet to 12 feet 7 inches and the upper rafters from, 10 feet to 9 feet 9 inches resulted in the capacity of the cribs being lessened by 1100 bushels. The defendant asserted as a defense (1) a denial of a failure to build in accordance with the contract, and (2) plaintiff is estopped from prosecuting this action inasmuch as he observed the manner in which the crib was being constructed and approved the same and thereafter paid for the work done by the defendant.

It is the claim of the defendant that the trial court should have directed a verdict in his favor at the close of all the evidence in that (1) the plaintiff had failed to prove the proper measure of damages; (2) he had failed to show a definite contract between the plaintiff and the defendant; (3) the plaintiff had waived any breach by approving the manner of construction of the building and thereafter, with knowledge of the claimed defects, had paid the defendant; (4) the testimony on behalf of the plaintiff was inconsistent with the physical facts and is not entitled to be relied upon.

The trial court submitted three items of damage to the jury. They were: (1) The use of an excessive amount of lumber at a cost of $65.25; (2) lowering the attic of the building in order to make it 7 feet at a cost of $216.35; (3) the proposed rebuilding of roof in a manner so as to comply with the plans and specifications at'a cost of $1805.

Involved in a consideration of the trial court’s claimed errors was the admission of the testimony of a different contractor, who, over the objections that the witness’ answers would be immaterial and would not show a proper measure of damages, gave an estimate of the cost of changing the corncrib 'by raising the lower rafters and making them longer, thereby increasing the capacity.

Damages were also sought to be proved in the amount of $216.35 by the testimony of William Walker who stated he cut 12 inches off the bin tops so as to make the space in the attic 7 feet instead of 6 feet. Damages in the amount of $65.25 for the use of excessive and unnecessary lumber were Shown by.the testimony of the plaintiff.

[1314]*1314It is shown by the evidence the defendant was to be compensated for his work on a cost pins basis of 10% and his actual compensation as so computed was $683.52. It should be here noted that the plaintiff has not, according to the evidence, made any of the changes he claims are necessary in connection with the rebuilding of the roof and is continuing to use the building as constructed.

I. The trial court, in the submission of the case to the jury, necessarily held there was a building contract for which the defendant could be held liable other than as originally contemplated. If it can be considered there was such a contract and the case was properly submitted to the jury the question arises whether the trial court committed error in receiving evidence bearing on the cost of making the necessary changes to comply with the claimed contract. It is contended the plaintiff did not submit testimony bearing on the proper measure of damages. It is also maintained the court committed error in giving the instruction it did relative to the measure of damages. These claimed errors involve the submitted item of damage of $1805. Consequently we must consider the applicable rule in determining what is, under the facts in this case, the proper measure of damages.

In 9' Am.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Busker v. Sokolowski
203 N.W.2d 301 (Supreme Court of Iowa, 1972)
Walker Manufacturing Co. v. Henkel Construction Co.
346 F. Supp. 621 (N.D. Iowa, 1972)
Conrad v. Dorweiler
189 N.W.2d 537 (Supreme Court of Iowa, 1971)
Shell v. Schmidt
330 P.2d 817 (California Court of Appeal, 1958)
Hansen v. Andersen
71 N.W.2d 921 (Supreme Court of Iowa, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
71 N.W.2d 921, 246 Iowa 1310, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hansen-v-andersen-iowa-1955.