Tolstoy Constructor Co. v. Minter

78 Cal. App. 3d 665, 143 Cal. Rptr. 570, 1978 Cal. App. LEXIS 1339
CourtCalifornia Court of Appeal
DecidedFebruary 7, 1978
DocketCiv. 50391
StatusPublished
Cited by5 cases

This text of 78 Cal. App. 3d 665 (Tolstoy Constructor Co. v. Minter) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tolstoy Constructor Co. v. Minter, 78 Cal. App. 3d 665, 143 Cal. Rptr. 570, 1978 Cal. App. LEXIS 1339 (Cal. Ct. App. 1978).

Opinion

*668 Opinion

JEFFERSON (Bernard), J.

This case involves a suit for breach of a contract to build a residence. Plaintiff Tolstoy Construction Company sought $7,301.16 in damages and requested attorney fees from the residence’s owner, Mamie R. Minter. Defendant Minter answered the complaint, denying liability on the ground that plaintiff had failed to perform the contract in a substantial and workmanlike manner. Defendant also cross-complained for damages of $25,000 for plaintiff’s breach of the same contract and $5,000 for plaintiff’s breach of a second contract between the parties.

Trial was by the court. Judgment was granted to plaintiff in the amount of $5,000 as damages and $550 for attorney’s fees. Defendant was denied relief on her cross-complaint. Defendant has appealed from the judgment.

Defendant attacks the sufficiency of the evidence to support the judgment. The appropriate standard of review in assessing such an attack is to “view the facts in the light most favorable to [the prevailing party below], giving [that party] the benefit of every reasonable inference and resolving all conflicts in [that party’s] favor . . . .” (Horn v. General Motors Corp. (1976) 17 Cal.3d 359, 367 [131 Cal.Rptr. 78, 551 P.2d 398].) “A reviewing court must uphold an award of damages whenever possible [citation] and all presumptions are in favor of the judgment [citations].” (Bertero v. National General Corp. (1974) 13 Cal.3d 43, 61 [118 Cal.Rptr. 184, 529 P.2d 608, 65 A.L.R.3d 878].)

With these principles in mind, we review the evidence adduced below.

Defendant owned an antique shop in Montebello, and, in 1973, was referred by a real estate agent to Jack J. Tolstoy, a licensed building contractor doing business as plaintiff company, concerning the construction of a residential unit on top of the antique shop where defendant would live. Tolstoy drew some tentative plans for the residence and discussed them with defendant. The plans were not complete; they did not show the location of electrical outlets or the water supply for the residential unit. Nor did they show that it would be necessary, in order to construct the staircase to the upper unit, to remove and relocate the water heater servicing the antique shop on the first floor.

*669 Defendant asked for some changes, but basically approved the plans submitted to her. She was told that the changes would be incorporated in the plans to be submitted to the Montebello Building Department (hereinafter, the Department).

On April 26, 1973, plaintiff company, by Jack J. Tolstoy, and defendant signed a document which had been prepared by Tolstoy entitled “Prime Construction Contract.” It, too, was devoid of details of the proposed construction, providing only that plaintiff would build for defendant a 2-bedroom apartment of approximately 1,100 square feet on top of the rear of the antique shop, “per plans submitted.” Total price was to be $21,500, of which $250 was payable upon execution of the agreement. No provision was made for installment payments, but extras and allowances were defined. Performance was to be completed within 125 days from the time defendant notified the contractor that the building site was available.

After the contract was signed, an amended set of plans, drawn by Bill, Jack J. Tolstoy’s son, was submitted to the Department. The plans showed one change defendant had requested (relative to bedroom size) but not the other (inclusion of a broom closet). Defendant did not see these plans. The Department directed some additional changes, including the construction of a carport, because the local code required a carport when the property use was to be mixed commercial-residential. The building permit was issued June 8, 1973, and construction began.

On June 29, 1973, defendant was presented with a letter by Tolstoy outlining the installment payments required during the course of construction. Defendant did not assent to this payment schedule either orally or in writing, but did make four timely installment payments pursuant to the letter’s timetable during the summer of 1973.

Various difficulties were encountered. The problem of the water heater was discussed by the parties and it was decided to place it in the upper unit’s second bathroom, although the contractor knew that a gas-fueled water heater standing open in the bathroom violated the local building code. The carport, built in August 1973, had to be moved; defendant asked that it be expanded so that it would abut the adjoining property, which she owned. This direction was not followed; a four and one-half-foot gap was left between the carport and the adjoining property. Appliances promised by the contractor did not materialize; defendant purchased them herself.

*670 The antique shop was painted barn red, and it was defendant’s instruction to plaintiff to have the stucco addition match the lower unit in color. There was something wrong with the paint used; it streaked. Tolstoy testified that he attempted to remedy the condition. There was testimony at trial from other witnesses that paint continued to come off the walls on the hands of anyone who touched the walls.

The job was essentially completed in October 1973. In mid-November 1973 there was a heavy rain and water flooded the antique shop, coming from the ceiling at the shop’s rear, through a light fixture. (The residence was located above this point.) One of plaintiff’s employees, Bill Tolstoy, arrived and attempted to patch the ruptures. There was general agreement among the witnesses called at trial by defendant, a roofing contractor and a general contractor, that the area of difficulty was where the new construction joined the old, and that to solve the problem of water collecting on the building reconstruction would be required (ranging in price from $600 to $900). The mid-November rains did some damage to defendant’s merchandise in the shop.

Defendant moved into the upstairs unit in November 1973. Department Inspector Patterson testified at trial that a certificate of occupancy was not issued for the unit, due to the open condition of the water heater. Defendant was not satisfied with the residence, and on December 28, 1973, refused to pay the fifth installment payment set forth in the schedule prepared by Tolstoy.

In January 1974, after plaintiff had refused to work further because of lack of payment, defendant contacted the Contractor’s State License Board, seeking their assistance. A representative of that board met with contractor Tolstoy and defendant. The result of that meeting was that the contractor was provided with a list of defendant’s complaints, but it appears that no corrections were attempted after that meeting.

The list was introduced at trial. In addition to the problems already encountered by defendant, these conditions were noted: areas of wood left unpainted; nailheads showing throughout the construction; no insulation; misaligned doors, windows and light switches; cracks in kitchen tile and around doors; chipped tile in bathrooms, and no light switch at all in one bathroom.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MURRAY'S IRON WORKS, INC. v. Boyce
71 Cal. Rptr. 3d 317 (California Court of Appeal, 2008)
Rrx Industries, Inc. v. Lab-Con, Inc.
772 F.2d 543 (Ninth Circuit, 1985)
Charles River Construction Co. v. Kirksey
480 N.E.2d 315 (Massachusetts Appeals Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
78 Cal. App. 3d 665, 143 Cal. Rptr. 570, 1978 Cal. App. LEXIS 1339, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tolstoy-constructor-co-v-minter-calctapp-1978.