Larry J. Kudsk v. Federal Solutions Group, Inc.

District Court, C.D. California·Decided September 16, 2020·No. 2:19-cv-00389·Unknown

Opinion

LARRY J. KUDSK, Case No. 2:19-cv-00389-GJS

Plaintiff MEMORANDUM OPINION AND ORDER v.

FEDERAL SOLUTIONS GROUP, INC. et al, Defendant.

INTRODUCTION This case arises out of various claims by and between Larry J. Kudsk dba Larry Kudsk Construction Services (“Kudsk”), The Vertex Companies, Inc. (“Vertex”) and Fidelity and Deposit Company of Maryland (“F&D”) concerning certain government construction projects. The claims before the Court, described below, were tried from December 10 to 12, 2019. Plaintiff filed a Motion for Judgement as a Matter of Law on the last day of trial [Dkt. 70], which the Court heard on February 5, 2020. [Dkt. 84.] Plaintiff’s motion was denied on March 30, 2020. [Dkt. 89.] The parties thereafter filed post-trial briefing addressing the claims and counterclaim tried to the Court, the timing of which was impacted by the availability proceedings. After further delay caused by the impact the COVID 19 pandemic has had on the Court and all civil litigants, the trial issues stand ready for decision. The parties do not dispute the basic background facts in this case, i.e., the situation that led up to the execution of the contracts into which they entered in 2017 and 2018. The Court will therefore only briefly summarize the parties’ history together and what led to the disputes that remained when trial in this matter began. Where more detail is required, or where the parties disputed a material fact that the Court decides herein, such detail will be set forth in the appropriate section below. This action is the remainder of two consolidated cases, one of which was originally brought in the Northern District of California. The Northern District case involved the “Moffett Field project,” for which Kudsk was the roofing subcontractor. An entity known as BARA was the prime contractor. The Northern District case was transferred to this District on July 2, 2019, and defendant BARA was dismissed. Only Kudsk and F&D remain parties to the Moffett Field claims. As set forth below, the only remaining Moffett Field issue is how much is owed to Kudsk under the Miller Act, as Kudsk properly completed the work that he was obligated to do based on the original contract with BARA for this project. The case brought here in the Central District concerns two projects, the “HVAC” and “Fire Alarm” projects, both of which were construction projects located at Vandenberg Air Force Base and are described further below. The parties generally involved in those claims and counterclaims are Kudsk, F&D, and Vertex. The prior general contractor in the Vandenberg related claims was Federal Solutions Group (“FSG”). FSG and BARA – neither of which is a party in the claims before the Court – were related entities, both owned by the same individual. Neither FSG nor BARA remain in business. Like BARA, FSG has also been dismissed without The vast majority of the time spent at trial was devoted to the Vandenberg HVAC Project disputes. Kudsk sued both Vertex and F&D claiming breach of contract associated with the Vandenberg HVAC Project Subcontract Agreement and Ratification Agreement. Kudsk also sued F&D in a claim for compensation under the Miller Act payment bond. Vertex did not file a counterclaim against Kudsk on the Vandenberg HVAC Project, but F&D contends that it is a third-party beneficiary under the Subcontract Agreement and has sued Kudsk for breach of the Subcontract Agreement. For the HVAC project, in summary form, Kudsk seeks: damages for (1) the unpaid Subcontract Balance, (2) extra work claims, and (3) extended field overhead based on work delays Kudsk encountered that were caused, according to Kudsk, by Vertex and the customer, i.e., the Air Force. F&D, as an alleged third-party beneficiary, contends that Kudsk abandoned the work required under the Subcontract and is thus entitled to no recovery for the work performed (beyond amounts already paid). F&D also countersues Kudsk for its alleged increased costs of completing the work. With respect to the Fire Alarm project, there were five different projects – different physical areas – that were part of the original contract between the government and the original contractor for which F&D was the surety. The work on four of those projects was completed before the default of the original contractor. At issue with those four projects are Kudsk’s claim that Kudsk is entitled to compensation for standing ready to complete any warranty work (although none was required), since warranty work was part of the original contract that F&D was required, as surety, to see to completion for the government. Work never began on the fifth and final fire alarm project, located at the Vandenberg Temporary Living Facility (“TLF”). The primary issue here is whether Kudsk is entitled to (1) compensation for the preparatory work he did in an attempt to make on this project even though he never received a Notice to Proceed and the TLF fire alarm project was never started, let alone completed. Kudsk essentially claims that Vertex had a duty under the subcontract to secure and approve a Notice to Proceed from the Air Force, for Kudsk’s benefit, in a timely manner yet failed to do so. The parties marked in excess of 250 trial exhibits on these issues. At trial, the exhibits were marked by project. Exhibits related to the Moffett Field related claim were marked with an “MF” prefix, those related to the Vandenberg HVAC project were marked with an “HVAC” prefix, and those related to the various fire alarm projects were marked with an “FA” prefix.1 The parties submitted declarations from the following witnesses which served as their direct testimony: Larry J. Kudsk, Samuel Reed, Paul Grego, and Alex Belooussov. The following witnesses appeared live for further examination: Kudsk, Reed, and Belooussov (Plaintiff chose not to cross examine Grego). The parties filed written objections to these declarations, on which the Court ruled at trial. The parties also stipulated that the Court could consider hearsay statements made by a BARA representative and one of Kudsk’s subcontractors, although they later disputed the extent of their stipulation (i.e., for what purposes the Court could consider the out of court statements). The Court notes that it did not rely on statements made by any witness who were not present or on-call for trial for the truth of the matter asserted in such statement in making the findings set forth in this Order. Certain other witnesses who had been identified in the parties’ joint witness list, including a representative of the Air Force, were not called at trial. Based on the evidence and argument adduced at trial as well as consideration

Free access — add to your briefcase to read the full text and ask questions with AI

Larry J. Kudsk v. Federal Solutions Group, Inc., (C.D. Cal. 2020).

Larry J. Kudsk v. Federal Solutions Group, Inc. (Larry J. Kudsk v. Federal Solutions Group, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States Ex Rel. Sherman v. Carter Constr. Co.
353 U.S. 210 (Supreme Court, 1957)
Tolstoy Constructor Co. v. Minter
78 Cal. App. 3d 665 (California Court of Appeal, 1978)