Larry J. Kudsk v. Federal Solutions Group, Inc.

CourtDistrict Court, C.D. California
DecidedSeptember 16, 2020
Docket2:19-cv-00389
StatusUnknown

This text of Larry J. Kudsk v. Federal Solutions Group, Inc. (Larry J. Kudsk v. Federal Solutions Group, Inc.) is published on Counsel Stack Legal Research, covering District Court, C.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Larry J. Kudsk v. Federal Solutions Group, Inc., (C.D. Cal. 2020).

Opinion

1 2 3 4 5 6 7 8 UNITED STATES DISTRICT COURT 9 CENTRAL DISTRICT OF CALIFORNIA 10 11 LARRY J. KUDSK, Case No. 2:19-cv-00389-GJS

12 Plaintiff MEMORANDUM OPINION AND ORDER 13 v.

14 FEDERAL SOLUTIONS GROUP, INC. et al, 15 Defendant.

17 INTRODUCTION 18 This case arises out of various claims by and between Larry J. Kudsk dba 19 Larry Kudsk Construction Services (“Kudsk”), The Vertex Companies, Inc. 20 (“Vertex”) and Fidelity and Deposit Company of Maryland (“F&D”) concerning 21 certain government construction projects. The claims before the Court, described 22 below, were tried from December 10 to 12, 2019. Plaintiff filed a Motion for 23 Judgement as a Matter of Law on the last day of trial [Dkt. 70], which the Court 24 heard on February 5, 2020. [Dkt. 84.] Plaintiff’s motion was denied on March 30, 25 2020. [Dkt. 89.] 26 The parties thereafter filed post-trial briefing addressing the claims and 27 counterclaim tried to the Court, the timing of which was impacted by the availability 28 1 2 proceedings. After further delay caused by the impact the COVID 19 pandemic has 3 had on the Court and all civil litigants, the trial issues stand ready for decision. 4 5 SUMMARY OF CLAIMS AND DECISION 6 The parties do not dispute the basic background facts in this case, i.e., the 7 situation that led up to the execution of the contracts into which they entered in 2017 8 and 2018. The Court will therefore only briefly summarize the parties’ history 9 together and what led to the disputes that remained when trial in this matter began. 10 Where more detail is required, or where the parties disputed a material fact that the 11 Court decides herein, such detail will be set forth in the appropriate section below. 12 This action is the remainder of two consolidated cases, one of which was 13 originally brought in the Northern District of California. The Northern District case 14 involved the “Moffett Field project,” for which Kudsk was the roofing 15 subcontractor. An entity known as BARA was the prime contractor. The Northern 16 District case was transferred to this District on July 2, 2019, and defendant BARA 17 was dismissed. Only Kudsk and F&D remain parties to the Moffett Field claims. 18 As set forth below, the only remaining Moffett Field issue is how much is owed to 19 Kudsk under the Miller Act, as Kudsk properly completed the work that he was 20 obligated to do based on the original contract with BARA for this project. 21 The case brought here in the Central District concerns two projects, the 22 “HVAC” and “Fire Alarm” projects, both of which were construction projects 23 located at Vandenberg Air Force Base and are described further below. The parties 24 generally involved in those claims and counterclaims are Kudsk, F&D, and Vertex. 25 The prior general contractor in the Vandenberg related claims was Federal Solutions 26 Group (“FSG”). FSG and BARA – neither of which is a party in the claims before 27 the Court – were related entities, both owned by the same individual. Neither FSG 28 nor BARA remain in business. Like BARA, FSG has also been dismissed without 1 2 The vast majority of the time spent at trial was devoted to the Vandenberg 3 HVAC Project disputes. Kudsk sued both Vertex and F&D claiming breach of 4 contract associated with the Vandenberg HVAC Project Subcontract Agreement and 5 Ratification Agreement. Kudsk also sued F&D in a claim for compensation under 6 the Miller Act payment bond. Vertex did not file a counterclaim against Kudsk on 7 the Vandenberg HVAC Project, but F&D contends that it is a third-party beneficiary 8 under the Subcontract Agreement and has sued Kudsk for breach of the Subcontract 9 Agreement. 10 For the HVAC project, in summary form, Kudsk seeks: damages for (1) the 11 unpaid Subcontract Balance, (2) extra work claims, and (3) extended field overhead 12 based on work delays Kudsk encountered that were caused, according to Kudsk, by 13 Vertex and the customer, i.e., the Air Force. 14 F&D, as an alleged third-party beneficiary, contends that Kudsk abandoned 15 the work required under the Subcontract and is thus entitled to no recovery for the 16 work performed (beyond amounts already paid). F&D also countersues Kudsk for 17 its alleged increased costs of completing the work. 18 With respect to the Fire Alarm project, there were five different projects – 19 different physical areas – that were part of the original contract between the 20 government and the original contractor for which F&D was the surety. The work on 21 four of those projects was completed before the default of the original contractor. 22 At issue with those four projects are Kudsk’s claim that Kudsk is entitled to 23 compensation for standing ready to complete any warranty work (although none was 24 required), since warranty work was part of the original contract that F&D was 25 required, as surety, to see to completion for the government. 26 Work never began on the fifth and final fire alarm project, located at the 27 Vandenberg Temporary Living Facility (“TLF”). The primary issue here is whether 28 Kudsk is entitled to (1) compensation for the preparatory work he did in an attempt 1 2 to make on this project even though he never received a Notice to Proceed and the 3 TLF fire alarm project was never started, let alone completed. Kudsk essentially 4 claims that Vertex had a duty under the subcontract to secure and approve a Notice 5 to Proceed from the Air Force, for Kudsk’s benefit, in a timely manner yet failed to 6 do so. 7 The parties marked in excess of 250 trial exhibits on these issues. At trial, the 8 exhibits were marked by project. Exhibits related to the Moffett Field related claim 9 were marked with an “MF” prefix, those related to the Vandenberg HVAC project 10 were marked with an “HVAC” prefix, and those related to the various fire alarm 11 projects were marked with an “FA” prefix.1 12 The parties submitted declarations from the following witnesses which served 13 as their direct testimony: Larry J. Kudsk, Samuel Reed, Paul Grego, and Alex 14 Belooussov. The following witnesses appeared live for further examination: 15 Kudsk, Reed, and Belooussov (Plaintiff chose not to cross examine Grego). The 16 parties filed written objections to these declarations, on which the Court ruled at 17 trial. The parties also stipulated that the Court could consider hearsay statements 18 made by a BARA representative and one of Kudsk’s subcontractors, although they 19 later disputed the extent of their stipulation (i.e., for what purposes the Court could 20 consider the out of court statements). The Court notes that it did not rely on 21 statements made by any witness who were not present or on-call for trial for the 22 truth of the matter asserted in such statement in making the findings set forth in this 23 Order. Certain other witnesses who had been identified in the parties’ joint witness 24 list, including a representative of the Air Force, were not called at trial. 25 Based on the evidence and argument adduced at trial as well as consideration 26

27 1 Exhibits are therefore referenced by prefix and exhibit number. For example, HVAC exhibit number 4 would be referenced as “HVAC 4,” Moffett Field exhibit 2 28 would be “MF 2,” etc. 1 2 1. On the Moffett Field Project, Kudsk is entitled to damages in the amount 3 of $93,190.50. 4 2. On the Vandenberg HVAC project: 5 a. Kudsk substantially completed the work required under the 6 subcontract. To the extent that certain work was not completed 7 within the time parameters set by the Subcontract Agreement, 8 Kudsk was prevented from completing such work or obtaining 9 necessary extensions because of Vertex’s breach of the Subcontract 10 Agreement’s payment provisions. 11 b. Kudsk is entitled to damages in the amount of $236,910.89.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Sherman v. Carter Constr. Co.
353 U.S. 210 (Supreme Court, 1957)
Tolstoy Constructor Co. v. Minter
78 Cal. App. 3d 665 (California Court of Appeal, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
Larry J. Kudsk v. Federal Solutions Group, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/larry-j-kudsk-v-federal-solutions-group-inc-cacd-2020.